Funds available, deadline expired, contractor's inefficacy delays project
Satwari- Kunjwani road widening project
7/28/2016 11:31:21 PM

G S Asgotra

Early Times Report

Jammu, July 28 Widening of busy Satwari Kunjwani road is reportedly being delayed not for want of funds but owing to inefficiency of the contractor while R&B department has not initiated any action warranted under rules against the erring contactor for the reasons best known to officers. Sources informed Early Times that usually development projects of government get delayed due to paucity of funds, astoundingly, Public Works Department has sufficient funds available for the completion of Satwari to Kunjwani road widening project but the contractor, executing construction of subways, has failed to complete them, after lapse of more than one year, since the expiry of deadline, fixed by department for the same.
Giving details about the project, sources in PWD department said that the department had planned to construct three subways in between Satwari to Kunjwani stretch. "One subway is already completed near Digiana Gurudwara and the second subway is to be constructed near Gangyal industrial chowk", sources said, adding that the construction work of three subways was started under Phase-II in 2013 and proposed date of completion was March 2015 but due to inefficiency of the contractor, only one subway is completed and other still in oblivion while third one is yet to take off.
"The callous approach of the department concerned can be gauged from this fact that after lapse of 16 months, rather than imposing penalty on contractor over delaying construction of subways, the department has obliged him, because of his close proximity in corridors of power", said a retired engineer.
"Everyone knows that the contractor is reportedly a partner of Former Minister and now also has made close relations with incumbent ministers, therefore the officials of PWD hesitate to initiate any action against the contractor", the engineer added.
Executive Engineer of Division Gandhi Nagar, Mohammed Abdullah said that there was no scarcity of funds but there were some minor glitches for the delay in the project. "Soon we will solve the issues and will hopefully complete the project in this financial year", he said.
  Share This News with Your Friends on Social Network  
  Comment on this Story  
 
 
 
Early Times Android App
STOCK UPDATE
  
BSE Sensex
NSE Nifty
 
CRICKET UPDATE
 
 
 
 
 
 
 
 
   
Home About Us Top Stories Local News National News Sports News Opinion Editorial ET Cetra Advertise with Us ET E-paper
 
 
J&K RELATED WEBSITES
J&K Govt. Official website
Jammu Kashmir Tourism
JKTDC
Mata Vaishnodevi Shrine Board
Shri Amarnath Ji Shrine Board
Shri Shiv Khori Shrine Board
UTILITY
Train Enquiry
IRCTC
Matavaishnodevi
BSNL
Jammu Kashmir Bank
State Bank of India
PUBLIC INTEREST
Passport Department
Income Tax Department
JK CAMPA
JK GAD
IT Education
Web Site Design Services
EDUCATION
Jammu University
Jammu University Results
JKBOSE
Kashmir University
IGNOU Jammu Center
SMVDU