Breaking News :   Lok Sabha polls: World’s biggest electoral exercise begins in India, over 62% turnout in phase-1 | Newlyweds queue up to cast votes | Udhampur witnesses 65.08 % polling, figures likely to go up | Returning officer stands in queue to cast his vote | Voters of 'silent hamlet' cast ballots for basic amenities | Inclement weather, rain spells dampen spirits | KP body lauds EC for scrapping ‘Form M’, urges community to vote in large numbers | PM Modi led Govt will never touch reservation policy: Amit Shah | Traditional boundaries getting blurred: IAF Chief | 25 candidates minus BJP file nomination papers from Anantnag-Rajouri LS seat | Specially-abled persons are real heroes: DC Jammu to Deaf Cricketers | Jan Ashuadi Stores | INDIA Bloc leaders resorting to politics of abuse, intimidation: BJP | PM Modi ends dynastic politics, paves way for transparent governance in J&K: Sham Langer | Report of 'Industrial Visit to TVS Motors and Signum Electro Pvt Ltd' organized by ECE and HSS department on 11 April 2024 | Rainy weather to continue for 2nd day in Kashmir | Two held for killing man in broad daylight | BJP banks on Modi, uses social media to win voters | Mamata responsible for violence on Ram Navami in Bengal: Malviya | Congress standing by Naxals for votes: BJP | NHRC directs J&K Chief Secy to deal issue of slain poet's family with 'Humane Approach' | NC, PDP, Cong no match to BJP in J&K: Kavinder | KU to promote voter education, awareness through campus activities | Not to contest polls from Kashmir was party's decision: Azad | Sajad ridicules Omar for good, bad politics | At least 80 Naxals killed, 125 arrested, 150 surrendered since January in Chhattisgarh | DRDO successfully conducts flight test of desi cruise missile | Infosys profit jumps 30 per cent to Rs 7,969 crore in Q4 | Congress has not shed its mindset of imposing emergency: PM Modi | Gulam Ali continues campaign for Jugal Kishore | Students of School of Civil Engineering, SMVDU presented a paper in a National Conference AEMTA-2024 | NSG Trust organize cloth distribution camp | IIM Jammu's immersion program for NIFTEM MBA students culminates with valedictory ceremony | Samba police reunites missing girl with family | Nine drug peddlers arrested in Kashmir: Police | Lucknow Super Giants face stern home test against quality CSK bowling | Pant mobility will give him and Team India management encouragement: Pietersen | BSI learning, Australia signs MoU with Aryans Group of Colleges | Juventus ordered to pay Ronaldo more than USD 10 million in salary dispute | Real Madrid beats Man City 4-3 on penalties to advance to the Champions League semifinals | Started preparing for freight train called SRH: DC bowling coach James Hopes | Down with hip strain, RCB Maxwell unlikely to play against KKR on Sunday | GCW Bhagwati Nagar organises student seminar | Back Issues  
 
news details
JK ERA imposes penalty of Rs 2 cr on contractor
1/31/2019 11:09:05 PM
Early Times Report

Jammu, Jan 31: The Contractor M/s. Simplex Infrastructure Ltd. (SIL) was again penalized by J&K ERA for skipping the previously agreed timelines of completing Phase - II (Rambagh -Alochibagh stretch) of Rambagh - Jehangir Chowk mega flyover project being implemented under ADB Loan - II. CEO J&K ERA Dr. Raghav Langer, IAS apprised that as per the revised time schedule submitted by SIL, the contractor had to complete the structural portion of Phase - II of the flyover project by 31st December 2018.
However, the same has now got delayed till ending of February 2019 due to sub-optimal manpower, material and machinery deployed by the contractor at the work site.
The CEO said that strict monitoring of milestones for the mega project is being done on a continuous basis and the contractor shall be penalized under relevant sections of contract agreement for delaying the works.
It may be recalled that in the month October 2018 already an initial penalty of Rs. 1.25 crore had been imposed on the contractor by J&K ERA. The CEO J&K ERA has also directed the project staff to impose employer's claims under relevant clauses on the contractor for delays in the project and additional burden being put on the state exchequer on account of salaries of employees and extension of tenure of the Design & Supervision Consultants deployed on the project by Government.
  Share This News with Your Friends on Social Network  
  Comment on this Story  
 
 
 
Early Times Android App
STOCK UPDATE
  
BSE Sensex
NSE Nifty
 
CRICKET UPDATE
 
 
 
 
 
 
 
 
   
Home About Us Top Stories Local News National News Sports News Opinion Editorial ET Cetra Advertise with Us ET E-paper
 
 
J&K RELATED WEBSITES
J&K Govt. Official website
Jammu Kashmir Tourism
JKTDC
Mata Vaishnodevi Shrine Board
Shri Amarnath Ji Shrine Board
Shri Shiv Khori Shrine Board
UTILITY
Train Enquiry
IRCTC
Matavaishnodevi
BSNL
Jammu Kashmir Bank
State Bank of India
PUBLIC INTEREST
Passport Department
Income Tax Department
JK CAMPA
JK GAD
IT Education
Web Site Design Services
EDUCATION
Jammu University
Jammu University Results
JKBOSE
Kashmir University
IGNOU Jammu Center
SMVDU