Breaking News :   Striking Balance | BJP ‘poster-boy’ unlikely to contest as rebel candidate | Candidates worried as Jammu-Reasi seat witnesses dull campaign | Azad hits out at Omar Abdullah | LG Sinha attends Utthan foundation’s symposium on Sanatan culture | Sajjad Lone meets Muzaffar Baig, seeks support to win Bla LS seat | Secular forces in Jammu rally against divisive politics: Sadhotra | Jammu: Over 17.80 lakh voters to decide fate of 22 candidates | DPAP contesting LS elections independently: Azad | Lashkar terrorist behind Govt employee’s killing: Police | ADGP Jammu conducted security review meeting at Reasi | 67 suspects detained | J&K Police urge vigilance against unauthorized social media posts featuring officers | Nitin Gadkari faints while speaking at campaign rally | Emergency procurement powers help Army to modernise itself: General Manoj Pande | 15 flights diverted from Delhi due to bad weather conditions | No action for short deduction of TDS if PAN linked with Aadhaar by May 31 | "Modi's Guarantee Is Global", says S Jaishankar | Encounter underway | Lightest bulletproof jacket | Voting for BJP means supporting patriots who want to establish 'Ram Rajya' in country: Shah | Govt official dismissed | School timing changed | Kavinder pitches for PM Modi's third term to continue India's development trail | DC Kupwara kick-starts plantation drive at PS Wadder Payeen | REC Ltd to extend term loan of Rs 1,869 Crores for Kiru HEP | Auction for Telecom Spectrum to continue, Administrative Allocation Limited: Report | DRI seizes valuables of Rs 10.48 Cr after busting gold smuggling syndicate in Mumbai; 4 held | Border Road Organisation opens Leh-Manali National Highway | Congress, its coalition aiming to loot income, savings, assets: BJP | BJP's communal narrative weakening national unity: Rattan Lal | Health Secretary reviews arrangements for Shri Amarnathji Yatra | Flag march conducted in Samba town ahead of second phase of Parliamentary elections | Medical health check up drive launched in GRP Jammu | DIG Udhampur-Reasi range conducted GELS-24 review meeting cum briefing session | Notorious criminal slapped PSA by police | Police foils bovine smuggling bid, arrests 2 smugglers | Cybercrime investigation unit recovers online defrauded amount | Navi Mumbai cops trace stray dog seen in CCTV footage to crack ragpicker's murder case | Breakthrough in Rajouri attack emerges | 16 chronic drug peddlers booked, lodged in jail | CUJ organizes corporate connect "Parshikshan Pe Samvad" 2024 | GDC Khour organizes an Awareness Lecture | Panchayat Diwas celebrated in National College of Education | Jodhamal organizes ICARUS'24: A Drone War Competition | Govt College for Women, Bhagwati Nagar organizes Quiz Competition | GDC Vijaypur organizes plantation drive | Empowering Adolescents: Addressing substance abuse and mental health | Electoral Literacy Club in collaboration with | YCET's students placed in KodNest Technologies Pvt Ltd | GDC Samba organizes a vibrant and educational Mock Parliament | Back Issues  
 
news details
7 years on, Sudhwala- Sooyian bridge awaits completion, people aghast
7/20/2019 12:36:39 AM
M S Nazki

Early Times Report

POONCH, July 19: Roads and Building (R&B) Department has failed to complete the construction of Sudhwala-Sooyian bridge in Mendhar area of Poonch district even Seven years after its foundation stone was laid.
Missing several deadlines, the construction of the bridge was started in June 2013 at an estimated cost of Rs 54. lakh and was supposed to be completed in March 2015
A group of locals at Sooyian Said that despite passing many deadlines, the government is yet to complete the project making people to face inconvenience of all sorts.
They alleged that the work has been going on at a snail's pace while people continue to suffer and take other routes in the area to commute.
Abdul Rehman Khan , a local at Sooyian said it is a completely a failure of the government. People living in the area extended cooperation to the authorities but they have failed to complete the project within the stipulated time, he said. Another local shopkeeper said it has become a routine for the authorities to initiate a project, construct some pillars or plinth and then abandon it. "It is unfortunate that government always extends deadlines rather than making officials accountable for their failure to complete projects on time," he said. The bridge was to be completed in 2015 but the deadline was extended to 2018. We don't know whom to blame, the locals said.
"A decade has passed since the work on the bridge was started and it is still incomplete. If they don't have funds
  Share This News with Your Friends on Social Network  
  Comment on this Story  
 
 
 
Early Times Android App
STOCK UPDATE
  
BSE Sensex
NSE Nifty
 
CRICKET UPDATE
 
 
 
 
 
 
 
 
   
Home About Us Top Stories Local News National News Sports News Opinion Editorial ET Cetra Advertise with Us ET E-paper
 
 
J&K RELATED WEBSITES
J&K Govt. Official website
Jammu Kashmir Tourism
JKTDC
Mata Vaishnodevi Shrine Board
Shri Amarnath Ji Shrine Board
Shri Shiv Khori Shrine Board
UTILITY
Train Enquiry
IRCTC
Matavaishnodevi
BSNL
Jammu Kashmir Bank
State Bank of India
PUBLIC INTEREST
Passport Department
Income Tax Department
JK CAMPA
JK GAD
IT Education
Web Site Design Services
EDUCATION
Jammu University
Jammu University Results
JKBOSE
Kashmir University
IGNOU Jammu Center
SMVDU