Breaking News :   Programme on 'Maintenance and Welfare of Parents, Senior Citizens Act, 2007' organized at GBHSS, Jammu | KPs take part in Cycling event of 350th martyrdom anniversary of Guru Teg Bahadur ji | Dr Ajaz Wani honoured with prestigious award | DC Bandipora reviews ODOP with Departments | Extension lecture on "Taraqqi Pasand Tehreek aur Urdu Afsana" organized | Jammu District Athletics Championship 2025-26 concludes | Handicrafts Dept to host 3-Day Artisan Carnival at Srinagar from Nov 20 | NR GM inspects Srinagar-Baramulla rail section, reviews passenger amenities | DLSA Srinagar organizes awareness programme on MWPSC Act 2007 at Chanapora | Court denies bail to Manjit Singh in Guru Granth Sahib arson case | Doda police arrest two drug peddlers; 12 grams heroin-like substance recovered | Bhalla demands restoration of statehood, vows to intensify struggle | SP South conducts Darbar at Police Station Bahu Fort to strengthen welfare, discipline of force | Striped Hyenas arriving in Jambu Zoo | Women stepping into roles that were once inaccessible: Sakeena Itoo | Capacity building training programme held | Javed Rana inaugurates, lays foundation stones of key Civic, Tourism projects | Narco-finances hit: Reasi police attach vehicle bought from drug money | Delhi air still 'very poor'; Wazirpur, Bawana record 'severe' AQI | SSP Doda reviews under-investigation UAPA cases and Court Processes with Supervisory Officers & SHOs | Renovation of Kamakhyaguri Railway Station under Amrit Bharat Station Scheme nears completion | RPF rescues 13 tribal minors, including 12 girls at Tatanagar Railway station | J&K BOSE notifies dates for filling of examination forms for Classes 10th , 11th and 12th | NIA arrests second mastermind in just 24 hours | From doctors to professors, terror ecosystem powered by privilege not poverty | Delhi Police summon Al Falah University Chairman | Court sends accused to 10-day NIA custody | Will continue to consider terrorists, their backers alike: Army Chief | Poonch Police announce reward for info on terrorists | DGP, other officers visit Tral meet family of martyr crime photographer | GDC Ramnagar felicitates medal winners of Annual Intercollegiate Sports Championship 2025–26 | International Conference on ‘BIOINNOVATE’ brings at LPU | GCW Bhagwati Nagar organises Career Counselling Session | GGM Science College Jammu concludes two days Workshop on “Virtual Labs” | Miss Asia 2025 Kavya Bali receives Royal welcome at DPS Jammu’s Children’s Day celebration | Awareness Programme on Senior Citizens Maintenance Act held at SPPND GDC Samba | IRCS imparts 3-Day First Aid Training to employees of Biostadt India Ltd, HPCL, Airforce Station, Pidilite Industries Ltd, Kathua | Balbir congratulates Prof Mohtra on his 4th term as State Head of BJP Library, Documentation Deptt | Rising white-collar involvement in terror module alarming: Dr Varinder Sharma | GDC Thannamandi organises Awareness Programme on Drug Abuse under Nasha Mukht Bharat Abhiyan | Director Agriculture Jammu inaugurates 5-Day Internship Programme for School Students | SKUAST Jammu celebrates “Janjatiya Gaurav Varsh Pakhwada” | Bar Association Jammu strongly express its displeasure over Supreme Court judgement in Rajanish K V Vs K Deepa | Back Issues  
 
news details
Supreme Court re-imposes ban on construction in Delhi-NCR, asks states to pay affected workers
11/25/2021 10:23:41 PM
Agencies

New Delhi, Nov 25: Taking note of the worsening air quality, the Supreme Court has re-imposed the ban on construction activities in Delhi and national capital region (NCR) and directed the states to provide subsistence to workers from the funds collected as labour cess for the period during which such activities are prohibited.
A special bench headed by Chief Justice NV Ramana, in an interim order uploaded on Wednesday night, also directed the Commission for Air Quality Management in the NCR and Adjoining Areas to “commission a scientific study of air quality based on available data of previous years bearing upon recorded levels of air pollution”.
“We direct that instead of waiting for the air quality to deteriorate before initiating action under the graded response plan, necessary measures must be put into place in anticipation of a deterioration of air quality.
For this purpose, it is necessary for the commission to engage expert agencies with domain knowledge in meteorological data and statistical modelling,” said the bench which also comprised Justices DY Chandrachud and Surya Kant.
Asking the commission on pollution and NCR states - Delhi, Uttar Pradesh, Haryana, Punjab and Rajasthan - to continue with their measures to curb the spike in pollution, the bench reversed the decision to allow construction activities from November 22 in view of improved ground situation in air pollution level.
“In the meantime, as an interim measure and until further orders, we re-impose the ban on construction activities in the NCR subject to the following two conditions: Non-polluting activities relating to construction such as plumbing work, interior decoration, electrical work and carpentry are allowed to be continued.
“The states shall use the funds which have been collected as labour cess for the welfare of construction workers to provide them subsistence for the period during which construction activities are prohibited and pay wages notified under the Minimum Wages Act for the respective categories of workers,” the order said.
The order took note of the submissions of solicitor general Tushar Mehta, appearing for the Centre, that a plan for graded response has been prepared in pursuance of which measures are identified to be taken progressively on the basis of worsening levels of ambient air pollution.
The bench said as of now, the action is proposed after air quality has deteriorated and directed the commission to take preventive advance measures to deal with the rise in the air pollution.
Asking the panel to undertake a study, the order said such a study “must factor in seasonal variations and other relevant parameters”.
“Once a scientific model is available, which factors in wind velocity as well as natural and man-made phenomena, the graded response plan can be modulated to provide for measures being taken in advance, based on anticipated changes in air quality without waiting for the air quality to deteriorate.
“On this basis, steps can be planned at least a week in advance and even earlier, based on anticipated levels of air pollution in the foreseeable future. The Commission shall carry out the above exercise within a month and report the steps taken for compliance with this direction,” it said.
  Share This News with Your Friends on Social Network  
  Comment on this Story  
 
 
 
Early Times Android App
STOCK UPDATE
 
 
 
 
 
 
 
   
Home About Us Top Stories Local News National News Sports News Opinion Editorial ET Cetra Advertise with Us ET E-paper
 
 
J&K RELATED WEBSITES
J&K Govt. Official website
Jammu Kashmir Tourism
JKTDC
Mata Vaishnodevi Shrine Board
Shri Amarnath Ji Shrine Board
Shri Shiv Khori Shrine Board
UTILITY
Train Enquiry
IRCTC
Matavaishnodevi
BSNL
Jammu Kashmir Bank
State Bank of India
PUBLIC INTEREST
Passport Department
Income Tax Department
JK CAMPA
JK GAD
IT Education
Web Site Design Services
EDUCATION
Jammu University
Jammu University Results
JKBOSE
Kashmir University
IGNOU Jammu Center
SMVDU