Breaking News :   Online radicalisation: Big digital security challenge in New Year | Decorated IPS Officer Mukesh Singh appointed new DGP of Ladakh | LG flags off group of youth for exposure tour | MHA orders major IAS transfers in AGMUT cadre | No Pak objection will be entertained: Khattar | Accused used ‘Ghost’ SIM cards to communicate with Pak handlers | ‘Over 80% psychiatric patients don’t receive timely care’ | NIA files chargesheet against main shooters | Hideout detected in Baramulla | MeT predicts cloudy conditions | Mughal Road opened for limited traffic | Registration process to commence soon | BJP will make Punjab leading state under leadership of PM Narendra Modi: Saini | Raj Kumar Jarmal Nominated as Publicity Secretary of SC Morcha, BJP Udhampur | ZDPC organizes Mahayagya on eve of Magh Mass | District police arrested 02 thieves, recovers stolen property worth Rs 4 lakhs | SKUAST faculty bag top awards | Somnath Swabhiman Parv – A 1000 Years of Unbroken Faith (1026-2026) | Mission YUVA: From Aspiration to Enterprise | Terror and cooperation can’t coexist | A new chapter in the Himalayas: Northern Railway's Jammu Division forges ahead on the path of new achievements | Sindhu festival a symbol of India’s civilizational roots, national unity, says LG Kavinder Gupta | Javid Dar greets people, Sikh Community on Parkash Purb of Sri Guru Gobind Singh Ji | Javed Rana greets people on Guru Gobind Singh Ji’s Jayanti | Javed Rana greets people on Guru Gobind Singh Ji’s Jayanti | Back Issues  
 
news details
Supreme Court re-imposes ban on construction in Delhi-NCR, asks states to pay affected workers
11/25/2021 10:23:41 PM
Agencies

New Delhi, Nov 25: Taking note of the worsening air quality, the Supreme Court has re-imposed the ban on construction activities in Delhi and national capital region (NCR) and directed the states to provide subsistence to workers from the funds collected as labour cess for the period during which such activities are prohibited.
A special bench headed by Chief Justice NV Ramana, in an interim order uploaded on Wednesday night, also directed the Commission for Air Quality Management in the NCR and Adjoining Areas to “commission a scientific study of air quality based on available data of previous years bearing upon recorded levels of air pollution”.
“We direct that instead of waiting for the air quality to deteriorate before initiating action under the graded response plan, necessary measures must be put into place in anticipation of a deterioration of air quality.
For this purpose, it is necessary for the commission to engage expert agencies with domain knowledge in meteorological data and statistical modelling,” said the bench which also comprised Justices DY Chandrachud and Surya Kant.
Asking the commission on pollution and NCR states - Delhi, Uttar Pradesh, Haryana, Punjab and Rajasthan - to continue with their measures to curb the spike in pollution, the bench reversed the decision to allow construction activities from November 22 in view of improved ground situation in air pollution level.
“In the meantime, as an interim measure and until further orders, we re-impose the ban on construction activities in the NCR subject to the following two conditions: Non-polluting activities relating to construction such as plumbing work, interior decoration, electrical work and carpentry are allowed to be continued.
“The states shall use the funds which have been collected as labour cess for the welfare of construction workers to provide them subsistence for the period during which construction activities are prohibited and pay wages notified under the Minimum Wages Act for the respective categories of workers,” the order said.
The order took note of the submissions of solicitor general Tushar Mehta, appearing for the Centre, that a plan for graded response has been prepared in pursuance of which measures are identified to be taken progressively on the basis of worsening levels of ambient air pollution.
The bench said as of now, the action is proposed after air quality has deteriorated and directed the commission to take preventive advance measures to deal with the rise in the air pollution.
Asking the panel to undertake a study, the order said such a study “must factor in seasonal variations and other relevant parameters”.
“Once a scientific model is available, which factors in wind velocity as well as natural and man-made phenomena, the graded response plan can be modulated to provide for measures being taken in advance, based on anticipated changes in air quality without waiting for the air quality to deteriorate.
“On this basis, steps can be planned at least a week in advance and even earlier, based on anticipated levels of air pollution in the foreseeable future. The Commission shall carry out the above exercise within a month and report the steps taken for compliance with this direction,” it said.
  Share This News with Your Friends on Social Network  
  Comment on this Story  
 
 
 
Early Times Android App
STOCK UPDATE
 
 
 
 
 
 
 
   
Home About Us Top Stories Local News National News Sports News Opinion Editorial ET Cetra Advertise with Us ET E-paper
 
 
J&K RELATED WEBSITES
J&K Govt. Official website
Jammu Kashmir Tourism
JKTDC
Mata Vaishnodevi Shrine Board
Shri Amarnath Ji Shrine Board
Shri Shiv Khori Shrine Board
UTILITY
Train Enquiry
IRCTC
Matavaishnodevi
BSNL
Jammu Kashmir Bank
State Bank of India
PUBLIC INTEREST
Passport Department
Income Tax Department
JK CAMPA
JK GAD
IT Education
Web Site Design Services
EDUCATION
Jammu University
Jammu University Results
JKBOSE
Kashmir University
IGNOU Jammu Center
SMVDU