Early Times Report MALIGAON, July 19: The Second Rail-cum-Road Bridge at Saraighat over the Brahmaputra River has been sanctioned as part of the doubling of the Agthori-Kamakhya railway line under Northeast Frontier Railway (NFR). This major infrastructure project was sanctioned during the FY 2023-24 with a sanctioned estimate of Rs. 1,473.77 crore, and is targeted for completion by December 2029. As part of the progress, detailed estimates have been sanctioned by the Railway Board in February 2024 and the Design Drawing & Report has been finalized and duly approved by competent authority in March, 2025. The geotechnical investigations have been completed for the design of the substructure & superstructure and an EPC tender has been floated for the construction of the bridge, including approach roads, rail viaducts, earthwork and ancillary works. The tender is expected to be finalized soon and construction works will be started immediately after the same.
|