Breaking News :   BJP campaigning on Anantnag-Rajouri seat without seeking votes for any party | Ladakh: Cong candidate files nomination | Jammu Police slaps PSA against ‘Gola Shah’ | Victim’s family stages protest, blocks Jammu-Pathankot highway | Court grants pre-arrest bail to Raman Bhalla’s son | Omar Abdullah files nomination for Baramulla seat | CIK arrests radicalized youth in Budgam | One killed, 11 injured in Ramban accident | ‘Intruder sent to test troops alertness’ | Police attach properties of drug peddler | School timings changed in Sgr | Tahir, Aarti set to enthrall with New Song Release" | Krishi Vigyan Kendra promotes Sericulture | Four youth nabbed with Charas, Cash | Strategic Leap | Vaish community supported BJP Govt in realizing economic growth, creating jobs: Kavinder | Ravinder Raina visited flood prone villages of Kupwara district | Regional parties dividing people on caste, religion: Azad | Studies suggest more ice on Moon within exploitable depths: ISRO | Delhi bomb scare: Senders' intention was to create mass panic, disturb public order, says FIR | Advisor Bhatnagar inspects the progress of establishment of Vidhya Samiksha Kendra | "CBI not under control of Union of India": Centre to Supreme Court | BSF recovers China made drone in Tarn Taran | Rahul will be forced to take out 'Congress Dhoondho Yatra' after June 4: Shah in Bareilly | "BJP Not Against Muslims, Islamic Nations Honoured PM Modi": Rajnath Singh | Adani Ports Q4 net profit surges 77% to Rs 2,014.77 crore | "India Has 1,300 Islands, I Got Satellite Survey Done": PM Modi | EC directs parties to stop registering voters for beneficiary schemes under guise of surveys | "Should set timeline for restoration of statehood to J&K": Omar Abdullah to Amit Shah | LG flags off Road Safety Awareness tour from Raj Bhawan | Dr Tajamul gets addl charge of Director Family Welfare, MCH, immunization J&K | Student shooting video on railway tracks hit by train in Haridwar, dies | Noida man arrested for allegedly sharing deepfake video of Yogi Adityanath | Red Cross Society organizes week-long activities to mark World Red Cross Day | Beware of fake calls: Public warned against scammers impersonating authorities | Dr Sonia Verma receives prestigious Padma Vibhushan Dr Nirmala Deshpandey Award 2024 | Police apprehends thief stolen property recovered | 3 bovine smuggling bids foiled, 49 bovines rescued, 3 vehicles seized | Bovine smuggler arrested, 20 bovine rescued | NIOS announces schedule for practical exams, internal assessment for April/May 2024 | CEO SSCL inspects Jehangir Chowk junction improvement | J&K police attaches property of drug peddlers in Katra-district police Reasi | Dewan Devi Public School, Rajpura Mangotrian, Jammu commemorates International Labour Day | GDC holds extension lecture | Pinegrove School Subathu awarded for sustainability endeavours | National Workshop on Green-certified building materials held at SMVD University | Alcaraz loses to Rublev in Madrid Open quarterfinals, Sinner withdraws with hip injury | Change of guard in women's hockey team: Salima replaces Savita as skipper | Amul to sponsor USA and South Africa in T20 World Cup | Dew and absence of key bowlers hurt us: CSK skipper Gaikwad | Golf: Diksha, Pranavi and Vani ready for Aramco Series Korea | Back Issues  
 
news details
Delay in up-gradation work of CHEP-I causes Rs 6 cr loss to exchequer
6/15/2018 11:21:43 PM
Early Times Report

Jammu, June 15: It seems that the State Power Development Corporation (SPDC) has become habitual of causing revenue loss to the exchequer due to its lackadaisical approach. For example, undue delay in completion of renovation, modernization of Chenani-I Hydroelectric Project has caused the exchequer a loss of Rs 6 crore.
Renovation, modernization and uprating (RMU) of Chenani-I Hydroelectric Project (CHEP-I) was approved in 2005 at a cost of Rs 39 crore to enhance the capacity of the power house from 17 MWs to 23 MWs and generate an additional 33 MUs.
"The SPDC floated tender for the civil and the mechanical works but failed to get response. Due to lack of response, the works were split into 50 electro-mechanical works and 20 civil works and awarded in piecemeal between 2011 to 2015. Although 40 electromechanical and 19 civil works had been completed in 2016 at an expenditure of Rs 14 crore, delay in completion of the RMU resulted in loss of generation of 33 MUs valued at Rs 6 crore per annum," they said.
Besides, unit-I and II of Pahalgam Hydroelectric Project had defect of recurring vibration since its commissioning in 2005. However, the defects had not been removed as of 2016 resulting in operation of units at a de-rated capacity of only one MW against the three MW capacity which resulted in loss of generation of 10 MUs per annum valued at Rs 3 crore.
Pertinently, timely and systematic renovation and maintenance is essential to maintain power generation and reduce generation losses. The BoD sanctioned a RMU programme for seven HEP at a cost of Rs 208 crore which were to be completed within a period of one to three years.
  Share This News with Your Friends on Social Network  
  Comment on this Story  
 
 
 
Early Times Android App
STOCK UPDATE
  
BSE Sensex
NSE Nifty
 
CRICKET UPDATE
 
 
 
 
 
 
 
 
   
Home About Us Top Stories Local News National News Sports News Opinion Editorial ET Cetra Advertise with Us ET E-paper
 
 
J&K RELATED WEBSITES
J&K Govt. Official website
Jammu Kashmir Tourism
JKTDC
Mata Vaishnodevi Shrine Board
Shri Amarnath Ji Shrine Board
Shri Shiv Khori Shrine Board
UTILITY
Train Enquiry
IRCTC
Matavaishnodevi
BSNL
Jammu Kashmir Bank
State Bank of India
PUBLIC INTEREST
Passport Department
Income Tax Department
JK CAMPA
JK GAD
IT Education
Web Site Design Services
EDUCATION
Jammu University
Jammu University Results
JKBOSE
Kashmir University
IGNOU Jammu Center
SMVDU