Breaking News :   BJP campaigning on Anantnag-Rajouri seat without seeking votes for any party | Ladakh: Cong candidate files nomination | Jammu Police slaps PSA against ‘Gola Shah’ | Victim’s family stages protest, blocks Jammu-Pathankot highway | Court grants pre-arrest bail to Raman Bhalla’s son | Omar Abdullah files nomination for Baramulla seat | CIK arrests radicalized youth in Budgam | One killed, 11 injured in Ramban accident | ‘Intruder sent to test troops alertness’ | Police attach properties of drug peddler | School timings changed in Sgr | Tahir, Aarti set to enthrall with New Song Release" | Krishi Vigyan Kendra promotes Sericulture | Four youth nabbed with Charas, Cash | Strategic Leap | Vaish community supported BJP Govt in realizing economic growth, creating jobs: Kavinder | Ravinder Raina visited flood prone villages of Kupwara district | Regional parties dividing people on caste, religion: Azad | Studies suggest more ice on Moon within exploitable depths: ISRO | Delhi bomb scare: Senders' intention was to create mass panic, disturb public order, says FIR | Advisor Bhatnagar inspects the progress of establishment of Vidhya Samiksha Kendra | "CBI not under control of Union of India": Centre to Supreme Court | BSF recovers China made drone in Tarn Taran | Rahul will be forced to take out 'Congress Dhoondho Yatra' after June 4: Shah in Bareilly | "BJP Not Against Muslims, Islamic Nations Honoured PM Modi": Rajnath Singh | Adani Ports Q4 net profit surges 77% to Rs 2,014.77 crore | "India Has 1,300 Islands, I Got Satellite Survey Done": PM Modi | EC directs parties to stop registering voters for beneficiary schemes under guise of surveys | "Should set timeline for restoration of statehood to J&K": Omar Abdullah to Amit Shah | LG flags off Road Safety Awareness tour from Raj Bhawan | Dr Tajamul gets addl charge of Director Family Welfare, MCH, immunization J&K | Student shooting video on railway tracks hit by train in Haridwar, dies | Noida man arrested for allegedly sharing deepfake video of Yogi Adityanath | Red Cross Society organizes week-long activities to mark World Red Cross Day | Beware of fake calls: Public warned against scammers impersonating authorities | Dr Sonia Verma receives prestigious Padma Vibhushan Dr Nirmala Deshpandey Award 2024 | Police apprehends thief stolen property recovered | 3 bovine smuggling bids foiled, 49 bovines rescued, 3 vehicles seized | Bovine smuggler arrested, 20 bovine rescued | NIOS announces schedule for practical exams, internal assessment for April/May 2024 | CEO SSCL inspects Jehangir Chowk junction improvement | J&K police attaches property of drug peddlers in Katra-district police Reasi | Dewan Devi Public School, Rajpura Mangotrian, Jammu commemorates International Labour Day | GDC holds extension lecture | Pinegrove School Subathu awarded for sustainability endeavours | National Workshop on Green-certified building materials held at SMVD University | Alcaraz loses to Rublev in Madrid Open quarterfinals, Sinner withdraws with hip injury | Change of guard in women's hockey team: Salima replaces Savita as skipper | Amul to sponsor USA and South Africa in T20 World Cup | Dew and absence of key bowlers hurt us: CSK skipper Gaikwad | Golf: Diksha, Pranavi and Vani ready for Aramco Series Korea | Back Issues  
 
news details
Power supply partially restored in Kishtwar after 11 days
Double circuit transmission line under arbitration for 10 years
2/18/2019 10:51:13 PM
Asif Iqbal Naik

Early Times Report

Jammu, Feb 18: After 10 days of hard efforts by the Power Development Department, the electricity to Kishtwar District of Chenab valley has been partially restored by converting NHPCs 132 KV transmission line from Thatri to Kishtwar Grid Station into 33 KV till the original 132 KV transmission line from Khelani grid upto Kishtwar was restored. It might take around another one week for restoration as half dozen towers suffered damages due to massive snowfall on 7-2-2019.
A senior officer in the PDD told ET that they have been authorized to draw 400 Amp power which is about 6-7 MW and added that efforts are on to distribute this power on alternatively. He said that City I fitter of Kishtwar town required 7 MW and called upon the people not to use heating gadgets so that hassle free power could be provided to the people. He said that efforts are also on to provide alternative connectivity to Kishtwar outskirts and called upon the people to maintain calm and peace.
In response to the question of restoration of 132 KV transmission line, the official said that the authorities are in direct contact with CMD NHPC and the union power ministry is also keenly watching the progress of the restoration of the transmission line which is likely to be completed in next one week. Meanwhile State own 132 KV double circuit transmission line which will connect Kishtwar-Doda-Ramban Districts with Baglihar power project is under arbitration for last 10 years after the contractor faced some issues due to land acquisition and financial disputes.
The officials at the helm of the affairs informed ET that successive governments failed to solve the issue with the contractor who later moved the court for arbitration. The official said that this double circuit transmission line holds key for Doda and Kishtwar District as the work on around 5-6 power project will be at its peak in next one or two years and the existing line cannot provide the required electricity for Kishtwar District.
The officials also said that during last 10 years, around 4 towers of this double circuit transmission line suffered damages and required immediate attention.
The authorities at the helm of the affairs also turned blind eye towards construction of 440/132 KV Grid Station at Kishtwar which still looks like a distant dream.
The 440/132 KV Grid Station at Kishtwar is key for tapping and transporting electricity from various power projects under construction at Kishtwar as it is not practically possible to transfer the power from each under construction power project to north grid.
The officials said that the matter is already known to the government as well as to the senior officials of the department and the state government along with NHPC and JKPSDC need to take up the final call with regard to construction of 440/132 KV Grid Station at Kishtwar that too in shortest possible time from now as the work on major power projects including 1000 MW Pakal-Dool, 850 MW Rattle and 640 MW Keru power project has begun after inauguration by Prime Minister.
  Share This News with Your Friends on Social Network  
  Comment on this Story  
 
 
 
Early Times Android App
STOCK UPDATE
  
BSE Sensex
NSE Nifty
 
CRICKET UPDATE
 
 
 
 
 
 
 
 
   
Home About Us Top Stories Local News National News Sports News Opinion Editorial ET Cetra Advertise with Us ET E-paper
 
 
J&K RELATED WEBSITES
J&K Govt. Official website
Jammu Kashmir Tourism
JKTDC
Mata Vaishnodevi Shrine Board
Shri Amarnath Ji Shrine Board
Shri Shiv Khori Shrine Board
UTILITY
Train Enquiry
IRCTC
Matavaishnodevi
BSNL
Jammu Kashmir Bank
State Bank of India
PUBLIC INTEREST
Passport Department
Income Tax Department
JK CAMPA
JK GAD
IT Education
Web Site Design Services
EDUCATION
Jammu University
Jammu University Results
JKBOSE
Kashmir University
IGNOU Jammu Center
SMVDU