Breaking News :   Counter secessionist attempts to radicalise youth in Kashmir: LG urges poets, writers | Luxury for preachers’ families, death for youth: Religious scholars unmask radical networks | NC Working Committee reaffirms its commitment to restoration of J&K’s special status, statehood | After request from LAB judicial panel extends deadline for Leh violence evidence to Dec 8 | DB upholds life sentence of husband, paramour | AHA, Govt Medical College organize PDMP | HC rejects bail of accused cop | No bail for pharma dealer accused in multi-state cartel | Our youth, our strength-driving PM's dream of fitter, stronger India: Gaurav Gupta | India voice of balance, responsibility: Rajnath | Kashmir experiencing coldest Nov since 2007 | CBK files chargesheet; 2 accused remanded to judicial custody | CGPWA members visit JKMPCL Milk Plant, Laud Transformation | Can sit in court till midnight: CJI Surya Kant | Searches launched in Udhampur | STD holds day long workshop on GST Analytics, Fraud Detection Portal | Police attach property worth Rs 75 lakhs belonging to drug peddler under NDPS | ‘Implement budgeting rules’ | NFR upgrades Pit Lines at Kamakhya to prepare for Vande Bharat & Amrit Bharat Trains | CASO in Lal Chowk; hotels checked | GPF interest rate revised | LG Gupta calls for aggressive global promotion to revive Ladakh tourism | Man arrested for posting communal content | SSP Reasi visits far-flung area of PP Dwal, reviews ecurity preparedness and operational readiness | PTTI Vijaypur organizes valediction of two training courses | Director Agriculture inspects state seed testing laboratory, Inaugurates 30 kVA Genset for Uninterrupted Power Supply | Vocal for Local’ is the path to a Developed India 2047 - CM Nayab Singh Saini | DAV organised talk on Developing Scientific Temperament | BLSKS Mounts 3 days special campaign on "Nasha Mukat Bharat, Khushaal Bharat" at Miran Sahib | DPS Jammu Clinches Overall First Prize at Ramakrishna Mission Youth Convention 2025 | Junior Red Cross, Youth Red Cross Awareness program | Term-End Examinations of IGNOU starting from December 1 | LG Sinha’s Clarion Call | GDC Vijaypur organises Painting Competition to Commemorate Celebration of Samvidhaan Diwas | Madhukar Ji’s birth day celebrated | police nabs bootlegger; illicit liquor seized in Katra | District police Reasi nabs four persons with heroin; vehicle seized, FIR registered | CSIR-IIIM organizes 2nd half-yearly meeting of TOLIC | Central University of Jammu organized consultative workshop on ITEP curriculum framework | Samba police foils bovine smuggling attempt; arrests bovine smuggler, rescues 4 bovines | CM Dr Yadav transferred Rs 249 crore as price difference amount to the accounts of 1.34 lakh farmers from Gautampura | Udhampur police secures conviction in NDPS case within record time of 2 months | For grand and divine organization of 2027 Kumbh, Chief Minister held meeting with Acharyas and saints of Akharas | India continues its spiritual and moral fight against terrorism: CM Yogi Adityanath | Understanding “Constitution Day” History & Origin | Pakistan’s anxiety over the flag hoisting at the Shri Ram Temple | Audit Diwas celebrated by Office of Principal Accountant General, Jammu | Samvedna Club's Tournament Veteran League Edition 1 concludes with "Say No To Drugs & Yes to Sports" slogan | UK prominent social activist Sat Paul releases Hindi poetic compositions of Balbir | Altaf Bukhari condemns communalization of MBBS admissions in SMVDIME | Inauguration of Project Sena Sarthi held at Leh | NCC Units of GDC Kathua conduct preamble pledge activity to celebrate Constitution Day | SMVDU conducts training session on "Relevance of Communication Skills at the Workplace" for Non-Teaching Staff | BMD Testing Camp organized at SVMMCH | Plantation drive organized by NSS Unit "Prabha" GDC Ramgarh | Sanfort Preschool holds heritage walk to Kirmchi Temples | CGC University, Mohali’s founder chancellor honoured with “The father of education” award in Japan | LNCT University's School of Legal Studies celebrates Constitution Day | Reasi police foil liquor smuggling bid, seize 32 bottles at Balini check post | Shiksha Niketan Sr Sec School pays tribute to 26/11 martyrs | Doda police arrested person for uploading communally sensitive content on social media | Secretary IT reviews progress of amended BharatNet implementation in Ladakh | Awareness-cum-Distribution Programme held at GHS Ritti | GDC Thannamandi Screens Documentary on "Making of the Indian Constitution" | Government Degree College Akhnoor Intra-Semester Volleyball Tournament | Government of India to invest Rs 4,500 crore for modernization of SCL Mohali; Assures that it will not be privatised | Back Issues  
 
news details
Construction company stops payment to contractors, sub-contractors; workers go on strike
Jehangir Chowk-Rambagh flyover hits yet another roadblock
5/20/2018 10:55:38 PM
Jehangir Rashid
Early Times Report
SRINAGAR, May 20: The joy about the inauguration of first phase of Jehangir Chowk-Rambagh (JCRB) flyover here in the summer capital of the state has been short lived since the work on the remaining portion of the flyover is suspended over the past 10 days.
Workers carrying out the job on the construction of flyover have gone on strike since their wages have not been paid over a period of time. The workers had in fact carried out a protest demonstration on the completed portion of flyover a day before the same was thrown open for traffic even though only for one side.
Early Times has learnt from sources that the contractors and sub-contractors working on the project have not received any payment from the company that has been assigned the task. Following this the contractors and sub-contractors have not been able to pay towards the workers thus resulting into suspension of work.
"Economic Reconstruction Agency (ERA) has been making payments towards Simplex, the company involved in the construction of flyover on regular basis. However, the contractors and sub-contractors engaged by the company are not receiving any payment. This has resulted into a situation where the construction work has been halted on the remaining portion of JCRB flyover," said sources.
It would be in place to mention here that first phase of JCRB flyover from Barzulla Bridge to Bakshi stadium was inaugurated by chief minister Mehbooba Mufti on May 11. The stretch was thrown for one way traffic bound for Hyderpora, Rawalpora, Rangreth, Humhama and Budgam with no vehicle being allowed to move from the opposite side.
"Due to the controversy that has come up over the payment issue none of the officials of Simplex was present at the inauguration of the first phase of flyover. Simplex is seeking compensation for the machinery damaged due to the 2014 devastating deluge. Since the machinery was insured the demand is not genuine and it is here the trouble started," said sources.
Sources said that due to demonetization announced in November 2016, Simplex is facing huge difficulties in completing the projects it has taken up in the different parts of the country. The money being received by the company in Kashmir is being diverted to the other sites where construction is going on over the past few years.
"The JCRB flyover project is funded by Asian Development Bank (ADB) and there is no issue of finances in the same. The ADB through ERA has been releasing the payment to Simplex. The company instead of paying the contractors and sub-contractors has been utilizing the money for development projects in other parts of country," said sources.
Sources said the company higher ups have shown their willingness to withdraw from the project and have said that they are ready to pay some penalty in this regard. The company officials have been maintaining that they have faced losses due to the delay in the completion of work on JCRB flyover.
"If the company withdraws from the project then it would be difficult for the government to find an alternate so that the work on JCRB flyover is completed. Given this situation the people of Srinagar and some other districts would have to yearn for jam free traffic movement to and fro summer capital of the state," said sources.
The work on two and half kilometers long JCRB flyover was started in March 2013 and the project was expected to be completed in three years. However, the 2014 flood and 2016 summer agitation in Kashmir meant that the flyover would many deadlines. The government has revised the deadline for completion of the project as September 30, 2018.
  Share This News with Your Friends on Social Network  
  Comment on this Story  
 
 
 
Early Times Android App
STOCK UPDATE
 
 
 
 
 
 
 
   
Home About Us Top Stories Local News National News Sports News Opinion Editorial ET Cetra Advertise with Us ET E-paper
 
 
J&K RELATED WEBSITES
J&K Govt. Official website
Jammu Kashmir Tourism
JKTDC
Mata Vaishnodevi Shrine Board
Shri Amarnath Ji Shrine Board
Shri Shiv Khori Shrine Board
UTILITY
Train Enquiry
IRCTC
Matavaishnodevi
BSNL
Jammu Kashmir Bank
State Bank of India
PUBLIC INTEREST
Passport Department
Income Tax Department
JK CAMPA
JK GAD
IT Education
Web Site Design Services
EDUCATION
Jammu University
Jammu University Results
JKBOSE
Kashmir University
IGNOU Jammu Center
SMVDU