Breaking News :   Previous records set to tumble | The Incomplete Return: Revisiting the Home We Never Lived In | Healing Wounds - Reviving Tourism in Kashmir | Turning Pages in a Scrolling World: The Quiet Return of Reading | Decades-old Kashmiri Pandit killing cases may reopen following LG’s initiative | Doda’s deadly roads: Fatal accidents persist | BJP misleading people of J&K and country on Omar Govt’s performance: Surinder Choudhary | HC reject pre-arrest bail in PMLA of Master-Mind in fake Cryptocurrency case | Robbery case solved Jammu police | Trials for upcoming national Netball championships | BIS JKBO Organizes "Manak Conclave" for Industries and Stakeholders Engagement in Kathua | Health & Education pillars of J&K's progress and prosperity: CM Omar Abdullah | CISF Wins 64 Medals at World Police and Fire Games 2025 in the USA | HC reject bail plea of Narco Terrorism | Another batch of pilgrims leaves Jammu for Amarnath Shrine | BJP Jammu & Kashmir holds joint organizational meeting | Swachhta Internship Program launched to foster cleanliness culture in schools | Reasi police nabs drug peddler; 509.930 grams of cannabis recovered | JKNC delegation meets Deputy Chief Minister Surinder Choudhary | Nominations for Padma Awards-2026 open till 31st July, 2025 | UIDAI urges parents and guardians to update children's Aadhaar biometrics; free between ages 5 and 7 | Gold declines Rs 200 to Rs 99,370/ 10 G; Silver plunges Rs 3,000 to Rs 1.12 lakh/kg | Ladakh Administration reopens property return portal for final time till July 30 | Tony leads delegation of Trikuta Nagar to JMC Commissioner, submits memorandum | CM Pushkar Singh Dhami meets Union Health Minister JP Nadda in Delhi | CM Yogi's Gram-Urja model to transform rural Uttar Pradesh into self-reliant, energy-rich villages | NFR's Seamless Electric Traction upto Dibrugarh & Naharlagun makes ease in Railway Transportation system for NE | DLSA Udhampur convenes UTRC meeting | Skilled youth are the backbone of self-reliant India: CM Yogi | Army organises Quiz Competition on Agra Summit | Children, Adolescent groups formed at Rajouri | Secretary, Department of Food & Public Distribution chairs review meeting with UT Ladakh Administration | SMVDNSH Katra achieves milestone with first neuro-navigation guided brain tumor surgery | Udhampur police busts Inter-State Gold fraud; accused arrested within 24 bours | Jammu Police seizes two tippers for Illegal Mining | J&K cadets script history on Mt Everest” | Kidnapped girl traced, accused arrested by Doda Police | UTDRF Doda unit organizes disaster awareness session | DC Srinagar reviews progress of construction of Panchayat Ghars | APS Damana hosts prestigious, spirited Inter-APSs cluster-I hindi debate competition | Udhampur Police book another Notorious bovine smuggler | J&K clinches Gold at National ODOP Awards 2024 for second consecutive year | Inter District Division Level Youth organizes Exchange Programme | Chairman DLSA emphasizes vital role of UTRC meetings in strengthening criminal justice system | Gill didn't look as technically tight or calm as usual: Vaughan | Happy to silence the the keyboard warriors: Jofra Archer | BLSKS observes “World Youth Skills Day 2025” | Back Issues  
 
news details
Construction company stops payment to contractors, sub-contractors; workers go on strike
Jehangir Chowk-Rambagh flyover hits yet another roadblock
5/20/2018 10:55:38 PM
Jehangir Rashid
Early Times Report
SRINAGAR, May 20: The joy about the inauguration of first phase of Jehangir Chowk-Rambagh (JCRB) flyover here in the summer capital of the state has been short lived since the work on the remaining portion of the flyover is suspended over the past 10 days.
Workers carrying out the job on the construction of flyover have gone on strike since their wages have not been paid over a period of time. The workers had in fact carried out a protest demonstration on the completed portion of flyover a day before the same was thrown open for traffic even though only for one side.
Early Times has learnt from sources that the contractors and sub-contractors working on the project have not received any payment from the company that has been assigned the task. Following this the contractors and sub-contractors have not been able to pay towards the workers thus resulting into suspension of work.
"Economic Reconstruction Agency (ERA) has been making payments towards Simplex, the company involved in the construction of flyover on regular basis. However, the contractors and sub-contractors engaged by the company are not receiving any payment. This has resulted into a situation where the construction work has been halted on the remaining portion of JCRB flyover," said sources.
It would be in place to mention here that first phase of JCRB flyover from Barzulla Bridge to Bakshi stadium was inaugurated by chief minister Mehbooba Mufti on May 11. The stretch was thrown for one way traffic bound for Hyderpora, Rawalpora, Rangreth, Humhama and Budgam with no vehicle being allowed to move from the opposite side.
"Due to the controversy that has come up over the payment issue none of the officials of Simplex was present at the inauguration of the first phase of flyover. Simplex is seeking compensation for the machinery damaged due to the 2014 devastating deluge. Since the machinery was insured the demand is not genuine and it is here the trouble started," said sources.
Sources said that due to demonetization announced in November 2016, Simplex is facing huge difficulties in completing the projects it has taken up in the different parts of the country. The money being received by the company in Kashmir is being diverted to the other sites where construction is going on over the past few years.
"The JCRB flyover project is funded by Asian Development Bank (ADB) and there is no issue of finances in the same. The ADB through ERA has been releasing the payment to Simplex. The company instead of paying the contractors and sub-contractors has been utilizing the money for development projects in other parts of country," said sources.
Sources said the company higher ups have shown their willingness to withdraw from the project and have said that they are ready to pay some penalty in this regard. The company officials have been maintaining that they have faced losses due to the delay in the completion of work on JCRB flyover.
"If the company withdraws from the project then it would be difficult for the government to find an alternate so that the work on JCRB flyover is completed. Given this situation the people of Srinagar and some other districts would have to yearn for jam free traffic movement to and fro summer capital of the state," said sources.
The work on two and half kilometers long JCRB flyover was started in March 2013 and the project was expected to be completed in three years. However, the 2014 flood and 2016 summer agitation in Kashmir meant that the flyover would many deadlines. The government has revised the deadline for completion of the project as September 30, 2018.
  Share This News with Your Friends on Social Network  
  Comment on this Story  
 
 
 
Early Times Android App
STOCK UPDATE
  
BSE Sensex
NSE Nifty
 
CRICKET UPDATE
 
 
 
 
 
 
 
 
   
Home About Us Top Stories Local News National News Sports News Opinion Editorial ET Cetra Advertise with Us ET E-paper
 
 
J&K RELATED WEBSITES
J&K Govt. Official website
Jammu Kashmir Tourism
JKTDC
Mata Vaishnodevi Shrine Board
Shri Amarnath Ji Shrine Board
Shri Shiv Khori Shrine Board
UTILITY
Train Enquiry
IRCTC
Matavaishnodevi
BSNL
Jammu Kashmir Bank
State Bank of India
PUBLIC INTEREST
Passport Department
Income Tax Department
JK CAMPA
JK GAD
IT Education
Web Site Design Services
EDUCATION
Jammu University
Jammu University Results
JKBOSE
Kashmir University
IGNOU Jammu Center
SMVDU