Breaking News :   3rd Ravi Tikku Memorial Speed Ball Championship concluded | HC asks centre to decide representation to include women in armed forces through CDS exam | Make Modi PM for third time to end terrorism, Naxalism: Amit Shah | IndiGo's Ahmedabad -Bound plane returns to Delhi airport due to glitch | Kavinder commends voters for record turnout, foresees BJP victory in Jammu-Reasi Parliamentary seat says PDP daydreaming on Art 370 | Shaurya Smarak' of three fallen army officers unveiled in Jammu | Rains lash J&K, MeT forecasts more in next few days | 24×7 kitchen operational to support families near Ramban land sinking camp site | Srinagar boat tragedy: Another boy's body found | Will not fight LS polls if NC gets INDIA Bloc to commit restoration of Article 370: Sajad Lone | Special training camp for Village Defence Guards held in Poonch | Cyber police Kashmir recovers 30 smartphones, returned to owners | Police seize huge illicit liquor in Darai area | Omar Abdullah visits Beerwah to offer condolences | GRP apprehends 28-year absconder | Drug labs unearthed in Rajasthan, Gujarat; 7 arrested, 300 kg narcotics seized: NCB | Government portal offered more jobs than applied for in 2023-24: Report | No 'Objectionable' book prescribed, developed by JKBOSE: J&K SED | Observers for Srinagar PC hold joint meeting with Officers at SKICC | Mentally deranged person behind disrespect to local shrine | Police cracks down on overloaded vehicles in Kishtwar | SVEEP: Signature Campaign held at GDC Sumbal | Cybercrime investigation unit recovers online defrauded amount | Archery WC: India bag three gold medals to sweep compound team events | Divyanshi Mahajan from DPS Jammu secures top spot among J&K UT girls in JEE mains 2024 | Felicitation ceremony held | Army Public School Ratnuchak hosts inspiring Parent-Teacher Orientation Program: "Ignite Your Potential" | JUIT, Solan, Himachal Pradesh, achieves A+ grade accreditation from NAAC for five years | Awareness cum skill enhancement workshop concludes at GCW Udhampur | Yuvraj identifies Surya, Bumrah as key to India's prospects in | NSS Unit of GDC RS Pura organizes cleanliness drive in alignment with Swachh Bharat Abhiyan | NC mounts pressure on Cong to field candidate from Kargil on Ladakh seat | Anantnag-Rajouri polls: BJP optimistic about postponement | Man commits suicide; family accuses police officer of ‘humiliating’ victim | CBI officer killed in motorcycle accident | Mughal Road shut after fresh snowfall | CS reviews flood management, mitigation plan for Kashmir | DAH Jammu celebrates World Veterinary Day-2024 | Expenditure Observer reviews enforcement of ECI regulations on election expenditure | GMC Baramulla initiates vaccination drive for Haj Pilgrim | Three day re-orientation training session for MLHPs, CHOs concludes at Doda | Cyber cell dpo jammu solved online financial fraud of Rs 1,40,683 | Back Issues  
 
news details
Construction company stops payment to contractors, sub-contractors; workers go on strike
Jehangir Chowk-Rambagh flyover hits yet another roadblock
5/20/2018 10:55:38 PM
Jehangir Rashid
Early Times Report
SRINAGAR, May 20: The joy about the inauguration of first phase of Jehangir Chowk-Rambagh (JCRB) flyover here in the summer capital of the state has been short lived since the work on the remaining portion of the flyover is suspended over the past 10 days.
Workers carrying out the job on the construction of flyover have gone on strike since their wages have not been paid over a period of time. The workers had in fact carried out a protest demonstration on the completed portion of flyover a day before the same was thrown open for traffic even though only for one side.
Early Times has learnt from sources that the contractors and sub-contractors working on the project have not received any payment from the company that has been assigned the task. Following this the contractors and sub-contractors have not been able to pay towards the workers thus resulting into suspension of work.
"Economic Reconstruction Agency (ERA) has been making payments towards Simplex, the company involved in the construction of flyover on regular basis. However, the contractors and sub-contractors engaged by the company are not receiving any payment. This has resulted into a situation where the construction work has been halted on the remaining portion of JCRB flyover," said sources.
It would be in place to mention here that first phase of JCRB flyover from Barzulla Bridge to Bakshi stadium was inaugurated by chief minister Mehbooba Mufti on May 11. The stretch was thrown for one way traffic bound for Hyderpora, Rawalpora, Rangreth, Humhama and Budgam with no vehicle being allowed to move from the opposite side.
"Due to the controversy that has come up over the payment issue none of the officials of Simplex was present at the inauguration of the first phase of flyover. Simplex is seeking compensation for the machinery damaged due to the 2014 devastating deluge. Since the machinery was insured the demand is not genuine and it is here the trouble started," said sources.
Sources said that due to demonetization announced in November 2016, Simplex is facing huge difficulties in completing the projects it has taken up in the different parts of the country. The money being received by the company in Kashmir is being diverted to the other sites where construction is going on over the past few years.
"The JCRB flyover project is funded by Asian Development Bank (ADB) and there is no issue of finances in the same. The ADB through ERA has been releasing the payment to Simplex. The company instead of paying the contractors and sub-contractors has been utilizing the money for development projects in other parts of country," said sources.
Sources said the company higher ups have shown their willingness to withdraw from the project and have said that they are ready to pay some penalty in this regard. The company officials have been maintaining that they have faced losses due to the delay in the completion of work on JCRB flyover.
"If the company withdraws from the project then it would be difficult for the government to find an alternate so that the work on JCRB flyover is completed. Given this situation the people of Srinagar and some other districts would have to yearn for jam free traffic movement to and fro summer capital of the state," said sources.
The work on two and half kilometers long JCRB flyover was started in March 2013 and the project was expected to be completed in three years. However, the 2014 flood and 2016 summer agitation in Kashmir meant that the flyover would many deadlines. The government has revised the deadline for completion of the project as September 30, 2018.
  Share This News with Your Friends on Social Network  
  Comment on this Story  
 
 
 
Early Times Android App
STOCK UPDATE
  
BSE Sensex
NSE Nifty
 
CRICKET UPDATE
 
 
 
 
 
 
 
 
   
Home About Us Top Stories Local News National News Sports News Opinion Editorial ET Cetra Advertise with Us ET E-paper
 
 
J&K RELATED WEBSITES
J&K Govt. Official website
Jammu Kashmir Tourism
JKTDC
Mata Vaishnodevi Shrine Board
Shri Amarnath Ji Shrine Board
Shri Shiv Khori Shrine Board
UTILITY
Train Enquiry
IRCTC
Matavaishnodevi
BSNL
Jammu Kashmir Bank
State Bank of India
PUBLIC INTEREST
Passport Department
Income Tax Department
JK CAMPA
JK GAD
IT Education
Web Site Design Services
EDUCATION
Jammu University
Jammu University Results
JKBOSE
Kashmir University
IGNOU Jammu Center
SMVDU