Breaking News :   Rs 500 crore needed to become Cong’s CM face, alleges Sidhu’s wife | Connectivity, coordination ensured historic success: Defence Minister | Singh dedicates BRO’s 22 vital infrastructure projects for J&K | Fight against Chitta: Rare political unity in Himachal sends message to J&K | Srinagar Police seize Rs 1 crore property of notorious drug peddler | 25 killed, 6 injured in fire at nightclub in Goa | Deeply saddened: LG Sinha | LG Sinha extends gratitude to soldiers, urges people to donate generously | JKPSC conducts CCE as per schedule | CBK files chargesheet, 2 booked | Parliamentary Panel to summon airline executives, regulator | PM Modi to initiate debate on Vande Mataram in Lok Sabha today | Cross-border arms smuggling module busted in Punjab | MeT predicts light snowfall | Forest fire triggers landmine blasts | MLA Ramgarh kick-starts lane & drain Development work at village Dabuj Kaka | Three of family killed as car overturns in Karnataka’s Mandya | Kendriya Vidyalaya Samba celebrated its Annual Sports Day with great zeal, enthusiasm | Natrang stages play Topian | CM Yogi Adityanath government intensifies crackdown on illegal liquor networks to safeguard public safety | JNV Budgam hosts Grand ‘Alumni Meet 2025’ | Under Chief Minister Yogi Adityanath’s leadership, Uttar Pradesh has emerged as the new powerhouse of Startup India | Armed Forces Flag Day: Div Com Kashmir pays homage to Armed forces | Uttarakhand: Interstate arms trafficker held with 5 guns, 40 cartridges | Self-employment is creating most new jobs in India: What this means for job seekers in the years to come | Manipulation in Campus Placements: IITs Ignite a needed ethical revolution | INDIA Bloc On Crossroads | Back Issues  
 
news details
Continuous rains, landslides may delay road widening projects
8/16/2018 10:42:09 PM
Ashwani Sharma
Early Times Report
Udhampur, Aug 14: The company 'Gammon Engineers , Contractors Pvt Ltd and other locals contractors engaged in road widening projects on Jammu-Srinagar national highway have suffered losses due to continuous rains and landslides triggered by the heavy rains. Apart from this the landslides and heavy rains have further delayed the completion of projects thereby affecting the deadlines.
A massive landslide from the hill side occurred on August 13 between km 71+140 to 280 and another place mord which km75/800/75/900 hill side occurred due to heavy rainfall on August 12 , 13 and 14 thereby blocking the newly constructed road.
All the earth moving machinery and manpower were pressed into action for restoring the traffic without much delay by the executing agency-Gammon Engineers and Contractors Pvt Ltd.
However, the traffic without much delay was restored by diverting traffic to the existing road which was into work for strengthening of the existing road.
The Project Manager (PM) of the company when contacted confirmed that once the slide is cleared from the newly constructed road, the traffic will be restored to new road and accordingly the works for strengthening of the existing road shall be taken up.
He also informed that the landslide and heavy rains had wasted precious time and consequently the completion time of the project will also be affected.
  Share This News with Your Friends on Social Network  
  Comment on this Story  
 
 
 
Early Times Android App
STOCK UPDATE
 
 
 
 
 
 
 
   
Home About Us Top Stories Local News National News Sports News Opinion Editorial ET Cetra Advertise with Us ET E-paper
 
 
J&K RELATED WEBSITES
J&K Govt. Official website
Jammu Kashmir Tourism
JKTDC
Mata Vaishnodevi Shrine Board
Shri Amarnath Ji Shrine Board
Shri Shiv Khori Shrine Board
UTILITY
Train Enquiry
IRCTC
Matavaishnodevi
BSNL
Jammu Kashmir Bank
State Bank of India
PUBLIC INTEREST
Passport Department
Income Tax Department
JK CAMPA
JK GAD
IT Education
Web Site Design Services
EDUCATION
Jammu University
Jammu University Results
JKBOSE
Kashmir University
IGNOU Jammu Center
SMVDU