Breaking News :   We have scripted new history under PM Modi’s guidance: LG Sinha | Take legislators, stakeholders on board for smooth execution of projects: CM Omar tells officials | HC upholds PSA detention of Kupwara man | Hundreds participate in Army-sponsored marathon near LoC | No airline will be permitted to cause hardship to passengers: Naidu | Border surveillance, digital tools reduce infiltration, terror activities: MHA | CBK cracks major grain misappropriation racket | Court extends NIA custody of Amir Rashid by 7 days | Baramulla doctor arrested for providing logistic support to suicide bomber | NIA conducts searches forests in Anantnag | BSF jawan found dead, CRPF constable dies | Biting cold grips Kashmir | Man accused of criminal, anti-social activities detained under PSA | Indian Youth and Education: Modern-Day Challenges and Opportunities | Procrastination — A quiet enemy of clear thinking | Symbols Of Resilience | LG Kavinder Gupta calls Financial Institutions catalysts of socio-economic change in Ladakh | "Separatist Thinking in Parliament": Gaurav hits out at NC MP Ruhullah Mehdi | Govt committed to deliver good governance that reflects aspirations of every section of society: Sakeena Itoo | General Manager of NFR inspects Darjeeling Himalayan Railway | DPIIT publishes first part of working paper on AI-copyright interface | District police Reasi seizes two dumpers carry illegal mining material at Katra | KC Gurukul Public School celebrates 15th Annual Day | JKPCC celebrates Sonia Gandhi Ji's birth day | M Suleman Choudhary-IPS, IGP Traffic J&K holds review meeting on traffic management in Jammu City | SC grants Interim bail to Bijbehara resident sent back to Jail 19 Years after acquittal | Shri Mata Vaishno Devi Narayana Hospital saves newborn from severe meningitis and septic shock | Governor of Punjab Inaugurated AIU North Zone Vice Chancellors' Meet 2025-26 at LPU | District police Reasi arrests drug peddler, recovers heroin during Naka checking | Youth Power for Life: ROTTO-PGIMER Champions Organ Donation at Haryana Youth Festival 2025 | GNDU's Golden Jubilee Centre for Entrepreneurship & Innovation Showcases Startups at PITEX 2025 | ATM theft accused arrested by Doda Police | Indian Army accelerates bridge restoration & medical aid in Sri Lanka under OP Sagar Bandhu | 2-day Kisan Mela/Workshop organised under MIDH at Ramgarh | Back Issues  
 
news details
BJP befools Jammuites on Tawi artificial lake project
Abandoned work yet to be resumed even after 3 yrs
9/22/2018 10:46:35 PM
G S Asgotra
Early Times Report
JAMMU, Sept 22: Despite claims of former Irrigation and Flood Control ministers and BJP's stalwarts about completing Tawi artificial lake project, work on the abandoned project is yet to resume even after more than three years.
After assuming power in the state as head of the coalition government of BJP-PDP, then Chief Minister Mufti Mohammed Sayeed while inspecting the project found it "not feasible." The then MoS, Tourism Priya Sethi was present during the inspection.
"However, this announcement made hue and cry within BJP which faced severe criticism from the opposition. To save their face, many BJP ministers later announced that the project would be completed at any cost", said sources.
Thereafter, the then minister for Irrigation and Flood Control, Choudhary Sukhnandan asserted that work on lake project, on which nearly Rs 57 crore had been spent by then, would be resumed "as soon as possible." He had also asserted that he had taken up the matter of Jammu's development with the Union Water Resource Minister, Uma Bharti, "who assured us to provide economical assistance to complete the abandoned project."
Surprisingly, after such a long lapse, nothing has been done so far to resume the work on the prestigious project which was abandoned by I&FC department.
The rhetoric of the BJP leaders can be gauged from this fact that they announced that the Tawi river would be developed on the pattern of Sabarmati river and that a memorandum of understanding was inked with Sabarmati River Front Development Corporation Limited (SRFDCL), and nearly Rs 75 lakh was released to prepare Detail Project Report.
Later, in December 2017, the then Minister I&FC, Choudhary Sham announced that the project would be completed "within four months," but his announcement proved a hoax again.
BJP insiders say that the hollow claims were made by BJP during three years in power, but nothing has been done on ground to complete the abandoned project, be it Suchetgarh Border project, or Ropeway project from Mubarak Mandi to Bahu Fort.
  Share This News with Your Friends on Social Network  
  Comment on this Story  
 
 
 
Early Times Android App
STOCK UPDATE
 
 
 
 
 
 
 
   
Home About Us Top Stories Local News National News Sports News Opinion Editorial ET Cetra Advertise with Us ET E-paper
 
 
J&K RELATED WEBSITES
J&K Govt. Official website
Jammu Kashmir Tourism
JKTDC
Mata Vaishnodevi Shrine Board
Shri Amarnath Ji Shrine Board
Shri Shiv Khori Shrine Board
UTILITY
Train Enquiry
IRCTC
Matavaishnodevi
BSNL
Jammu Kashmir Bank
State Bank of India
PUBLIC INTEREST
Passport Department
Income Tax Department
JK CAMPA
JK GAD
IT Education
Web Site Design Services
EDUCATION
Jammu University
Jammu University Results
JKBOSE
Kashmir University
IGNOU Jammu Center
SMVDU