Breaking News :   Governor blames everyone except corrupt officials around him? | Will Modi Govt withdraw security to separatists? | Killings of militants frustrates accomplices, desperate to derail election process | Not seen on ground, Omar Abdullah concerned on twitter | Inspectors hold Assistant Commissioners' offices | Curfew in Jammu city after protests over Pulwama attack, Army called out | Curfew extended for 72 hours | Home Minister Rajnath Singh sends strong message to separatists | Condemns violent incidents, appeals to maintain communal harmony | GCW Parade organizes One Day National Seminar | Withdraw security to Farooq, Omar, Mehbooba, abrogate Articles 35A, 370: Prof. Hari OM | Series of protests against Pulwama terror attack rocks Jammu | Awantipura attack on CRPF convoy | Pulwama Attack: Stand steadfast in support of the brave Indian soldiers | Let us be pro active and take some strict actions before we lose more lives | Security & intelligence laxity cost 40 CRPF lives | Jammu-Srinagar highway closed after fresh landslides | Won't forget, won't forgive': CRPF vows to avenge death of 49 bravehearts | J&K National Highway death Trap for security forces; 58 Jawans killed since 2013 | 80 kg high-grade RDX used by Jaish terrorist in Pulwama attack | Pulwama attack: Court of Inquiry ordered after number of deaths rises | Jammu University postpones all Exams scheduled on February 16 | NIA begins investigation, 7 detained after raids | Ensure enabling environment for all disabled persons in J&K: HC | Death toll in IED attack on CRPF reaches 49 | Pulwama attack: FIR against AMU student Basim Hilal for tweeting How's the Jaish | A strong policy for Kashmir should be priority of Government: ABVP | Suicidal attack on CRPF convoy evokes wide condemnation | DERS organises environment awareness prog | Guv addresses concerns of Kargil | Many youth join Aam Aadmi Party | Lecture on "Aadhunika Yug Mein Vedon ki Prasangikataa" organised | Financial literacy awareness programmes organised | Four-day Vice-Chancellors' meet on "Academic Leadership Training in Higher Education" concludes | Back Issues  
 
news details
Delay in shifting of utilities has hampered developmental projects in JK
11/13/2018 10:39:46 PM
Early Times Report

JAMMU, Nov 13: Shifting of utilities from the areas where new road projects are under construction coupled with delay in grant of forest clearance has delayed construction of new projects sanctioned over years back in Jammu region.
This delay has been a cause of concern for the officers who have been entrusted the job of constructing these projects in the State.
Sources said the Power Development Department (PDD) and Public Health Engineering (PHE) Department has failed to shift the utilities from the area where new projects are under construction.
Sources said that PDD and other departments are framing estimates much higher than what should be the genuine cost involved for shifting of utilities with the result the project gets delayed.
Sources said the higher authorities in Civil Secretariat have also taken a strong exception to the delay caused in shifting of utilities and framing of higher rated estimates which the Government can't afford to pay.
Even in some cases the Government has to pay more for shifting of utilities than what is the actual cost of the project.
This being of a scandleous proposition needs investigation at higher level, sources said.
Sources said the issue has been brought in the notice of Union Government by some State leaders who alleged that a deliberate attempt is being made to sabotage under construction projects in the State under a hatched conspiracy.
Sources said the Central Government has already taken up the issue with the concerned officers in State Government which has sought ordering of s probe into the same and action against the erring officers framing estimates by fudging figures.
Sources said a Union Minister when apprised about the same in a meeting at Jammu termed a scandal and sought action on the same so that the projects sanctioned by the Union Government will get delayed.
Sources said the delay has been caused in speeding up of work on Akhnoor road where the PHE deptt and PDD are delaying the shifting of utilities. Besides the delay has been caused on construction of road widening along Keerian Gandial bridge in Kathua and other developmental projects due to shifting of utilities.
  Share This News with Your Friends on Social Network  
  Comment on this Story  
 
 
 
Early Times Android App
STOCK UPDATE
  
BSE Sensex
NSE Nifty
 
CRICKET UPDATE
 
 
 
 
 
 
 
 
   
Home About Us Top Stories Local News National News Sports News Opinion Editorial ET Cetra Advertise with Us ET E-paper
 
 
J&K RELATED WEBSITES
J&K Govt. Official website
Jammu Kashmir Tourism
JKTDC
Mata Vaishnodevi Shrine Board
Shri Amarnath Ji Shrine Board
Shri Shiv Khori Shrine Board
UTILITY
Train Enquiry
IRCTC
Matavaishnodevi
BSNL
Jammu Kashmir Bank
State Bank of India
PUBLIC INTEREST
Passport Department
Income Tax Department
JK CAMPA
JK GAD
IT Education
Web Site Design Services
EDUCATION
Jammu University
Jammu University Results
JKBOSE
Kashmir University
IGNOU Jammu Center
SMVDU