Breaking News :   Rs 500 crore needed to become Cong’s CM face, alleges Sidhu’s wife | Connectivity, coordination ensured historic success: Defence Minister | Singh dedicates BRO’s 22 vital infrastructure projects for J&K | Fight against Chitta: Rare political unity in Himachal sends message to J&K | Srinagar Police seize Rs 1 crore property of notorious drug peddler | 25 killed, 6 injured in fire at nightclub in Goa | Deeply saddened: LG Sinha | LG Sinha extends gratitude to soldiers, urges people to donate generously | JKPSC conducts CCE as per schedule | JKPSC conducts CCE as per schedule | CBK files chargesheet, 2 booked | Parliamentary Panel to summon airline executives, regulator | PM Modi to initiate debate on Vande Mataram in Lok Sabha today | Cross-border arms smuggling module busted in Punjab | MeT predicts light snowfall | Forest fire triggers landmine blasts | MLA Ramgarh kick-starts lane & drain Development work at village Dabuj Kaka | Three of family killed as car overturns in Karnataka’s Mandya | Kendriya Vidyalaya Samba celebrated its Annual Sports Day with great zeal, enthusiasm | Natrang stages play Topian | CM Yogi Adityanath government intensifies crackdown on illegal liquor networks to safeguard public safety | JNV Budgam hosts Grand ‘Alumni Meet 2025’ | Under Chief Minister Yogi Adityanath’s leadership, Uttar Pradesh has emerged as the new powerhouse of Startup India | Armed Forces Flag Day: Div Com Kashmir pays homage to Armed forces | Uttarakhand: Interstate arms trafficker held with 5 guns, 40 cartridges | Self-employment is creating most new jobs in India: What this means for job seekers in the years to come | Manipulation in Campus Placements: IITs Ignite a needed ethical revolution | INDIA Bloc On Crossroads | Back Issues  
 
news details
Chief Secretary reviews progress of USB Rail Link Project
70 per cent tunneling work completed on Udhampur-Srinagar-Baramulla rail link project
7/5/2019 8:03:00 PM


SRINAGAR, JULY 05: Chief Secretary, B V R Subrahmanyam chaired the Apex Committee meeting to review the progress of the Udhampur-Srinagar-Baramulla Rail Link (USBRL) Project.
Principal Secretary, Home , Financial Commissioner Revenue, J&K, Principal Secretary, Planning Development & Monitoring Department, Administrative Secretaries of the Departments Forest, Ecology & Environment, PDD, Revenue and Tourism, Divisional Commissioner, Kashmir, Chief Administrative Officer (CAO), USBRL Project, Deputy Commissioner, Srinagar, Deputy Commissioner Budgam and other senior officers and representatives of Railway Authorities were present in the meeting.
Divisional Commissioner, Jammu, Deputy Commissioner, Ramban and Deputy Commissioner, Reasi participated in the meeting through video conferencing.
CAO, USBRL Project informed the Committee that out of the total 272 Km Rail line between Udhampur and Bramulla, 111 Km stretch between Katra and Banihal remains to be connected. The stretch has tunnels in 97 Km length and surface Rail line on 14 Kms. He said 67 Km long escape tunnels are also being provided alongside the main tunnels.
Regarding progress of work on the 111Km Katra-Banihal stretch, CAO, USBRL Project informed that 67 Km construction work of the main Tunnels has been completed along with 30 Km of the escape tunnels. He said work on the project is going on smoothly. However, certain issues requiring intervention of the State Government are projected for early resolution.
To expedite the resolution of the issues and completion of the Project, Chief Secretary directed the Railway Authorities to submit on every Monday by 11:00 AM, a weekly progress report along with details about bottlenecks/stoppages, if any, encountered during the previous week to his office, Principal Secretary, Home, Divisional Commissioner, Jammu, IGP Jammu and concerned DCs/SSPs. He asked the Railway Authorities to first seek resolution of the issues with the concerned DCs and Divisional Commissioner, Jammu before referring them to Government.
In order to put in place a coordination mechanism at the district level for the USBRL Project, State Government will constitute Committees of Deputy Commissioners of Ramban and Reasi with District SPs, concerned Revenue Authorities etc and representatives of IRCON and KRCL as members to review the progress of work every week and discuss resolution of issues, if any.
Timelines were also fixed by Chief Secretary for time bound resolution and completion of the few pending land acquisition, utility shifting and compensation issues in Reasi, Ramban and Budgam districts.
  Share This News with Your Friends on Social Network  
  Comment on this Story  
 
 
 
Early Times Android App
STOCK UPDATE
 
 
 
 
 
 
 
   
Home About Us Top Stories Local News National News Sports News Opinion Editorial ET Cetra Advertise with Us ET E-paper
 
 
J&K RELATED WEBSITES
J&K Govt. Official website
Jammu Kashmir Tourism
JKTDC
Mata Vaishnodevi Shrine Board
Shri Amarnath Ji Shrine Board
Shri Shiv Khori Shrine Board
UTILITY
Train Enquiry
IRCTC
Matavaishnodevi
BSNL
Jammu Kashmir Bank
State Bank of India
PUBLIC INTEREST
Passport Department
Income Tax Department
JK CAMPA
JK GAD
IT Education
Web Site Design Services
EDUCATION
Jammu University
Jammu University Results
JKBOSE
Kashmir University
IGNOU Jammu Center
SMVDU