Breaking News :   Terror trail to pulpit: NIA raids cleric’s room in Kashmir in Red Fort blast probe | LG Sinha chairs high level meeting of Home Department | LG reviews progress of Pradhan Mantri TB Mukt Bharat Abhiyaan | Court cracks down on terror mastermind, issues non-bailable warrant against Syed Salahuddin | No rain since September: Jammu farmers fear Rabi crop failure | Sessions Court rejects bail plea of accused | NIA Court refuses bail in grenade attack case | SSP Jammu launches online tenant verification portal ‘KIRAYEDAR’ | CBK files charge sheet against 4 accused | 2 arrested under UAPA | 16th State Speedball Championship DAY-2 (FOR JUNIORS) | ACB arrests Patwari | Registration for healthcare professionals begins | Celebrations of World Aids Day | GGM Science College bags first prize in Group Dance Mahotsav-2025 | Nirvan Divas of Sant Gadge Maharaj observed | Strict action against those cheating people in name of overseas jobs: CM Yogi | Impact of CM Yogi’s vision becomes visible: Rural women earning up to Rs 2.5 lakh by becoming self-reliant | Mann Govt advances citizen-first revenue administration in Punjab | Dhami inaugurated ‘Mushroom Gram’ in Buggawala, new initiative to increase farmers' income | Haryana implements revised guidelines & SOPs to support poor prisoners | The layers of pollution and the difficulty of farmers | The Aravallis: Protected in Spirit, Vulnerable in Law | Back Issues  
 
news details
Chief Secretary reviews progress of USB Rail Link Project
70 per cent tunneling work completed on Udhampur-Srinagar-Baramulla rail link project
7/5/2019 10:25:10 PM
Early Times Report
SRINAGAR, July 5: Chief Secretary, B V R Subrahmanyam chaired the Apex Committee meeting to review the progress of the Udhampur-Srinagar-Baramulla Rail Link (USBRL) Project.
Principal Secretary, Home , Financial Commissioner Revenue, J&K, Principal Secretary, Planning Development & Monitoring Department, Administrative Secretaries of the Departments Forest, Ecology & Environment, PDD, Revenue and Tourism, Divisional Commissioner, Kashmir, Chief Administrative Officer (CAO), USBRL Project, Deputy Commissioner, Srinagar, Deputy Commissioner Budgam and other senior officers and representatives of Railway Authorities were present in the meeting.
Divisional Commissioner, Jammu, Deputy Commissioner, Ramban and Deputy Commissioner, Reasi participated in the meeting through video conferencing.
CAO, USBRL Project informed the Committee that out of the total 272 Km Rail line between Udhampur and Bramulla, 111 Km stretch between Katra and Banihal remains to be connected. The stretch has tunnels in 97 Km length and surface Rail line on 14 Kms. He said 67 Km long escape tunnels are also being provided alongside the main tunnels.
Regarding progress of work on the 111Km Katra-Banihal stretch, CAO, USBRL Project informed that 67 Km construction work of the main Tunnels has been completed along with 30 Km of the escape tunnels. He said work on the project is going on smoothly. However, certain issues requiring intervention of the State Government are projected for early resolution.
To expedite the resolution of the issues and completion of the Project, Chief Secretary directed the Railway Authorities to submit on every Monday by 11:00 AM, a weekly progress report along with details about bottlenecks/stoppages, if any, encountered during the previous week to his office, Principal Secretary, Home, Divisional Commissioner, Jammu, IGP Jammu and concerned DCs/SSPs. He asked the Railway Authorities to first seek resolution of the issues with the concerned DCs and Divisional Commissioner, Jammu before referring them to Government.
In order to put in place a coordination mechanism at the district level for the USBRL Project, State Government will constitute Committees of Deputy Commissioners of Ramban and Reasi with District SPs, concerned Revenue Authorities etc and representatives of IRCON and KRCL as members to review the progress of work every week and discuss resolution of issues, if any.
Timelines were also fixed by Chief Secretary for time bound resolution and completion of the few pending land acquisition, utility shifting and compensation issues in Reasi, Ramban and Budgam districts.
  Share This News with Your Friends on Social Network  
  Comment on this Story  
 
 
 
Early Times Android App
STOCK UPDATE
 
 
 
 
 
 
 
   
Home About Us Top Stories Local News National News Sports News Opinion Editorial ET Cetra Advertise with Us ET E-paper
 
 
J&K RELATED WEBSITES
J&K Govt. Official website
Jammu Kashmir Tourism
JKTDC
Mata Vaishnodevi Shrine Board
Shri Amarnath Ji Shrine Board
Shri Shiv Khori Shrine Board
UTILITY
Train Enquiry
IRCTC
Matavaishnodevi
BSNL
Jammu Kashmir Bank
State Bank of India
PUBLIC INTEREST
Passport Department
Income Tax Department
JK CAMPA
JK GAD
IT Education
Web Site Design Services
EDUCATION
Jammu University
Jammu University Results
JKBOSE
Kashmir University
IGNOU Jammu Center
SMVDU