Breaking News :   Youngsters must inculcate ancient values, ideals in present-day life: LG Sinha | Betrayal for lakhs: Kashmir youth duped in fake Railway jobs scam | LBA rift widens: Kargil unit cries foul over ‘unconstitutional’ ouster of vice-president | NIA to grill Naseer Bilal for 7 more days | Several flights cancelled at Srinagar Airport | Dense fog keeps visibility low in Delhi | Lok Sabha adjourned sine die | CM Omar meets Union Jal Shakti Minister | Pharma company owner arrested on drug trafficking charges | Searches launched in Rajouri villages | Cold conditions intensify in Kashmir | DC Doda reviews functioning of SPCA | DC Rajouri reviews winter preparedness, issues comprehensive directions to line departments | Doda admin launches Sushasan Saptah with wide-ranging good governance initiatives | Artificial Intelligence and the Evolving Role of Teachers | India’s future is at stake: Premature Old Age among young people and increasing burden from the elderly | Twenty first century warfare | 16th State Speedball Championship 2025 declare open by Dr Koshal Kumar Sharma, SSP | Action taken by centre to resolve Ladakh's issues will be in UT's interest: LG Gupta | Samba police attaches property worth Rs 46.48 lacs of notorious drug peddler under NDPS Act | Mohd Suleman Choudhary chairs review meeting to assess preparedness in view of adverse weather forecast | Anantang police organised awareness programme, drawing competition | Samba police seizes 5 dumpers for illegal mining | Narayana Hospital & CGPWA organize Free ENT Camp today | CAT raps School Edu Dept over transfer of 70% disabled lecturer, orders ramps in all schools | Deputation meets Chief Secretary; raises concern over mass mortality of sacred fish at Martand Mattan | Lack of basic facilities at Udhampur Sports Stadium raised with leader of opposition | Suresh Sharma kick started blacktopping work in Chowki Choura | Pravasi Panchayats should be organised across the state to promote reverse migration: CM Dhami | ICAMEES 2.0 at UPES brings together 200+ researchers to shape sustainable technologies | Kavi Darbar held at Dera Baba Singh Bahadur Reasi | Stupendous success of ‘Bring Dry Paddy in Mandis’ campaign propelled success of paddy procurement season | Yogi Government's major initiative: MICE Incentive Scheme to provide a global platform for MSMEs | Back Issues  
 
news details
Ganai sets November 2019 deadline for completion of college buildings
7/12/2019 10:35:01 PM
Early Times Report

SRINAGAR, July 12: Advisor to Governor Khurshid Ahmad Ganai today chaired a meeting here to take stock of the progress on construction of Polytechnic Colleges in the State wherein he directed the executing agencies to expedite work on the prestigious projects and complete them by November 2019.
The meeting was attended by Managing Director JKPCC M. Raju, Secretary Technical Education Zubair Ahmad, Additional Secretary Technical Education Niraj Kumar, Director Technical Education Dr. Ravi Shankar Sharma, Chief Engineer R&B Kashmir Sami Aarif, CE R&B Jammu Nasir Goni, General Manager (Central) JKPCC Harkewal Singh and other concerned.
During the meeting, Advisor Ganai enquired about the progress made on the construction of each Polytechnic College in the State. It was said that of 18 Colleges, 10 have been awarded to J&K Projects Construction Corporation, 6 to PWD (R&B) and one each would be built by Islamic University of Science and Technology, Awantipora and Baba Ghulam Shah Badshah University, Rajouri.
The expenditure registered on both the civil and mechanical components at each location was ascertained. Ganai instructed the executing agencies to expend the funds kept for both the components strictly as per the set plan. He was informed that some of the colleges have already been completed and handed over to the Technical Education Department while rest are in final stages of completion.
Secretary Technical Education informed the meeting that colleges handed over to the Department have already been made functional. He also said that the Department has already initiated the process of purchasing machinery and equipment for rest of the colleges nearing completion. He assured that these would be started expeditiously after taking over from the executing agencies.
Managing Director, JKPCC briefed the meeting that colleges at Udhampur, Kupwara and Bandipora would be handed over till August 15 this year while others would be handed over within the specific deadline. The concerned Chief Engineers also told the meeting that necessary steps would be taken to meet the deadline of November 2019.
The meeting was also informed that each college was to be constructed at an estimated cost of Rs 13 crore but due to various issues like land disputes and other additional allied works, escalation of costs has been registered at many places.
The Advisor called for reports against each such case and said that same needs to be diligently justified before the project committee for evaluation.
The Advisor said that these colleges have an important role in producing professionals having requisite skills and technical training to meet the market requirements. He urged the officials to introduce those courses that have greater viability and demand among the student community.
  Share This News with Your Friends on Social Network  
  Comment on this Story  
 
 
 
Early Times Android App
STOCK UPDATE
 
 
 
 
 
 
 
   
Home About Us Top Stories Local News National News Sports News Opinion Editorial ET Cetra Advertise with Us ET E-paper
 
 
J&K RELATED WEBSITES
J&K Govt. Official website
Jammu Kashmir Tourism
JKTDC
Mata Vaishnodevi Shrine Board
Shri Amarnath Ji Shrine Board
Shri Shiv Khori Shrine Board
UTILITY
Train Enquiry
IRCTC
Matavaishnodevi
BSNL
Jammu Kashmir Bank
State Bank of India
PUBLIC INTEREST
Passport Department
Income Tax Department
JK CAMPA
JK GAD
IT Education
Web Site Design Services
EDUCATION
Jammu University
Jammu University Results
JKBOSE
Kashmir University
IGNOU Jammu Center
SMVDU