Breaking News :   Indian Chamber of Commerce (ICC) Jammu (Jammu & Kashmir) | Under CM Yogi Adityanath's leadership, UP has delivered outstanding results under the Pradhan Mantri Surya Ghar Yojana | Jammu Police give big blow to commercial supply chain of Narcotics! | Instructions on using Aadhaar as proof of identity, not citizenship, already issued: EC to SC | Leopard found dead in Poonch | Javid Dar expresses deep grief on loss in Nowgam accidental blast | AIIMS Jammu invites diaspora medical professionals to strengthen healthcare back home | Div Com, Deputy Commissioner visit SMHS, Ujala Hospitals; enquire about well-being of injured persons | Substandard meat seized; fines imposed on retail shopkeepers | Sakeena Itoo visits Ujala Cygnus Hospital, enquires about wellbeing, treatment of injured persons of Nowgam explosion | The double-engine government ensures the security, dignity, and self-reliance of tribal communities: CM Yogi | Raffa Boules India Federation honours Dr Turkman, president of CBI | GDC Hiranagar organized Skill Development Workshop on Horticulture Techniques | UPES, in association with ISRO, AIAA, ISpA, IN-SPACe & SIA-India, organises a flagship convention to promote aerospace innovation | Humanity Public School celebrated Bal Mela to commemorate Children's Day | MCM marks National Cyber Security Awareness Month | Our great gurus have always shown path of social equality, brotherhood: Swami Suchetanand | GNDU signs MoU with Spring Dale Senior School to strengthen Special Education and Professional | Police tightens noose on illicit liquor trade | Two-day ICSSR-sponsored seminar on "Emerging Fields in Education Research held | Children's Day celebrated at SD Tara Puri Public School, Gandhi Nagar | Special ticket checking campaign conducted | Jammu District Netball Championship concludes | Ayush Wellness Camp organized at Vishavkarma Temple, New Plot | DAV College Hosts "Buildathon," Fostering Innovation and Startup Spirit Among School Students | Jharkhand Foundation Day celebrated at LG Secretariat | Dr Ashu Sharma youth president of Dogri Bhasha Academy conferred with the PhD degree | UGC-supported 19th NEP Orientation & Sensitization Program conducted at SMVDU | 9 killed, 32 injured as seized explosive detonates at Nowgam Police Station | LG visits hospitals, meets injured | LG Sinha, CM Omar mourn loss of lives | Farooq demands thorough probe | Explosives transported from Faridabad in pickup truck | CM promises compensation for damaged buildings | DGP, IGP visit site, review damage | Dr Muzaffar emerges as kingpin of ‘white coat’ terror module | 2 more Al Falah University doctors among 3 held | Cops track down parked vehicles, quiz drivers | After Bihar disaster, pressure mounts on J&K Cong | Jammu Police solve Ring Road burning case | Back Issues  
 
news details
Delay in bunkers construction annoys residents in J&K's bordering districts
9/18/2019 10:08:01 PM
Early Times Report
Jammu, Sept 18: The delayed project of bunkers construction along the International Border and the Line of Control in five districts of Jammu region has annoyed the border residents as they alleged that due to regular ceasefire violations by the Pakistan, they are living under the shade of fear psychosis and their lives under threat.
The Government of India had announced 10,000 bunkers in Jammu region two years back and the project was supposed to be completed by April 2019 but it got delayed and only 3,000 to 3,500 bunkers are ready in all the five bordering districts of the region.
"Two years are on but the bunkers project is yet to be completed," sources said.
They said that out of total 10,000 bunkers, around 3,000 to 3,500 are ready and rest are under construction.
"There are many reasons responsible for the delay in completion of the project," sources said and added that the government claimed that the entire project will be finished by 2020 ending and in Jammu district, as many as allotted number of bunkers will be completed by November this year.
The bunkers are being constructed in Jammu, Samba and Kathua districts along International Border and in Rajouri, Poonch districts along the Line of Control.
"Regular ceasefire violations by the Pakistan, non acquisition of land at some places, non release of funds to the executing agencies are among some of the major reasons behind delay in project," sources added.
However, the border residents have expressed annoyance over delay as they claimed that life along borders is not peaceful and they are always scared of shelling from across the border.
As per official sources, in Jammu, 1,200 bunkers are to be made but around 700 are ready and the district administration has claimed of competing them by November this year.
In Kathua, 1976 are to be made but only 700 are ready. Due to some technical error in the designs of the bunkers, delayed the project, they added.
As per Kathua administration, by July this year, as many as 918 individual and 70 community bunkers are completed along the International Border. It was informed that a total of 2,126 bunkers are being constructed including 1956 individual and 170 community bunkers. Of these, 918 individual bunkers and 70 community bunkers have been completed official spokesman.
In Samba, 1,900 are to being made and out of them 1,000 are ready, sources said and added that due to non availability of land in many households, the construction project delayed and the locals appealed the government to allot land for bunkers.
In Rajouri, out of 2,806 only 914 are ready, they added and said that the project was handed over to two executing agencies, due to which, the project delayed besides, inclement weather conditions.
In Poonch, out of total 375 bunkers, only 150 are ready as the work was affected many times due to bad weather and heavy shelling by the Pakistan.
"The wok on construction of bunkers is in full swing and the task will soon be accomplished," Sanjeev Verma, Divisional Commissioner, Jammu here told .
He added that in Jammu, bunkers will be completed by ending year while the target of completing the project will be achieved by 2020.
  Share This News with Your Friends on Social Network  
  Comment on this Story  
 
 
 
Early Times Android App
STOCK UPDATE
 
 
 
 
 
 
 
   
Home About Us Top Stories Local News National News Sports News Opinion Editorial ET Cetra Advertise with Us ET E-paper
 
 
J&K RELATED WEBSITES
J&K Govt. Official website
Jammu Kashmir Tourism
JKTDC
Mata Vaishnodevi Shrine Board
Shri Amarnath Ji Shrine Board
Shri Shiv Khori Shrine Board
UTILITY
Train Enquiry
IRCTC
Matavaishnodevi
BSNL
Jammu Kashmir Bank
State Bank of India
PUBLIC INTEREST
Passport Department
Income Tax Department
JK CAMPA
JK GAD
IT Education
Web Site Design Services
EDUCATION
Jammu University
Jammu University Results
JKBOSE
Kashmir University
IGNOU Jammu Center
SMVDU