Breaking News :   Article 370 abrogation brought dynamic change in J&K: LG Sinha | ‘Young generation true inheritor of eternal traditions’ | Over speeding kills: 98% road deaths in J&K linked to rash driving | Cong disowns SC cell chairman; Bhagat hits back at Karra | CM Omar reviews J&K’s overall fiscal position | 2 J&K natives arrested for espionage | Aadhaar OTP verification now in 322 trains | ‘Secure schools, hospitals, stadiums from stray dogs’ | GoI cancels 3.6 lakh MGNREGA job cards in J&K, Ladakh | Teacher suspended for misconduct | Kulgam Police tighten noose on narco-network | Chinese national deported for visa violations | The skill of letting Go: A guide to Intentional attention | Tradition in transition: How Indian handicrafts are shaping a modern design identity | Remarkable Move | Lawrence Public School, concludes 40th anniversary celebrations | Digital transformation is no longer a choice - it is spine of modern banking : MD & CEO | BJP levels allegations on NC | Pardeep Sharma urged citizens to adopt ‘Har Ghar Swadeshi, Ghar-Ghar Swadeshi’ campaigns | HC dismisses bail Plea in NDPS Case | JKPDD launches massive energy conservation campaign | Heritage luxury showroom ‘Rouche’ opened in Jammu | Power Shutdown by KPDCL | Div Com Kashmir reviews Jal Shakti Department, calls for timely completion of AMRUT 2.0 projects | Tawi Welfare Society’s Sweater distribution drive held | J&K police arrested absconding person in recovery warrant at Billawar | CEPC announces results of elections of Chairperson and Vice Chairperson | Jammu (Rural) police crack down on vehicles brought from outside | Noida International Airport set to be global landmark, combining Swiss efficiency with Indian hospitality | West Zone Inter-University Volleyball (Men) begins at LNCT | Doda police traced missing lady, reunited her with family | Ramban police arrest woman for possession of Charas; 528 grams recovered during raid | J&K police conduct searches at locations linked to banned Tehreek-E-Hurriyat in Sopore | Budgam police books homestay owner for concealing stay of foreign national | For first time in history Magh Mela unveils official logo released at Chief Minister's level | Traffic police challan 27 vehicles, impose Rs 49,800 penalty; one vehicle seized | MLA Bahu Ch Vikram Randhawa conducts intensive tour of Ward No. 43, Nanak Nagar | SIA Jammu succeeded in attachment of an immovable property | Khatana raises concern over slowdown in Forest Rights Act implementation in J&K | AAI senior management conducts inspection at Jammu Airport | SSP Reasi interacts with VDG; reviews their deployment & firing practice | DyCM Choudhary highlights NC Govt's developmental achievements in Naushera rally, stresses unity and pluralism | 6 vagrants detained by Samba police, sent to District Jail Kathua | UNESCO Honour for Deepavali is Modi's cultural Masterstroke: Gaurav | High Court of J&K, Ladakh declares Dec 20 as working day | Indian Railways strengthens ticket reservation system with Robust Cyber Security | PTTI Vijaypur organizes lecture on Cyber Crime/Cyber Security | Back Issues  
 
news details
Multi level parking at Bus Stand Jammu misses another deadline
10/10/2019 12:42:15 AM

Early Times Report

Jammu, Oct 9: After missing the fixed first three year deadline of 2019, the much awaited multi storied parking project at General Bus Stand Jammu has missed another deadline of September this year.
Sources informed Early Times that the proposed multi storied parking which was supposed to reduce traffic congestion and provide much needed parking space to Jammuities by accommodating 1300 cars and will provide access corridor to 80 buses, one taxi stand and an air-conditioned ticket booking office as well as waiting hall for the commuters but ironically inordinate delay in completion of the mega project, the Jammuities have been depriving to avail facilities.
Sources further said that the multi storied parking project was put forth by National Conference -Congress coalition government in 2010-2011 and in month of September, 2014 the then chief minister, Omar Abdullah had laid the foundation stone and announced that the project would be completed within three years.
"Unfortunately, after changing of guard at State level, the new government of BJP-PDP had once again laid foundation stone of the same project in month of October by then Chief Minister Mufti Mohammed Syeed and then Minister Local Bodies, Dr Nirmal Singh and announced that the same project would be completed in month of April, 2019", said sources while wishing anonymity.
After missing April, 2019 deadline, the executing agency fixed one more deadline of five month and announced that the project would be completed in September, 2019 but ironically the same project is still incomplete.
"However, the project is supposed to connect with six flyover, but the connecting work with flyover is yet not started and hopefully would be initiated soon ", said an official on the condition not to mention here and added that if the work is done on war-footing by the construction agency, hopefully the project handed over to Jammu Development Authority by January, 2019.
  Share This News with Your Friends on Social Network  
  Comment on this Story  
 
 
 
Early Times Android App
STOCK UPDATE
 
 
 
 
 
 
 
   
Home About Us Top Stories Local News National News Sports News Opinion Editorial ET Cetra Advertise with Us ET E-paper
 
 
J&K RELATED WEBSITES
J&K Govt. Official website
Jammu Kashmir Tourism
JKTDC
Mata Vaishnodevi Shrine Board
Shri Amarnath Ji Shrine Board
Shri Shiv Khori Shrine Board
UTILITY
Train Enquiry
IRCTC
Matavaishnodevi
BSNL
Jammu Kashmir Bank
State Bank of India
PUBLIC INTEREST
Passport Department
Income Tax Department
JK CAMPA
JK GAD
IT Education
Web Site Design Services
EDUCATION
Jammu University
Jammu University Results
JKBOSE
Kashmir University
IGNOU Jammu Center
SMVDU