Breaking News :   Air Pollution Damaging Brain Health; Worsening Disease Burden in India | Ah, Appropriate Time ! | Health Of Citizens | Piyush Pandey Passes Away: Advertising Legend with a Heart and a Jammu and Kashmir Connection | Bickering erupts in Congress over appointment of Rajouri district chief | Sonu Nigam’s Srinagar concert will boost tourism, local artistes: LG Sinha | Mian Altaf backs Ruhullah, warns CM Omar on governance, jobs | MP Ruhullah hits out at CM Omar for mocking people who elected him | Mehbooba accuses NC of betraying Budgam | ‘Darbar Move’ to Jammu in full swing after 4-year break | True empowerment lies in health of citizens: Rajnath Singh | Study links bright light at night with 56% higher risk of heart failure | NC candidate who lost RS Poll says some MLAs promised support but ‘backstabbed’ | Op Sindoor, eradication of Naxalism added colour to festivals: PM Modi | 3 drug peddlers held | BSF seizes pistols, drones, heroin | Mahindra Scorpio JK14A-7380 seized for illegal Khair Billets Transport | NC Minority Wing holds meeting, urges support for Aga Syed Mehmood in Budgam By-Election | EC to hold presser on pan-India SIR of voters' list on Monday evening: Officials | Garhmukteshwar fair to reflect devotion, discipline and cleanliness: CM Adityanath | J&K witnessing transformation from separatism to self-reliance under PM Modi: Tarun Chugh | Century Bank Brokers hold meeting | Delhi man arrested for robbing, abducting truck driver; four absconding | Three killed, five injured as SUV rams into parked truck in UP's Jaunpur | Changemakers igniting transformation across Uttar Pradesh's villages | Peace Conference on Communal Harmony held to Mark Sir Syed's 208th Birth Anniversary | Modi govt has taken the health sector to new heights in 11 years: Balbir | Sarveshwar Group organised Basmati Export Promotion Programme | Accession Day celebrated at Udhampur | Centre has given Rs 4,500 crore to PWD since 2023: Himachal Pradesh minister | Unseasonal rains: 'Yellow' alert issued for Nanded between Oct 26-29 | Wanted criminal arrested by Delhi Police in Badarpur after brief encounter | Supplementary Randomization of EVMs Conducted at Budgam | JBM launched membership drive at Sunderbani | Jewar Airport to set a new benchmark in digital connectivity | IIPA J&K Regional Branch organizes lecture | Dr Tarunjit Singh Butalia receives lifetime achievement award at global interfaith conference | IWC Jammu Sampark visited Old Age Home Kot-Bhalwal | DC Baramulla chairs meeting at Gulmarg | Indian Army conducted a 30-day cutting, tailoring course for empowering women | United Nations Day Celebrated at Government High School, Upper Dharana at Rajouri | NFR to observe Vigilance Awareness Week | Indian Army on Alert for Cyclone "Montha" - Coordinated Readiness Along East and West Coasts | Rang-e-Chinar' 2.0 concludes at NIT Srinagar with vibrant performances, massive participation | Back Issues  
 
news details
11. 61 KM stretch nearing completion; work on 4.6 KM flyover under Package II in full swing
Jammu-Akhnoor 4-lane project
8/9/2020 1:21:32 AM
Early Times Report

JAMMU, Aug 8: The work on Jammu–Akhnoor Four lane project has gained substantial momentum with the execution of 31 percent work on Package II of the project which starts from 800 meters and ends at 6 km (from canal head to Ganesh Vihar). It includes construction of 4.6 km long flyover.
The flyover will have 126 foundations out of which 93 have been completed. Also the work on package III has gained pace which starts from Ganesh Vihar to Khati Chowk (km 06 to km 26.350).
The Deputy Commissioner, Jammu Sushma Chauhan, visited various construction sites and inspected the pace of progress on the project. ACR Jammu, Vijay Sharma, SDM Jammu North, Pawan Kotwal besides officers from PHE, PDD, NHIDC and other concerned departments also accompanied the Deputy Commissioner.
The senior functionaries of executing agency (NHIDCL Engineers) briefed the Deputy Commissioner Jammu about the work done so far.
The Deputy Commissioner was further informed by the Site Engineer that clearance of structures is complete with all the 580 structures having been cleared in last one year.
It was further told that over 90% land/structure compensation has been disbursed to the rightful claimants.
Giving further details, the DC was told that a total 11.618 km hindrance free stretch has been completed in the last one year.
The Shifting of PDD poles and the infrastructure of PHE department coming in the alignment of the project shall be completed in a scheduled manner.
The instructions have been issued by Deputy Commissioner to the concerned officers to adhere with the instructions and get the work completed in a time bound manner. The on spot directions have been issued to General Manager NHIDCL to improve the condition of in use service lanes.
The patch work shall be completed in a week’s time so that the general public may not suffer due to the poor condition of the road.
  Share This News with Your Friends on Social Network  
  Comment on this Story  
 
 
 
Early Times Android App
STOCK UPDATE
 
 
 
 
 
 
 
   
Home About Us Top Stories Local News National News Sports News Opinion Editorial ET Cetra Advertise with Us ET E-paper
 
 
J&K RELATED WEBSITES
J&K Govt. Official website
Jammu Kashmir Tourism
JKTDC
Mata Vaishnodevi Shrine Board
Shri Amarnath Ji Shrine Board
Shri Shiv Khori Shrine Board
UTILITY
Train Enquiry
IRCTC
Matavaishnodevi
BSNL
Jammu Kashmir Bank
State Bank of India
PUBLIC INTEREST
Passport Department
Income Tax Department
JK CAMPA
JK GAD
IT Education
Web Site Design Services
EDUCATION
Jammu University
Jammu University Results
JKBOSE
Kashmir University
IGNOU Jammu Center
SMVDU