Breaking News :   New freight train service big step for Kashmir apple growers: LG Sinha | LG attends closing ceremony of ‘Jashn-e-Dal’ | Will take up restoration of Jmu-Sgr highway with Union Minister: CM Omar | Cloudburst triggers flash floods in Reasi, no casualties | Day 21: Vaishno Devi Yatra remains suspended | Fruit growers’ union delegation meets LG | Doda: Educational institutions reopen after 3 weeks | Fraudster impersonating LG’s duty officer held in Rs 50 lakh scam: CBK | PM Modi lays foundation stone of projects worth around Rs 40,000 crore in Bihar | PM Inaugurates 16th armed forces’ conference at Eastern Command HQ | ITR filing deadline ends | DC Budgam calls for stronger enforcement & rehabilitation measures | DYSSO Samba launches major Inter-Zonal Sports tournament | Modi’s Governance: Gujarat Model to Bharatiya Model | Safety of Indians in America | Celebrating National Hindi Diwas | Parcel Train | FICCI FLO JKL rolls out Phase-4 of flood relief efforts in Jammu | Kuch Din Toh Aaiyein Ladakh Mein: LG Kavinder appeals in Navi Mumbai | Give your best to steer our nation ahead in growth & development: DyCM | MLA Sham Lal Sharma Pays Tribute to Sir M. Visvesvaraya on Engineers Day | Power shut down in several areas | Parcel cargo train from Kashmir to Adarsh Nagar Delhi flagged off | Javid Dar reviews status of NH-44 restoration | Only Aadhaar-authenticated users can book online general tickets in first 15 mins from Oct 1: Railways | DC Srinagar convenes DLSCC meeting | MLA Poonch, Ajaz Ahmed Jan offer condolences | Pakistan's terror nexus exposed again at UNSC: Gaurav | Randhawa reviews preparations at Bawe Wali Mata Mandir | Itoo flags off Dental Awareness Rally on Oral health hygiene | MLA Arvind Gupta inaugurates long-pending drain work at Rajpura | Boy injured in landmine blast in Anantnag, dies | Indian Army's first exclusive freight train on USBRL marks breakthrough | Punjab police busts cross-border weapon smuggling module with links to Pak | WPI inflation turns positive after 2 months, at 0.52% in August | SC to pass order on Sept 26 in suo motu case over lack of functional CCTVs in police stations | On Engineer's Day GCET Jammu inaugurates two-week induction programme | Crackdown on illegal mining continue on 2nd day | Ramban police recovers 30 lost mobile phones | Ravinder visits rain affected areas of Sunderbani, seeks relief, restorations on war footing | AIIMS Bathinda reaffirms zero tolerance for unethical practices | Indian Army organised interaction with prominent locals, media at Samote | JKEDI launches 3rd batch of Management Development Programs | GDC Bishnah celebrates Hindi Diwas in collaboration with J&K Rashtriya Bhasha Prachar Samiti | YCET conducts Induction Program | CCI raise serious issue of infrastructure crises | GCOE Jammu celebrates Hindi Diwas | MCM celebrates Hindi Diwas with fervour | Dogra Degree College celebrates Hindi Diwas | IIM Jammu hosts valedictory xeremony of Management Development Program on Corporate Governance | 3 cab drivers booked for violating traffic advisory, overcharging | Doda Police urges public to combat fake news, misinformation | PM Modi at 75: A legacy of vision, valor, Nation-Building: Rohiin Chandan | IRCS J&K provides relief material to flood-affected | JKAACL Jammu organizes one day symposium | Principal Secretary, Culture inaugurates hindi Pakhwada at K.L. Saigal Hall | SP North Vivek Shekhar Sharma releases devotional bhajan “Lad Fadeya Mahamai Da” | IGNOU Jammu successfully concludes Swachhata Pakhwada, reaffirming commitment to cleanliness | Back Issues  
 
news details
Div Com Jammu reviews progress on Mega projects
10/22/2020 12:31:56 AM
Early Times Report
JAMMU, Oct, 21: Divisional Commissioner, Jammu Sanjeev Verma, today reviewed the physical and financial progress on mega projects which include AIIMS Samba, Boundary wall and alternate road to IIM, 100 bedded hospital at Kot Bhalwal, and Government Ayurvedic Medical College cum Hospital at Akhnoor.
Chief Engineer, PWD (R&B), Ashok Kikroo; Project Engineer, IIM Rakesh Shami; Superintendent Engineer, JKPCC, Har Kewal Singh; EE&SMC CPWD, Jammu, Gurvinder Singh; Executive Engineer, R&B, Rajesh Kumar Bhagat; Assistant Executive Engineer, J&K Housing Board, Deepak Digra and Executive Engineer PSM, AIIMS CPWD. Hukmi Chand and other concerned officers attended the meeting.
The R&B Chief Engineer gave a brief about the progress on construction work on the 5.65 Kilometer long precast panel compound wall at permanent campus of IIM Jammu at Jagti Nagrota. It consists of a precast panel concrete wall of 4.34 Kilometer and chain link fencing of 1.30 Kilometer. The project costing Rs. 17.78 crore is targeted to be completed by January 31, 2021. At present 2.0 Kilo meter boundary wall is complete and the construction work of remaining length is also completed upto plinth level/column level.
The progress of the work is in full swing post covid lockdown and from 1st September to 20th October, 2020, around 820 meter length of precast panelled wall and 200 meter length of chainlink fencing was completed. the total achievement of work is 70 percent completed physically till date. He said that the works are being monitored regularly and stress is being laid on their timely completion the projects.
The Divisional Commissioner stressed the need for close monitoring and coordination among government departments and executing agencies for the timely completion of development projects. He called for adhering to all parameters of architectural values use of construction material. He laid special emphasis on regular monitoring and ensuring quality of works.
The Divisional Commissioner also reviewed the physical status of construction of 100 bedded hospital Kot Bhalwal, Jammu and Government Ayurvedic College cum Hospital at Akhnoor. He called upon the concerned officers to speed up the progress and complete the projects in the stipulated time frame.
The concerned officer gave a detailed overview of the projects and informed that the work is almost 90 percent complete . The estimated cost of the 100 bedded hospital is Rs. 21.46 crore, while the Government Ayurvedic College cum Hospital is coming up at a cost of Rs. 25.80 crore.
  Share This News with Your Friends on Social Network  
  Comment on this Story  
 
 
 
Early Times Android App
STOCK UPDATE
  
BSE Sensex
NSE Nifty
 
CRICKET UPDATE
 
 
 
 
 
 
 
 
   
Home About Us Top Stories Local News National News Sports News Opinion Editorial ET Cetra Advertise with Us ET E-paper
 
 
J&K RELATED WEBSITES
J&K Govt. Official website
Jammu Kashmir Tourism
JKTDC
Mata Vaishnodevi Shrine Board
Shri Amarnath Ji Shrine Board
Shri Shiv Khori Shrine Board
UTILITY
Train Enquiry
IRCTC
Matavaishnodevi
BSNL
Jammu Kashmir Bank
State Bank of India
PUBLIC INTEREST
Passport Department
Income Tax Department
JK CAMPA
JK GAD
IT Education
Web Site Design Services
EDUCATION
Jammu University
Jammu University Results
JKBOSE
Kashmir University
IGNOU Jammu Center
SMVDU