Breaking News :   India's COVID-19 caseload nears 95-lakh mark with 36604 new infections | Senior doctor ignored, junior becomes Principal GMC Jammu | BJP ‘double-minded’ to act against ‘potential’ rebels | Several PMGSY projects hang in balance as release of funds delayed | Now demand for details of funds collected for Rasana victim gains momentum ! | Washed away in 2014 Digwar bridge still awaits reconstruction | People accuses doctor of abandoning patients for sake of private practice | Govt schools go smart in Srinagar, remain ‘dull’ in Jammu! | COVID-19 recovery rate in JK reaches 94% as 503 more patients get discharged; 454 new cases, eight fresh deaths | Fire extinguishers pose threat to lives at MCH Anantnag | Show Some Respect | Progress of Education in India | Black deeds under ‘Roshni’-B | Munish Gupta asks government to solve problems of people of Sector A Shastri Nagar | Advisor Baseer Khan reviews PMAY (G), MGNREGA, Panchayat Ghars | Pvt Schools indulging in organized loot, Govt unconcerned: Parents Association | Election Commission will take final call on assembly polls in J-K: Sharma | Army gears up to fight ‘weather blues’ on Mughal Road | Shehla 'episode' proof of youth playing in hands of anti-nationals: Kavinder | Cabinet Secy reviews arrangements for COVID-19 vaccine roll-out in J&K | BJP will not tolerate Pakistan''s policy of bloodshed in J-K: Raina | PDP, NC fighting against each other in triangular contest | CS chairs maiden meeting of UT Steering Committee ON COVID Vaccination | Implementation of Central scheme of financing facility under AFI | ACB files charge-sheet against then DSWO Kupwara, ors in illegal appointment case | 2nd phase of DDC election register around 49% of voter turnout in J&K | 69.66% polls recorded in Bandipora for second phase of DDC elections | Only one-way traffic on Leh, Kashmir highways; Mughal road shut | Tarigami moves SC challenging MHA order on land purchase | People in Kashmir angry after abrogation of Article 370, claims Soz | BJP hopeful of thumping victory in Chenani-Kud constituency | Corporator Ritu Choudhary inaugurates drain, tiles work | People craving to see change through DDC polls: Raman Suri | DDC Poll results to decide fate of Jammuites: TMF | Bhim Singh appoints Saddam as Gen Secy | Court rejects bail in NDPS Act | National Sikh Font expresses gratitude for Guru Nanak Dev Chair | YCET concludes Induction Programme | Pathseekers celebrate Guru Nanak Dev Ji birth anniversary | Srishti represents India at 6th BRICS Youth Summit | Omma Productions launches short Dogri musical film | Mayor kick starts development work in Janipur area | CCA office organises Pensioners Camp | Educational institutions observe “World AIDS Day” | Nat Manch performs nukkad natak on World AIDS Day | Shiksha Niketan organizes online Fancy Dress competition | JU organizes webinar on topic "Gulzar Ki Treweni" | Sri Sri Ravi Shankar calls for more research on AYUSH medicine for COVID-19 | GDC Ramgarh organises "Manodarpan" | GDC Vijaypur organizes online poster making, slogan writing competition | Army to hold recruitment rally for 10 Jammu distts in Feb-March | Power shut down | Attention GP Fund Subscribers of Jammu District | Back Issues  
 
news details
PWD executes hundreds of road works without DPRs
11/22/2020 12:00:57 AM
Early Times Report

Jammu, Nov 21: The Public Works Department (PWD) has come under scanner for its irrational functioning by executing hundreds of road works amounting to crores without Detailed Project Reports and administrative approval in violation of rules and regulations.
Moreover, the casual approach of the department in taking up road projects without following guidelines has increased the risk of abandonment of many projects.
Sources said that over 200 road works were executed without DPR on which expenditure of Rs 250 crore was incurred and most of the road projects were not administratively approved by the competent authorities.
They further informed that around 130 projects were taken up in Jammu district without DPRs.
Similarly 50 projects in Rajouri, 10 projects in Poonch, 35 projects in Kathua and many projects in Kashmir division were taken up.
Sources informed that as per guidelines envisaged in Financial Code no works should be commenced or liability incurred in connection with it until Administrative Approval has been obtained from the authority appropriate in each case sanction, either special or general, of competent authority authorizing the expenditure has been obtained, and a properly detailed design and estimate supported by complete details such as schedule of all items, quantities, rates, cost, drawings, specifications, rate analysis etc., has the sanction of the competent authority.
They further said that it has been observed that departments always adopt prohibited methods by preparing abstract costs of these works and by sending the same to higher authorities and after which funds are released. But the fact of the matter is that execution of works in the absence of Detailed Project Report and Administrative Approval cannot be taken up for execution.
  Share This News with Your Friends on Social Network  
  Comment on this Story  
 
 
 
Early Times Android App
STOCK UPDATE
  
BSE Sensex
NSE Nifty
 
CRICKET UPDATE
 
 
 
 
 
 
 
 
   
Home About Us Top Stories Local News National News Sports News Opinion Editorial ET Cetra Advertise with Us ET E-paper
 
 
J&K RELATED WEBSITES
J&K Govt. Official website
Jammu Kashmir Tourism
JKTDC
Mata Vaishnodevi Shrine Board
Shri Amarnath Ji Shrine Board
Shri Shiv Khori Shrine Board
UTILITY
Train Enquiry
IRCTC
Matavaishnodevi
BSNL
Jammu Kashmir Bank
State Bank of India
PUBLIC INTEREST
Passport Department
Income Tax Department
JK CAMPA
JK GAD
IT Education
Web Site Design Services
EDUCATION
Jammu University
Jammu University Results
JKBOSE
Kashmir University
IGNOU Jammu Center
SMVDU