Breaking News :   Exit Polls Turned Exact Polls | The field of Ayurvedic Medicine is full of Opportunities | TB-Free Jammu & Kashmir : How NHM turned a national mission into a people’s movement | Jaishankar’s Reminder | Arrested terrorist was building drone bombs for pan-India attacks | CIK foils attempt to recruit females in terror groups on instruction of ‘Madam Surgeon’ | Police, admin check lockers at SMGS Hospital | Video glorifying suicide attack found in bomber’s phone | Delhi Court remands co-conspirator to 10-day NIA custody | ED raids trustees, promoters of Al Falah University | Remain ready to meet evolving security challenges: Northern Army Commander to soldiers | 3 convicted in 2016 Doda murder case | Govt issues advisory after TV channels carry reports on making explosives | J&K’s power demand likely to surge by 50% in a decade | ‘Zero tolerance, no whitewashing’: Jaishankar on terrorism at SCO meet | 3 IPS officers transferred to J&K | 255 Pak drones neutralised in 11 months: BSF | 3 injured in wild boar attack | NFR enhances renewable energy footprint with 11.95 MWp solar installations across its zone | Chief Secy visits Sujeet Mattoo's residence to offer condolences on mother's demise | Gandhi Nagar police achieves major success in operation Meghdoot | India speaks loud and clear, no whitewashing of terrorism: Gaurav | Apni Party voiced deep concern over recent car blast in New Delhi | MLA Bahu Vikram Randhawa launches multiple development works | JKAS officer, VLW granted pre-arrest bail | IWMP Udhampur hosts awareness programme at Kallar | Gupta urges workers to remain steadfast; renews call for J&K statehood | HC denies bail to two NDPS accused, flags commercial quantity & repeat offending | Two get 10 years, one 2 years as Bhaderwah Court decides 2016 killing | No major snowfall expected in J&K before Dec 15: Sonam Lotus | One dead, two rescued as truck falls into gorge on Srinagar-Jammu Highway | Security tightened at Vaishnodevi; shrine board orders additional deployment, verification drive | X down for thousands globally, users report error loading posts | PM to inaugurate natural farming summit, to release aid under PM-Kisan in Coimbatore on Nov 19 | Two inter-district drug peddlers arrested with poppy straw at Chenani by Udhampur police | PU Vice-Chancellor calls for Neuroscience Education to Build Sustainable Brain Health | Over 2.15 crore farmers in Uttar Pradesh to receive 'PM Kisan Samman Nidhi' | Traffic police advisory for 19th November 2025 | Nationwide protest against 25 percent increase in kilometer rates for running staff | DC Rajouri receives national honour from President of India for Excellence in Jal Sanchay Jan Bhagidari | The new Uttar Pradesh has zero tolerance for crime: Chief Minister | Reasi police nab drug peddler, heroin-like substance seized | Back Issues  
 
news details
CS, Secy MoRTH review Road Sector Projects under PMDP in J&K
CS asks for parking bays/toilets on national highway; urges completion of works within timelines
9/14/2021 10:37:00 PM
Early Times Report
SRINAGAR, Sept 14: The Chief Secretary, Dr. Arun Kumar Mehta and Union Secretary, Ministry of Road, Transport & Highways, Giridhar Aramane, today in a high-level meeting reviewed the implementation of road sector projects in Jammu and Kashmir under Prime Minister's Development Package (PMDP).
During the meeting, it was observed that substantial progress has been achieved in the widening of National Highway-44, including in the completion of Chenani-Nashri and Qazigund-Banihal sections on the highway.
It was further observed that the remaining works on Udhampur-Ramban section, Ramban-Banihal section and Srinagar-Banihal section are also going on in full swing and are expected to be completed in the next year.
It was informed that works on Baramullah- Gulmarg road are in full swing and are likely to be completed by April 2022.
Similarly, works on Jammu semi-ring road and Jammu-Akhnoor-Poonch road have been accelerated and are expected to be completed in March 2022, and March 2024, respectively.
It was informed that work on Srinagar-Shopian-Qazigund road will also commence soon with the construction of 3 by-pass roads for Pulwama, Kulgam, and Shopian towns.
While stating that the national highway is relatively in better shape due to improved maintenance, Mr Mehta emphasised that the Ramban-Banihal segment is the most critical section on the National Highway and requires the focused attention for early execution of works related to tunnels and re-alignment of land slip prone stretches.
He also pitched for the development of parking bays and toilet facilities on the national highway to improve the travel experience of the commuters.
It is expected that these facilities will come up by November end 2021.
The Union Secretary, MoRTH asked the project executing agencies to lay special emphasis on quality of works and conduct quality inspections for completed works.
While highlighting that works may suffer in some areas in J&K in winter due to harsh weather conditions, Mr Mehta urged the agencies to make all out efforts to expedite the construction works so that all the works are completed within the timelines. He assured the project executing agencies of all the support from the UT administration in the execution of works.
  Share This News with Your Friends on Social Network  
  Comment on this Story  
 
 
 
Early Times Android App
STOCK UPDATE
 
 
 
 
 
 
 
   
Home About Us Top Stories Local News National News Sports News Opinion Editorial ET Cetra Advertise with Us ET E-paper
 
 
J&K RELATED WEBSITES
J&K Govt. Official website
Jammu Kashmir Tourism
JKTDC
Mata Vaishnodevi Shrine Board
Shri Amarnath Ji Shrine Board
Shri Shiv Khori Shrine Board
UTILITY
Train Enquiry
IRCTC
Matavaishnodevi
BSNL
Jammu Kashmir Bank
State Bank of India
PUBLIC INTEREST
Passport Department
Income Tax Department
JK CAMPA
JK GAD
IT Education
Web Site Design Services
EDUCATION
Jammu University
Jammu University Results
JKBOSE
Kashmir University
IGNOU Jammu Center
SMVDU