Breaking News :   Treat armed terrorists, their supporters, OGWs equally: LG Sinha tells top security brass | NIA nabs 9th accused from Delhi, tightens grip on terror conspiracy | BJP gears up for ULB elections | J&K Govt mandates GPS, RFID for mineral transport vehicles | HC announces winter vacation schedule | 40 lakh annual FASTag passes issued since August: Gadkari | ACB files chargesheet against PDD meter reader | Kashmir braces for ‘Chillai-Kalan’ | File annual property returns online by Jan 31: Govt directs employees | Culture is the soul of the nation: CM Yogi Adityanath | Human solidarity: The last hope for a fragmented world | Six interesting facts about Srinivasa Ramanujan | Collective Effort Is The Way Forward | SS Sodhi Graces 68th National Shooting Championship Finals | CM Yogi govt to gift 1.5 lakh govt jobs to youth in 2026 | LG Kavinder Gupta releases 'Celebrate Ladakh' Calendar; UT Administration declares nine UT-Level Festivals to boost year-round Tourism | JMC Commissioner inspects green strip, canal walkway at Bagad Mandi | Jammu West set to become model constituency through development initiatives: Arvind Gupta | Rich tributes paid to martyr Grewal Singh on his martyrdom anniversary | SIR is very important step for India: Pradeep Sharma | Gharu, Tony launch Gharana double-lane road project | Punjab Governor Union Ministers in Delhi; Discusses Key Issues | DC Samba reviews preparations for Ratkhada Mela at Ghagwal Temple | DC Doda reviews implementation of power sector schemes | Inter Division UT Level Competitions of baseball U-AAG Boys, Girls commence at Khel Goan | GDC Neeli Nallah organizes multifarious activities under celebration of World AIDS Day | Compassion Drive: Students of Cambridge International School extend support to aged | Emerges as top India-Origin Medical University in Caribbean | LPU Reinforces Global Education Strategy; Hosts UK Delegation for Specialized Academic & Cultural Exchange | District Panel approves 4 CLU cases in Doda | Distt admin plans to host 43 public service & grievances redressal camps: DC | District AYUSH organises one day training programme for MPWs in Ramban | JKEDI trains 258 entrepreneurs under RAMP, concludes MDPs in 13 districts | NIILM university, NGAI forge pioneering partnership to elevate Gatka as competitive sport | 2-day District-Level Philately Exhibition commences at Udhampur | SMVDU faculty delivered lecture at DAAM | MCM faculty delivers expert lecture on Adolescent Nutrition at NSS Camp | Back Issues  
 
news details
CS, Secy MoRTH review Road Sector Projects under PMDP in J&K
CS asks for parking bays/toilets on national highway; urges completion of works within timelines
9/14/2021 10:37:00 PM
Early Times Report
SRINAGAR, Sept 14: The Chief Secretary, Dr. Arun Kumar Mehta and Union Secretary, Ministry of Road, Transport & Highways, Giridhar Aramane, today in a high-level meeting reviewed the implementation of road sector projects in Jammu and Kashmir under Prime Minister's Development Package (PMDP).
During the meeting, it was observed that substantial progress has been achieved in the widening of National Highway-44, including in the completion of Chenani-Nashri and Qazigund-Banihal sections on the highway.
It was further observed that the remaining works on Udhampur-Ramban section, Ramban-Banihal section and Srinagar-Banihal section are also going on in full swing and are expected to be completed in the next year.
It was informed that works on Baramullah- Gulmarg road are in full swing and are likely to be completed by April 2022.
Similarly, works on Jammu semi-ring road and Jammu-Akhnoor-Poonch road have been accelerated and are expected to be completed in March 2022, and March 2024, respectively.
It was informed that work on Srinagar-Shopian-Qazigund road will also commence soon with the construction of 3 by-pass roads for Pulwama, Kulgam, and Shopian towns.
While stating that the national highway is relatively in better shape due to improved maintenance, Mr Mehta emphasised that the Ramban-Banihal segment is the most critical section on the National Highway and requires the focused attention for early execution of works related to tunnels and re-alignment of land slip prone stretches.
He also pitched for the development of parking bays and toilet facilities on the national highway to improve the travel experience of the commuters.
It is expected that these facilities will come up by November end 2021.
The Union Secretary, MoRTH asked the project executing agencies to lay special emphasis on quality of works and conduct quality inspections for completed works.
While highlighting that works may suffer in some areas in J&K in winter due to harsh weather conditions, Mr Mehta urged the agencies to make all out efforts to expedite the construction works so that all the works are completed within the timelines. He assured the project executing agencies of all the support from the UT administration in the execution of works.
  Share This News with Your Friends on Social Network  
  Comment on this Story  
 
 
 
Early Times Android App
STOCK UPDATE
 
 
 
 
 
 
 
   
Home About Us Top Stories Local News National News Sports News Opinion Editorial ET Cetra Advertise with Us ET E-paper
 
 
J&K RELATED WEBSITES
J&K Govt. Official website
Jammu Kashmir Tourism
JKTDC
Mata Vaishnodevi Shrine Board
Shri Amarnath Ji Shrine Board
Shri Shiv Khori Shrine Board
UTILITY
Train Enquiry
IRCTC
Matavaishnodevi
BSNL
Jammu Kashmir Bank
State Bank of India
PUBLIC INTEREST
Passport Department
Income Tax Department
JK CAMPA
JK GAD
IT Education
Web Site Design Services
EDUCATION
Jammu University
Jammu University Results
JKBOSE
Kashmir University
IGNOU Jammu Center
SMVDU