Breaking News :   BJP campaigning on Anantnag-Rajouri seat without seeking votes for any party | Ladakh: Cong candidate files nomination | Jammu Police slaps PSA against ‘Gola Shah’ | Victim’s family stages protest, blocks Jammu-Pathankot highway | Court grants pre-arrest bail to Raman Bhalla’s son | Omar Abdullah files nomination for Baramulla seat | CIK arrests radicalized youth in Budgam | One killed, 11 injured in Ramban accident | ‘Intruder sent to test troops alertness’ | Police attach properties of drug peddler | School timings changed in Sgr | Tahir, Aarti set to enthrall with New Song Release" | Krishi Vigyan Kendra promotes Sericulture | Four youth nabbed with Charas, Cash | Strategic Leap | Vaish community supported BJP Govt in realizing economic growth, creating jobs: Kavinder | Ravinder Raina visited flood prone villages of Kupwara district | Regional parties dividing people on caste, religion: Azad | Studies suggest more ice on Moon within exploitable depths: ISRO | Delhi bomb scare: Senders' intention was to create mass panic, disturb public order, says FIR | Advisor Bhatnagar inspects the progress of establishment of Vidhya Samiksha Kendra | "CBI not under control of Union of India": Centre to Supreme Court | BSF recovers China made drone in Tarn Taran | Rahul will be forced to take out 'Congress Dhoondho Yatra' after June 4: Shah in Bareilly | "BJP Not Against Muslims, Islamic Nations Honoured PM Modi": Rajnath Singh | Adani Ports Q4 net profit surges 77% to Rs 2,014.77 crore | "India Has 1,300 Islands, I Got Satellite Survey Done": PM Modi | EC directs parties to stop registering voters for beneficiary schemes under guise of surveys | "Should set timeline for restoration of statehood to J&K": Omar Abdullah to Amit Shah | LG flags off Road Safety Awareness tour from Raj Bhawan | Dr Tajamul gets addl charge of Director Family Welfare, MCH, immunization J&K | Student shooting video on railway tracks hit by train in Haridwar, dies | Noida man arrested for allegedly sharing deepfake video of Yogi Adityanath | Red Cross Society organizes week-long activities to mark World Red Cross Day | Beware of fake calls: Public warned against scammers impersonating authorities | Dr Sonia Verma receives prestigious Padma Vibhushan Dr Nirmala Deshpandey Award 2024 | Police apprehends thief stolen property recovered | 3 bovine smuggling bids foiled, 49 bovines rescued, 3 vehicles seized | Bovine smuggler arrested, 20 bovine rescued | NIOS announces schedule for practical exams, internal assessment for April/May 2024 | CEO SSCL inspects Jehangir Chowk junction improvement | J&K police attaches property of drug peddlers in Katra-district police Reasi | Dewan Devi Public School, Rajpura Mangotrian, Jammu commemorates International Labour Day | GDC holds extension lecture | Pinegrove School Subathu awarded for sustainability endeavours | National Workshop on Green-certified building materials held at SMVD University | Alcaraz loses to Rublev in Madrid Open quarterfinals, Sinner withdraws with hip injury | Change of guard in women's hockey team: Salima replaces Savita as skipper | Amul to sponsor USA and South Africa in T20 World Cup | Dew and absence of key bowlers hurt us: CSK skipper Gaikwad | Golf: Diksha, Pranavi and Vani ready for Aramco Series Korea | Back Issues  
 
news details
Div Com reviews progress of works on sewerage projects
UEED & NBCC directed to meet revised timelines, Div Com takes cognisance of perpetual delays
11/20/2021 10:27:41 PM

EArly Times REport

JAMMU, Nov 20: Divisional Commissioner Jammu, Dr Raghav Langer on Saturday chaired a meeting to review progress on various ongoing sewerage network projects and new plants proposed for the city, here.
The Divisional Commissioner directed the agencies to categorise their targets with respect to number of households, effluent volume and nallahs to be tapped. He sought detailed stage wise progress on each individual portion of the city’s sewerage network.
While examining the presentation by UEED, the Div Com stressed that certain areas like project reports should be improved. He directed the agency representative(s) to identify bottlenecks and eliminate the same.
The Divisional Commissioner insisted that the agencies design the ambitious project with the aim of arresting dump of undesirable city effluents into river Tawi at the earliest, and set separate targets on the projects for its right and left banks.
Dr Langer was informed that roughly 40% of the projected number of households and its population on the right bank of River Tawi, has been linked with sewerage lines and the projects for saturating the rest population are under preparation. A total of 293 kms of sewerage network has been laid on the right bank in parts of Jammu East/Jammu West areas (Zone I&II). A total of 55,000 households have been tapped till date under the ongoing projects.
There are total 13 Nallahs draining into the river on the right bank and the departmental officials apprised the Div Com that approx 500 cr shall be required to fully tap them and lay complete network to fully cover all households on the right bank of City.
NBCC was reprimanded for being unable to complete the balance 1850 household connections under JNNURM/Languishing sector scheme and deadline of January 15, 2022 was set for the same.
67 MLD capacity of Sewerage treatment plants (STPs) stands created in Bhagwati Nagar. The Div Com directed the respective officers to submit reports of daily inflow-outflow and power consumption logs of sewage treatment plants currently running in the city in addition to their BOD-COD test levels summaries.
Other aspects of the project, which include restoration, resurfacing of roads and electrification of the digging affected areas were also sought by the Div Com. He also directed complete resurfacing of the Circular Road within fifteen days.
Meanwhile, the Div Com was apprised that works on sewerage scheme costing 51 cr is under progress through UEED on the left bank of Tawi River in which 05 Nallahs are to be tapped.
Work on 4 MLD STP is compete however, the works on sewerage network is progressing at a very slow pace; upon which SE UEED was directed by the Div Com to invoke penalty clause on the contractor and get works executed at the risk and cost of the defaulting contractor.
Those present in the meeting included Commissioner JMC, Avny Lavasa; Director ERA Jammu, Ravinder Mansotra; Executive Director, NBCC, MK Chawla; Chief Engineer PHE Jammu, Manish Kumar Bhat; Chief Engineer R&B, Manzoor Hussain, Chief Engineer, PDD (JPDCL) Ashwani Sachdewa, SE UEED, Rakesh Kumar among other senior officers.
  Share This News with Your Friends on Social Network  
  Comment on this Story  
 
 
 
Early Times Android App
STOCK UPDATE
  
BSE Sensex
NSE Nifty
 
CRICKET UPDATE
 
 
 
 
 
 
 
 
   
Home About Us Top Stories Local News National News Sports News Opinion Editorial ET Cetra Advertise with Us ET E-paper
 
 
J&K RELATED WEBSITES
J&K Govt. Official website
Jammu Kashmir Tourism
JKTDC
Mata Vaishnodevi Shrine Board
Shri Amarnath Ji Shrine Board
Shri Shiv Khori Shrine Board
UTILITY
Train Enquiry
IRCTC
Matavaishnodevi
BSNL
Jammu Kashmir Bank
State Bank of India
PUBLIC INTEREST
Passport Department
Income Tax Department
JK CAMPA
JK GAD
IT Education
Web Site Design Services
EDUCATION
Jammu University
Jammu University Results
JKBOSE
Kashmir University
IGNOU Jammu Center
SMVDU