Breaking News :   Reshaping Taxation System | India’s Labour Codes: Towards a Coherent and Modern Regulatory Framework | SIR - Revamping India’s Electoral Rolls | A New Warmth in India–Canada Relations Signal Major Transformation | Young athletes Bharat’s ‘Bhagya Vidhatas’: LG Sinha | White collar terrorists turning to Telegram for secret communication | Ladakh autonomy row deepens as prominent Buddhist leader flags exclusion, intimidation | Centuries-old wounds healing: PM Modi in Ayodhya | Souls of those who sacrificed life for Ram Temple must be in peace today, says RSS Chief | Property scam: CBK files chargesheet against 4 accused | J&K Police probe ‘tax evasion’ by schools | Cold wave grips Kashmir | Winter break for schools announced | Police recovers over 10 stolen motorcycle, major theft network busted | DC Doda reviews revision of Stamp Duty Rates for 2026 | Tourism Deptt organizes Hertigage Walk from Mubarak mandi to Amar Mahal | Amit takes over as Director Census Operations J&K and Ladakh, holds introductory meeting | PETA India, SAVE Society in coordination with Jammu police organised workshop at DPL Jammu to Combat Cruelty to Animals | Neuro-Otology Workshop held at AIIMS Jammu to strengthen advanced ENT & Vertigo Care | Dr Rajiv Kumar at EPFO's RGDE stresses Gross Welfare, climate urgency, and district-level development as pillars of India's 2047 journey | Northeast Frontier Railway strengthens safety measures for approaching foggy season | Centuries-old wounds are healing, pain is being laid to rest, and long-cherished resolve is being fulfilled today: PM Modi | JU organises International Symposium | Flag hoisting is not the culmination of a yajna, but the beginning of a new era: Chief Minister Yogi Adityanath | Absconder wanted for 15 yrs arrested by police in Gajansoo area | Sikh Progressive Front organizes exhibition hockey matches to mark 350th Shaheedi Divas of Sri Guru Tegh Bahadur Sahib Ji | SMVDU cadet selected for prestigious NCC Para Basic Course at Army Airborne Training School Agra | Supertech Kids Valley Playway School organizes eye check-up camp for children | SMVD Narayana Superspeciality Hospital sets new benchmark in HPB surgeries with world-class outcomes | GDC Vijaypur organized Hackathon on "Modern Technological Ways to Prevent Drug Abuse" under Nasha Mukht Bharat Abhiyan | Bani Premier League kicks off | Crackdown on illegal mining continues police, seizes 7 dumpers | Delhi Airport sees flight cancellations, delays due to volcanic ash plumes impact | Sarbat Da Bhala Ikattarta: AAP leaders highlight unparalleled sacrifice of “Hind Di Chadar” Sri Guru Tegh Bahadur Ji | KVK Reasi organises Training Programme on Natural Farming | WAVES Film Bazaar 2025 concludes; Ladakhi film "Kakthet" shines with top honor | Back Issues  
 
news details
Another milestone achieved in under-construction Kashmir railway project
12/5/2021 11:05:30 PM
Early Times Repor

Banihal/Jammu, Dec 5: The Northern Railway achieved another milestone on Sunday with one more tunnel in the Bankot area near Banihal in Jammu and Kashmir’s Ramban connected after a breakthrough, officials said.
With the breakthrough of the tunnel, most of the excavation work of railway tunnels between Banihal and the Khari sector has been completed by IRCON International Limited, they added.
The work on the Kashmir rail project in a 110-km-long railway line between Katra and Banihal is underway and is likely to be completed within the next two years. The project is part of the 272-km Udhampur-Srinagar-Baramulla railway line to provide an alternative surface link between Kashmir and the rest of the country.
“The around-two-km-long tunnel project in Bankot is being constructed at a cost of Rs 300 crore in two parts,” an official said.
Additional Deputy Commissioner, Ramban, Harbans Lal Sharma, who attended the breakthrough ceremony, said the Indian Railways has crossed another challenging milestone between Banihal and the Khari sector of the Katra-Banihal railway link, coinciding with the world tunnelling day.
He said travelling by train from Kashmir to Kanyakumari is expected to start in the next two years and to achieve the deadline, work is in full swing in Ramban.
Sharma said 96 per cent of the 53-kilometre-long railway line in the mountainous Ramban district passes through underground tunnels and land measuring over 11,000 kanal (550 hectares) has been handed over to the railways.
Managing director, Beigh Construction Company (BCC), Imran Beig said a road-header machine is being used for the first time in the excavation of railway tunnels in the Kashmir rail project.
“The load-header machine is being used in tunnel excavation and thanks to the machine, there is no need for carrying out blasts inside the tunnels, which sometimes damage the nearby residential houses coming along the railway tunnels,” he said.
“We have been given a one-year deadline to complete tunnel number 77 and I am hopeful that we will complete the project within the deadline,” he added.
  Share This News with Your Friends on Social Network  
  Comment on this Story  
 
 
 
Early Times Android App
STOCK UPDATE
 
 
 
 
 
 
 
   
Home About Us Top Stories Local News National News Sports News Opinion Editorial ET Cetra Advertise with Us ET E-paper
 
 
J&K RELATED WEBSITES
J&K Govt. Official website
Jammu Kashmir Tourism
JKTDC
Mata Vaishnodevi Shrine Board
Shri Amarnath Ji Shrine Board
Shri Shiv Khori Shrine Board
UTILITY
Train Enquiry
IRCTC
Matavaishnodevi
BSNL
Jammu Kashmir Bank
State Bank of India
PUBLIC INTEREST
Passport Department
Income Tax Department
JK CAMPA
JK GAD
IT Education
Web Site Design Services
EDUCATION
Jammu University
Jammu University Results
JKBOSE
Kashmir University
IGNOU Jammu Center
SMVDU