Breaking News :   Siblings ran international drug cartel on directions of handlers in Pak, Canada | LG Sinha releases ‘Jai Kashmir’ | Delegations call on Lieutenant Governor | 50 Pak terrorists active in eight Jammu districts | We hit 9 terror targets in Pak with precision: NSA Doval | Crime Branch books SI, teacher, Anganwadi worker for using fake documents | PM Modi to distribute over 51,000 appointment letters | Wildlife Board clears over 30 defence projects | ED restores Rs 55 cr proceeds of crime | 10th batch of over 6,400 pilgrims leaves for Kashmir | ACB arrests lineman for accepting bribe | GST-linked bank account mandatory for e-tendering | Groom among 3 injured in mishap | NMC suggests 3-tier grievance-redressal mechanism | Justice for terror victims | Technology is helping turn NEP 2020 vision into reality in classrooms | The paper bag: A simple switch for a cleaner world | Kanwar Yatra: A Journey of Faith, Endurance, and Devotion | CM Yogi hears grievances of people in Janata Darshan | Yogi Govt deploys anti-drones to ensure safe, secure Kanwar Yatra | CM Pushkar Singh Dhami stresses simplification of Loan, Insurance processes | Jodhamal student sets an international record | Back Issues  
 
news details
Progress of CD Panchayat works reviewed in Rajouri
12/3/2022 10:53:52 PM
Early Times Report
RAJOURI, Dec 3: District Development Commissioner Rajouri, Vikas Kundal today reviewed the progress on CD Panchayat works being executed by the Rural Development Department in the district.
At the outset of the meeting, Assistant Commissioner Development, Vijay Kumar apprised that out of 151 CD Panchayat works, the tenders for 124 works have been allotted. It was also informed that as many as 32 works are complete and 86 are in progress. The DDC stressed on tendering of the rest of the works at the earliest.
Taking note of the financial progress of the works, it was informed that against the release of Rs 2.4. crore, an expenditure of Rs 29.53 lakh has been incurred till date.
The DDC asked the RDD to expedite the process and ensure that works are completed within the stipulated timeline.
The DDC also stressed on close monitoring of the works to maintain quality while executing works and said that no laxity shall be tolerated in this regard.
Officers present in the meeting were Assistant Commissioner Development, Vijay Kumar; Executive Engineer REW, Zahir Khan; AD Planning, Bansi Lal; BDO Rajouri, Chander Kant Bhagat and AEE REW, Ather Parwaiz.
  Share This News with Your Friends on Social Network  
  Comment on this Story  
 
 
 
Early Times Android App
STOCK UPDATE
  
BSE Sensex
NSE Nifty
 
CRICKET UPDATE
 
 
 
 
 
 
 
 
   
Home About Us Top Stories Local News National News Sports News Opinion Editorial ET Cetra Advertise with Us ET E-paper
 
 
J&K RELATED WEBSITES
J&K Govt. Official website
Jammu Kashmir Tourism
JKTDC
Mata Vaishnodevi Shrine Board
Shri Amarnath Ji Shrine Board
Shri Shiv Khori Shrine Board
UTILITY
Train Enquiry
IRCTC
Matavaishnodevi
BSNL
Jammu Kashmir Bank
State Bank of India
PUBLIC INTEREST
Passport Department
Income Tax Department
JK CAMPA
JK GAD
IT Education
Web Site Design Services
EDUCATION
Jammu University
Jammu University Results
JKBOSE
Kashmir University
IGNOU Jammu Center
SMVDU