x

Like our Facebook Page

   
Early Times Newspaper Jammu, Leading Newspaper Jammu
 
Breaking News :   Low voter turnout in urban areas worries BJP leaders | After Mehbooba’s Poonch tour, BJP to devise fresh strategy | Ramban: Over 500 persons relocated to safer places amid land sinking | ‘Rebuild our shattered lives’ | Those who turned down Ram temple invitation will be rejected by voters: PM Modi | Will support like-minded parties in Kashmir: Ravinder Raina | 3 accused arrested within hours, case solved: Police | VDG killed in Udhampur gunfight | More rain in Kashmir till April 30: MeT | Property used as shelter by terrorists attached | BRO rescues people stuck at Razdan Pass | NTA to announce details of exam centers | Annual Foundation Day celebrated | Interaction-Cum-Workshop held | BJP exploited public sentiments: Javed Rana | Higher Edu Deptt, IITs offering Internship, Sponsor M. Tech. Program Opportunity for Students from Ladakh for 2024 | 27th Annual Bhandra organized at Vaishno Mandir Bhagwati Nagar | Grand celebration marks 101st Birth Anniversary of Veer Ram Chander Ji | Man arrested with narcotics material on Rajouri highway | Preserving Water Bodies | Ajaz Jan urges maximum participation in LS Polls to safeguard our distinctive identity | VDGs playing vital role in containing terrorism in J&K: Kavinder | JKNC Student Wing convenes meeting, advocates for youth empowerment | 4 killed, 2 missing in road accident in Ganderbal | BJP Govt failed to fulfill promises made with KP migrants: Rattan Lal Gupta | Cardiovascular health in developing world - Multifactorial and intersectoral determinants: Dr Sushil Sharma | Interaction between ADGP Armed J&K and JKP MRT held | Mehbooba appeals ECI not to defer elections in Anantnag-Rajouri LS seat | Back Issues  
 
news details
Sharp curve in India's 1st vertical bridge poses challenge for railways
4/9/2024 10:33:33 PM
Agencies
NEW DELHI, Apr 9: A sharp curve in the upcoming Pamban railway bridge, India's first vertical-lift bridge connecting the country's mainland with Rameswaram island, has become an additional challenge for the Railways besides its mechanical peculiarity and a rough sea.
The Rail Vikas Nigam Limited (RVNL), which is constructing this 2.08-km-long bridge, is facing a huge challenge in moving a lift span, which is 72.5-m-long, 16-m-wide and weighs 550 tonne, from the Rameshwaram end to 450 m in the sea to fix it to the bridge.
"We started moving this lift span on March 10 and till date, we have moved the 550 ton lift span 80 m towards the centre of the bridge. The biggest challenge is the 2.65 degree of curved alignment of the bridge. Had it been straight, we would have moved it faster," a senior official of RVNL said, adding the curved shape was essential due to various alignment changes.
The movement of the lift span to its final fixing point shall be completed by the end of May, as it still has to be carried 370 m more.
"Once we cross the curved portion, we can expedite its movement. We have taken a huge precaution while moving it in the sea as its size and weight requires great precision at each step," the official said.
The RVNL has set a deadline of June 30 to make the bridge operational and its officials say that they are trying their level best to meet it.
"Once the lift span is fixed, the remaining work is no big deal," an RVNL official said.
He added, "This lift span can be lifted up automatically up to 17 m for ships to pass. It will take 5 minutes to go up and the same time to come down and will be scheduled in such a way so that train services shouldn't be disrupted." The RVNL got this lift span designed from Spanish firm TYPSA and it was manufactured at Sattirakkudi Railway Station, which is 20 km away from the sea coast.
"We brought it in various parts and assembled it here at the coast because it was not possible to carry such a huge structure from the manufacturing point," the RVNL official said.
The train services between Mandapam in the mainland and Rameswaram island were suspended on December 23, 2022 after the existing rail bridge, which was built in 1913, was declared non-operational from the safety point of view.
"When the Pamban bridge was operational, trains used to move to the bridge and reach Rameshwaram. They used to move slowly on the Pamban bridge and reach the pilgrimage town in about 15 minutes," a Southern Railway official said.
At present, all trains terminate at Mandapam and people use road routes to reach Rameswaram. Prime Minister Narendra Modi laid the foundation stone of the new bridge, parallel to the old one, in November 2019 and the work was started in February 2020 by RVNL.
  Share This News with Your Friends on Social Network  
  Comment on this Story  
 
 
 
Early Times Android App
STOCK UPDATE
  
BSE Sensex
NSE Nifty
 
CRICKET UPDATE
 
 
 
 
 
 
 
 
   
Home About Us Top Stories Local News National News Sports News Opinion Editorial ET Cetra Advertise with Us ET E-paper
 
 
J&K RELATED WEBSITES
J&K Govt. Official website
Jammu Kashmir Tourism
JKTDC
Mata Vaishnodevi Shrine Board
Shri Amarnath Ji Shrine Board
Shri Shiv Khori Shrine Board
UTILITY
Train Enquiry
IRCTC
Matavaishnodevi
BSNL
Jammu Kashmir Bank
State Bank of India
PUBLIC INTEREST
Passport Department
Income Tax Department
JK CAMPA
JK GAD
IT Education
Web Site Design Services
EDUCATION
Jammu University
Jammu University Results
JKBOSE
Kashmir University
IGNOU Jammu Center
SMVDU