Breaking News :   Dr Andrabi welcomes first batch of Amarnath Ji Yatris | Adopt zero tolerance approach towards illegal mining in J&K: Dy CM to Officers | Transport Commissioner inspects driving test centre, RTO office Srinagar | Freight unloading at NFR holds steady growth during the month of June 2025 | Sadhotra seeks probe into non-utilization of bunker construction funds in border areas | Javed Rana, Javid Dar review irrigation scenario in JK | Illegal timber transportation foiled; truck seized | NIPCCD renamed as Savitribai Phule National Institute of Women, Child Development | Nominations for Padma Awards-2026 open till 31st July, 2025 | Extensive studies by ICMR, AIIMS on sudden deaths establish no linkage between COVID-19 vaccines | Cyber Cell solves online frauds, recovers money | Encounter breaks out between terrorists, security forces in Kishtwar | DB stays writ Court order to Repatriate 63-Year-Old Woman Deported to Pakistan | CCI president calls on LG Sinha | Amarnath ji pilgrims accorded rousing reception at Udhampur | SBSP president Vivek Bali welcomes first batch of Amarnath Yatra pilgrims | DC Poonch visits Gurudwara Deri Sahib Khari | ELI Scheme will be Game-Changer for Youth Employment & Economic Growth in country: Kavinder | ADC Bhaderwah reviews functioning of Tehsil Library | District Administration Ramban welcomes first batch of Shri Amarnath Ji Yatra-2025 Pilgrims | Apni Party's deputation submits memorandum to DC Jammu | Dr Javid Iqbal honoured with two awards on Doctors' Day at GMC Rajouri | Police apprehends man with sharp-edged weapon | COAS visits Bhutan to strengthen bilateral defence cooperation | Suresh Sharma inspects roads in Maira Mandrian, ensures Monsoon readiness | Induction Training for newly promoted L/A-Headmasters inaugurated at Polytechnic College, Jammu | Udhampur police recovers Rs 1.13 lakh in 7 different cyber fraud cases | Special facilities arranged for Amarnath passengers by Railway Administration | Doda police traced out 2 missing ladies and re-united with families | SMVDU NCC Cadet participated in Special National Integration Camp | LPU Launched RCI-Approved M.A. Clinical Psychology Programme | 'Dr Vinod Kumar Sharma's Famous Poems' Released at MCM | Preparation for classical chess requires a lot of effort: Praggnanandhaa | Asian champion 100m hurdler Yarraji suffers injury, in big blow to World C'ships hopes | Sudhanshu Mittal re-elected as KKFI chief | IIM Signs MoU with Sheffield University Management School | Temple of learning ? | "The Power of Pen" | Your Dream Doesn’t Have an Expiry Date | In today’s digital age, Screen dominate Simple ways Parents can get kids off Screen and back into Real Books | Underground Hospital | Kashmir Muslims greet yatris to strengthen brotherhood | All officers on ground to ensure peaceful yatra: DGP Prabhat | ONGC sets up Yatri Niwas and Disaster Management Complex at Baltal | Kashmir traders pin hopes on Yatra for tourism revival | CRPF deploys women ‘May I Help You’ Teams, Mountain Rescue Units’ | Amarnath pilgrims laud ‘Operation Sindoor’ | Special arrangements at Jammu Railway Station | J&K Police establish helpline for terrorism victims | 5 springs sealed in Rajouri | Back Issues  
 
news details
7 years on, Sudhwala- Sooyian bridge awaits completion, people aghast
7/20/2019 12:36:39 AM
M S Nazki

Early Times Report

POONCH, July 19: Roads and Building (R&B) Department has failed to complete the construction of Sudhwala-Sooyian bridge in Mendhar area of Poonch district even Seven years after its foundation stone was laid.
Missing several deadlines, the construction of the bridge was started in June 2013 at an estimated cost of Rs 54. lakh and was supposed to be completed in March 2015
A group of locals at Sooyian Said that despite passing many deadlines, the government is yet to complete the project making people to face inconvenience of all sorts.
They alleged that the work has been going on at a snail's pace while people continue to suffer and take other routes in the area to commute.
Abdul Rehman Khan , a local at Sooyian said it is a completely a failure of the government. People living in the area extended cooperation to the authorities but they have failed to complete the project within the stipulated time, he said. Another local shopkeeper said it has become a routine for the authorities to initiate a project, construct some pillars or plinth and then abandon it. "It is unfortunate that government always extends deadlines rather than making officials accountable for their failure to complete projects on time," he said. The bridge was to be completed in 2015 but the deadline was extended to 2018. We don't know whom to blame, the locals said.
"A decade has passed since the work on the bridge was started and it is still incomplete. If they don't have funds
  Share This News with Your Friends on Social Network  
  Comment on this Story  
 
 
 
Early Times Android App
STOCK UPDATE
  
BSE Sensex
NSE Nifty
 
CRICKET UPDATE
 
 
 
 
 
 
 
 
   
Home About Us Top Stories Local News National News Sports News Opinion Editorial ET Cetra Advertise with Us ET E-paper
 
 
J&K RELATED WEBSITES
J&K Govt. Official website
Jammu Kashmir Tourism
JKTDC
Mata Vaishnodevi Shrine Board
Shri Amarnath Ji Shrine Board
Shri Shiv Khori Shrine Board
UTILITY
Train Enquiry
IRCTC
Matavaishnodevi
BSNL
Jammu Kashmir Bank
State Bank of India
PUBLIC INTEREST
Passport Department
Income Tax Department
JK CAMPA
JK GAD
IT Education
Web Site Design Services
EDUCATION
Jammu University
Jammu University Results
JKBOSE
Kashmir University
IGNOU Jammu Center
SMVDU