Breaking News :   Action against terror-linked employees to pick up in 2026, 120 black-sheep under scanner | Pak drone drops arms, narcotics on New Year's Day on LoC in Poonch | TAC formed for ICT lab approvals | GST collections rise by 6% | Search ops intensified in Pir Panjal ranges | Air Marshal Kapoor takes charge | Snowfall shuts Mughal Road | ATF Price cut by steep 7% | Goodbye Bye 2025, welcome 2026 | My rights, in Kashmiri language | A twist in the Tale: Are scientists wrong about dark energy? | Local Bodies Set To Reappear | Uttar Pradesh's Data Center Policy makes state new hub of digital investment | LG Ladakh directs fortnightly field visits, public accessibility of Administrative Secretaries | DC inspects development works at Ramban | J&K Govt orders transfer of Secretariat Service Officials | BOSE discards old syllabus; advises concerned students to opt for new syllabus in 2026 | Crime Branch Kashmir chargesheets two in fake agriculture dept appointment scam | Blast Near Nalagarh Police Station In Himachal; No Casualty Reported | Extradition of 26/11 accused, over 92% conviction rate among key milestones of NIA in 2025 | Woman arrested for pickpocketing in J&K's Kulgam | Govt's major digital initiative, state-of-the-art single window clearance system to be launched | Haryana Cabinet Approves Key Amendments to Deen Dayal Lado Lakshmi Yojana to Strengthen Women Empowerment | Poonch Brigade to organise national integration tour to Delhi & Amritsar | CEO SSCL conducts site review of Heritage Wooden Footbridge at Amira Kadal | Haryana Cabinet extends OPS, other benefits to 347 contractual drivers appointed in 2002 | Gupta slams BJP for Youth Unemployment; challenges Sunil Sharma to account for decade of misrule | Tinsukia Division of NFR achieves major progress in track electrification | Sakeena Itoo calls for comprehensive revamp of sanitation, cleanliness measures in health facilities across J&K | CCI Welcomes Rs 1,430 Crore MHA assistance, seeks early relief for affected families | Jammu Club welcomes NewYear 2026 with grand cultural evening | Two terror associates held with arms, grenades, Rs 8.4 lakh cash in J&K's Ganderbal | AI a "Big Opportunity", essential to ensure its benefits reach all: President Murmu | JBM resolves to launch united crusade against drug menace in Jammu; announces official website | Punjab Govt drives education revolution, over 1,700 government school students trained for IITs, NITs, AIIMS other competitive exams | Taste of Integration: Culinary Journeys on Kashmir Vande Bharat Express | Back Issues  
 
news details
‘‘PMGSY Deptt shows dismal performance in Rajouri’
Rajouri-Darhal-Parori road project incomplete even after lapse of deadline
6/19/2020 12:04:58 AM
ANKIT KESSAR

EARLY TIMES REPORT

RAJOURI, June 18: The much ambitious Rajouri-Darhal-Parori road project, which is being executed under Pradhan Mantri Gram Sadak Yojna (PMGSY), is still incomplete even after lapse of its deadline, exposing the poor, dismal performance of the PMGSY Department in Rajouri district.
Sources told Early Times that thousands of the people have been facing huge hardships due to non-completion of the Rajouri-Darhal-Parori road as this is the only route where people living adjoining areas have to take this road for commuting on daily basis but due to dilapidated condition of the road from Rajouri to Darhal and thereafter upto Prori have made difficult for them to move from one place to other and making it non motor able.
Earlier the road was under PWD (R&B), which didn’t take attention toward the poor condition of road but after the local people raised their voices on various platforms then that the road from Kassian to Darhal and from Darhal to Prori was included in the PMGSY upgradation programme, they said.
“Many accidents were taken place on this stretch due to dilapidated condition of the road yet the concerned department seems least bothered to redress the issue on prompt mode, which can be gauged from the that the project has to be completed within 25 months (i.e. early this year) but even the end of this deadline, only 20-30% work has been done till date,” said Zahid Sarfraz Malik General Secretary JKPC Vichar Vibhag.
They further said that the firm which was given the contract for the execution of work, further sublet the many parts of this project to non-professional contactors, which was also another reason that the project continue to be delayed.
“M/S TBA Infrastructure Pvt Ltd being the successful bidder was allotted work of the road on 19-12-2017 and the time period for completion of the project was 25 months but company adopted snail pace due to which the work could not meet the deadline.
Although unwarranted delay on the part of Construction Company was informed to the concerned department many a times but except empty assurances nothing was done,” informed Zahid Malik, adding that such construction companies should be blacklisted for their lacklustre attitude.
They added that due to digging on the road by the executing agency it is impossible for the people to travel and even the local transporters sometimes refused to ply their vehicles on this road adding more and more suffering to the people of the area.
The locals including Karamat Malik, Quyoom Malik, Aflad Hussain, Zaheer Abass accused the department for not taking action against the contractor for making delay in the project.
They alleged that there is nexus between contractors and the officials of PMGSY due to which project is not completed and next time the project is again retendered with cost escalation.
Concerned Executive Engineer PMGSY Mahmood Ahmed, when contacted in this connection, failed to give a satisfactory reply on the delay in completion of the project. He said that he can only serve the notice to the concerned firm for delay and as far as the action is concerned only higher authorities can do that. “We are trying our level best to complete the project at the earliest but there are some land issues in the project, which are creating hurdles in its completion,” he said.
On being asked about the subletting of the project by the firm, he said that they can’t do anything about it.
  Share This News with Your Friends on Social Network  
  Comment on this Story  
 
 
 
Early Times Android App
STOCK UPDATE
 
 
 
 
 
 
 
   
Home About Us Top Stories Local News National News Sports News Opinion Editorial ET Cetra Advertise with Us ET E-paper
 
 
J&K RELATED WEBSITES
J&K Govt. Official website
Jammu Kashmir Tourism
JKTDC
Mata Vaishnodevi Shrine Board
Shri Amarnath Ji Shrine Board
Shri Shiv Khori Shrine Board
UTILITY
Train Enquiry
IRCTC
Matavaishnodevi
BSNL
Jammu Kashmir Bank
State Bank of India
PUBLIC INTEREST
Passport Department
Income Tax Department
JK CAMPA
JK GAD
IT Education
Web Site Design Services
EDUCATION
Jammu University
Jammu University Results
JKBOSE
Kashmir University
IGNOU Jammu Center
SMVDU