Breaking News :   Terrorist country Pak wants to derail J&K’s development journey: LG Sinha | LG visits Nunwan base camp, interacts with pilgrims, officials, others | RSS to reach every home during centenary year | Op Sindoor led to increase in demand for indigenous defence products: Rajnath Singh | Army, Defence Minister pay tribute to Capt Batra | Azad unofficially disbands DPAP as key leaders desert party! | Pahalgam terror attack: NIA gets custody of 2 accused for 10 more days | Day 5: 23,857 pilgrims pay obeisance, figure crosses 90,000 mark | 3 yatris among 4 injured in Anantnag accident | Court rejects bail of woman involved in terror activities | BSF jawan shoots himself dead | 2 civilians stranded on landslide-hit road rescued | Kashmir: Schools to reopen today | Mission Director HADP inaugurates capacity building programme of FPO’s | Conduct of Medical Patrol for Awam at Songri, Rajouri | Ex-Servicemen Rally, outreach Program conducted | Shri Amar Kshatriya Rajput Sabha holds meeting | Awareness Camp organized under Dharti Aaba Janjatiya Utkarsh Abhiyan | Take Modi government’s 11 years of achievements to every household: Balbir | Empowering Voices of Justice: National Gurjar Advocates Conference held | Two-day Shoulder Rehabilitation workshop organises | DLSA Srinagar organizes awareness programme on drug abuse | Amarnath Yatra a spiritual & religious journey | Invisible Walls | Parched Paradise: Scorching heat dries up Kashmir’s Summer Charm | LG Sinha’s Rallying Call | BNI J&K hosts 4th edition, uniting 300 business leaders from across India, honoring top | One notorious drug peddler nabbed by Jammu Police | Himachal Rains: Rescue Operations On To Trace 30 Missing After Cloudbursts, Landslips In Mandi | Police arrests a drug peddler from Bus Stand | BRO CE calls on Dy CM; discusses road infra in Jammu province | Adityanath pays tributes to Kargil martyr Captain Vikram Batra on death anniversary | Delhi Speaker meets Amit Shah, briefs about ongoing initiatives in Assembly | Youtuber Jyoti Malhotra's Judicial Custody Extended By 14 Days In Espionage Case | ISRO Chief Dr V Narayanan meets CM Yogi, explores dedicated satellite for Uttar Pradesh | 'Approval for Phase IV of the Pradhan Mantri Gram Sadak Yojana will be given as per the state's proposal' - Shri Shivraj Singh | NFR Strengthens Safety Measures for Monsoon Operations | DIG JKS Range Shiv Kumar IPS conduct Security Review | HC dismissed petition with costs Rs 50000 | Elderly man loses Rs 73.72 lakh in gold trading draud after meeting woman on dating app | Luggage packed, will move out of official residence: Ex-CJI DY Chandrachud | Van Mahotsav 2025: Forest Dept to plant 3.5 crore saplings along riverbanks | Shrine Board Judokas to represent India at International Competitions | International recognition of cross-border terrorism validates India's stand: Kavinder Gupta | DC Kulgam takes review of Mission YUVA; assesses implementation, progress | Sheep Husbandry deptt organizes PMFME workshop/awareness programme | ABRSM delegation meets CEO Jammu, highlights teachers' key issues | Macadamization work begins on Tujjar Sharief to Zaingeer road, Baramulla | Over Rs.41 crore allocated under DDC, BDC, PRI & Aspirational Grants in Bandipora | PAC holds meet at Srinagar, discusses Audit Paras of HUDD | J&K Cine Association slams 'Hillywood' label as misleading and politically driven | UP CM orders strict action against those attempting to defile Kanwar Yatra | 5 of family murdered on suspicion of practising witchcraft in Bihar, oppn slams govt | PM Modi at BRICS, a global wake-up call against terrorism: Gaurav Gupta | Shiv Sena distributed poster to Amarnath pilgrims for 'Jammu-Darshan' | SBI hands over Rs 1.10 Crore DSP PAI claim to family of Martyr Rifleman Sunil Kumar | Mission Director HADP inaugurates five-day Capacity Building Programme for FPOs | Beating the heat wave and humidity, IGNOU flying squad teams charge into Exam Centres for on-the-spot monitoring | FVSc and AH, SKUAST-Jammu celebrates World Zoonoses Day- 2025 | Annual congregation of All India Rohmetra Mahajan Biradari on 10th , July | Bovine smuggling attempt foiled, 09 bovines rescued, in Latti | LIC of India introduces new Plans LIC's Nav Jeevan Shree (Plan 912) & LIC's Nav Jeevan Shree Single Premium (Plan 911) | 15-day Youth Development Programme on 'Premier Banker' inaugurates | Mechanical Engineering students of DBU developed "Multi-Utility Power Generating Kit" | 'Kala aur Atmanirbharta' culminates at MCM | Tanvi Sharma eyes junior titles before full-fledged senior switch | JKCCA appoints Dr Rekha Rani Sharma as Advisor | Pinegrove Director elected president BSAI | Aryaveer and Aaryavir: The Kohli, Sehwag connection at this year's DPL | Indian archers eye World Championship preparation at Madrid World Cup | Back Issues  
 
news details
‘‘PMGSY Deptt shows dismal performance in Rajouri’
Rajouri-Darhal-Parori road project incomplete even after lapse of deadline
6/19/2020 12:04:58 AM
ANKIT KESSAR

EARLY TIMES REPORT

RAJOURI, June 18: The much ambitious Rajouri-Darhal-Parori road project, which is being executed under Pradhan Mantri Gram Sadak Yojna (PMGSY), is still incomplete even after lapse of its deadline, exposing the poor, dismal performance of the PMGSY Department in Rajouri district.
Sources told Early Times that thousands of the people have been facing huge hardships due to non-completion of the Rajouri-Darhal-Parori road as this is the only route where people living adjoining areas have to take this road for commuting on daily basis but due to dilapidated condition of the road from Rajouri to Darhal and thereafter upto Prori have made difficult for them to move from one place to other and making it non motor able.
Earlier the road was under PWD (R&B), which didn’t take attention toward the poor condition of road but after the local people raised their voices on various platforms then that the road from Kassian to Darhal and from Darhal to Prori was included in the PMGSY upgradation programme, they said.
“Many accidents were taken place on this stretch due to dilapidated condition of the road yet the concerned department seems least bothered to redress the issue on prompt mode, which can be gauged from the that the project has to be completed within 25 months (i.e. early this year) but even the end of this deadline, only 20-30% work has been done till date,” said Zahid Sarfraz Malik General Secretary JKPC Vichar Vibhag.
They further said that the firm which was given the contract for the execution of work, further sublet the many parts of this project to non-professional contactors, which was also another reason that the project continue to be delayed.
“M/S TBA Infrastructure Pvt Ltd being the successful bidder was allotted work of the road on 19-12-2017 and the time period for completion of the project was 25 months but company adopted snail pace due to which the work could not meet the deadline.
Although unwarranted delay on the part of Construction Company was informed to the concerned department many a times but except empty assurances nothing was done,” informed Zahid Malik, adding that such construction companies should be blacklisted for their lacklustre attitude.
They added that due to digging on the road by the executing agency it is impossible for the people to travel and even the local transporters sometimes refused to ply their vehicles on this road adding more and more suffering to the people of the area.
The locals including Karamat Malik, Quyoom Malik, Aflad Hussain, Zaheer Abass accused the department for not taking action against the contractor for making delay in the project.
They alleged that there is nexus between contractors and the officials of PMGSY due to which project is not completed and next time the project is again retendered with cost escalation.
Concerned Executive Engineer PMGSY Mahmood Ahmed, when contacted in this connection, failed to give a satisfactory reply on the delay in completion of the project. He said that he can only serve the notice to the concerned firm for delay and as far as the action is concerned only higher authorities can do that. “We are trying our level best to complete the project at the earliest but there are some land issues in the project, which are creating hurdles in its completion,” he said.
On being asked about the subletting of the project by the firm, he said that they can’t do anything about it.
  Share This News with Your Friends on Social Network  
  Comment on this Story  
 
 
 
Early Times Android App
STOCK UPDATE
  
BSE Sensex
NSE Nifty
 
CRICKET UPDATE
 
 
 
 
 
 
 
 
   
Home About Us Top Stories Local News National News Sports News Opinion Editorial ET Cetra Advertise with Us ET E-paper
 
 
J&K RELATED WEBSITES
J&K Govt. Official website
Jammu Kashmir Tourism
JKTDC
Mata Vaishnodevi Shrine Board
Shri Amarnath Ji Shrine Board
Shri Shiv Khori Shrine Board
UTILITY
Train Enquiry
IRCTC
Matavaishnodevi
BSNL
Jammu Kashmir Bank
State Bank of India
PUBLIC INTEREST
Passport Department
Income Tax Department
JK CAMPA
JK GAD
IT Education
Web Site Design Services
EDUCATION
Jammu University
Jammu University Results
JKBOSE
Kashmir University
IGNOU Jammu Center
SMVDU