Breaking News :   Siblings ran international drug cartel on directions of handlers in Pak, Canada | LG Sinha releases ‘Jai Kashmir’ | Delegations call on Lieutenant Governor | 50 Pak terrorists active in eight Jammu districts | We hit 9 terror targets in Pak with precision: NSA Doval | Crime Branch books SI, teacher, Anganwadi worker for using fake documents | PM Modi to distribute over 51,000 appointment letters | Wildlife Board clears over 30 defence projects | ED restores Rs 55 cr proceeds of crime | 10th batch of over 6,400 pilgrims leaves for Kashmir | ACB arrests lineman for accepting bribe | GST-linked bank account mandatory for e-tendering | Groom among 3 injured in mishap | NMC suggests 3-tier grievance-redressal mechanism | Justice for terror victims | Technology is helping turn NEP 2020 vision into reality in classrooms | The paper bag: A simple switch for a cleaner world | Kanwar Yatra: A Journey of Faith, Endurance, and Devotion | CM Yogi hears grievances of people in Janata Darshan | Yogi Govt deploys anti-drones to ensure safe, secure Kanwar Yatra | CM Pushkar Singh Dhami stresses simplification of Loan, Insurance processes | Jodhamal student sets an international record | Back Issues  
 
news details
DC reviews progress of JJM works in Kathua District
9/18/2023 10:20:30 PM
Early Times Report

KATHUA, Sept 18: Deputy Commissioner Kathua Rakesh Minhas today chaired a meeting of concerned officers and contractors to review the progress achieved under flagship Jal Jeevan Mission in the district.
At the outset, Superintendent Engineer Hydraulic R. K Gupta apprised the Deputy Commissioner about the financial and physical progress achieved under the Mission.
The DC, while interacting with contractors executing the JJM work, emphasised upon them to complete all assigned works within stipulated timeframes. He further called upon the executing agencies to ensure no laxity in execution of the works and asked for penalizing the defaulters.
Underlining the need for quality asset creation within set timelines, the DC called upon the engineers to take PRIs on board for proper monitoring of the assets being created in their respective areas. He further called for speeding up the works to rule out any chance of carrying forward any financial liabilities.
Issues such as construction of Overhead tanks, slow sand filtration plant and Rapid Sand filtration plants remained the focal point of concern wherein DC passed directions to all concerned to mobilize men and machinery for achieving progress before the cut-off timelines.
Earlier, SE Hydraulic gave a brief account of the works undertaken wherein he informed about the status of all allotted works, including OHTs, Regarding Slow sand filtration plant, Rapid Sand filtration plant.
CPO Kathua Uttam Singh, XEN PHE Kathua and other concerned officers were also present.
  Share This News with Your Friends on Social Network  
  Comment on this Story  
 
 
 
Early Times Android App
STOCK UPDATE
  
BSE Sensex
NSE Nifty
 
CRICKET UPDATE
 
 
 
 
 
 
 
 
   
Home About Us Top Stories Local News National News Sports News Opinion Editorial ET Cetra Advertise with Us ET E-paper
 
 
J&K RELATED WEBSITES
J&K Govt. Official website
Jammu Kashmir Tourism
JKTDC
Mata Vaishnodevi Shrine Board
Shri Amarnath Ji Shrine Board
Shri Shiv Khori Shrine Board
UTILITY
Train Enquiry
IRCTC
Matavaishnodevi
BSNL
Jammu Kashmir Bank
State Bank of India
PUBLIC INTEREST
Passport Department
Income Tax Department
JK CAMPA
JK GAD
IT Education
Web Site Design Services
EDUCATION
Jammu University
Jammu University Results
JKBOSE
Kashmir University
IGNOU Jammu Center
SMVDU