Breaking News :   Justice For Terror Victim Families | Kathua Administration welcomes first Batch of Amarnath Yatris at Lakhanpur | Yatra of resilience: LG to flag off first batch today after Pahalgam carnage, Op Sindoor | LG visits Yatri Niwas at Bhagwati Nagar, reviews arrangements | LG reviews final preparations | LG chairs high-level meeting, discusses issues of terror victim families | LG flags off fleet of ambulances in Ramban, Anantnag districts | 5 real brothers from Budgam among fraudulently selected candidates | Hope beneath the surface: Govt plans underground hospital in Poonch | ACB catches DDC member red handed | Crime Branch books J&K Bank officers, others for frauds | Back Issues  
 
news details
DC Ganderbal reviews progress under CAPEX Budget 2023-24
3/5/2024 10:30:10 PM

Early Times Report

GANDERBAL, Mar 5: The Deputy Commissioner (DC) Ganderbal, Shyambir today conducted a comprehensive review meeting to assess the physical and financial status of projects taken under the District Capex Plan 2022-23.
The meeting, held at the V.C Room of the DC Office, included Sectoral and District Officers to provide insights into various sectors such as R&B, Jal Sakhti, Education, Health, and Youth Sports.
During the session, the DC scrutinized the funds released and expenditures incurred across different sectors, emphasizing the critical need for timely project completion to ensure efficient fund utilization and overall district development.
He directed officers to expedite ongoing projects while maintaining strict adherence to timelines and quality standards.
It was revealed during the meeting that out of the total 1307 works initiated under the District Capex, 965 have been successfully completed, with the remaining projects currently in progress. Furthermore, it was highlighted that 62 percent of the released budget for the year 2022-23 has been utilized to date.
The DC underscored the significance of close monitoring and coordination among departments to overcome any bottlenecks and ensure seamless project progress.
He urged officers to provide regular updates and promptly address any issues to prevent delays, emphasizing the importance of efficient implementation for the benefit of the district’s residents.
The meeting witnessed the presence of key officials including the Assistant Commissioner Revenue, Chief Planning Officer, Executive Engineers of KPDCL and Jal Sakhti, GM DIC, CMO, CEO, AEE R&B, and other stakeholders.
  Share This News with Your Friends on Social Network  
  Comment on this Story  
 
 
 
Early Times Android App
STOCK UPDATE
  
BSE Sensex
NSE Nifty
 
CRICKET UPDATE
 
 
 
 
 
 
 
 
   
Home About Us Top Stories Local News National News Sports News Opinion Editorial ET Cetra Advertise with Us ET E-paper
 
 
J&K RELATED WEBSITES
J&K Govt. Official website
Jammu Kashmir Tourism
JKTDC
Mata Vaishnodevi Shrine Board
Shri Amarnath Ji Shrine Board
Shri Shiv Khori Shrine Board
UTILITY
Train Enquiry
IRCTC
Matavaishnodevi
BSNL
Jammu Kashmir Bank
State Bank of India
PUBLIC INTEREST
Passport Department
Income Tax Department
JK CAMPA
JK GAD
IT Education
Web Site Design Services
EDUCATION
Jammu University
Jammu University Results
JKBOSE
Kashmir University
IGNOU Jammu Center
SMVDU