Breaking News :   Absconder wanted for 19 years arrested | Uttar Pradesh is set to become the powerhouse of Viksit Bharat | PM Modi's tribute to India's Tribal Freedom Fighters | Chief Secy launches Single Window System for Recruitment Rules | Driver found dead inside vehicle at Sopore Mandi; Police launch probe | HC orders major reshuffle in J&K, Ladakh Judiciary | 23 foreigners living illegally, sent for deportation: Police | Bihar Results People's Stamp Of Approval On NDA Govt's Service: Amit Shah | Multipurpose Stall started at Shaheed Captain Tushar Mahajan Railway Station (Udhampur) | Centre notifies appointment of two new LS MPs in key disability empowerment committee | Secretary ITD reviews progress on integration of BHASHINI in digital framework of J&K | NC's Hollow Palace Is Crumbling: LoP Sunil Sharma Says Downfall Begins from Nagrota to Budgam | Police attaches immovable property worth lacs of drug peddler in Billawar | CISF Jammu Airport organized program on Bal Diwas | CM Omar Abdullah lays foundation stone of Indoor swimming pool at Jammu, felicitates paragliders | J&K Govt honoured with top achiever award in EoDB, BRAP at Udyog Samagam 2025 | "Modi wave drives Congress-Mukt Bharat Momentum": Gaurav | Janjati Bhagidari Utsav was organized in Lucknow under the guidance of Chief Minister Yogi Adityanath | Dewan Devi School celebrates Childrens Day | MCM hosts workshop on Social Entrepreneurship | IWC Jammu Sampark New Gen ceremonies Children Day | Alexander Memorial School, celebrates Children’s Day with joyful activities and festive spirit | GDCW Kathua hosts guest lecture on media opportunities | Hindi Fortnight Prize Distribution Ceremony at Pondicherry University | Faculty development programme on "Insight into Research Tools" conducted at DBU | PGIMER Shines at DHR-ICMR Summit 2025, Sweeps National Honors for 2nd Year in a Row | Ramakrishna Mission Medical Centre organizes Free Orthopedic & Physiotherapy Camp | AM Kia Jammu welcomed Kia delegates from Korea on their first official visit | Three-day workshop on "Brainstorming on Start-up Ideas" concludes at Government MAM College | CRC Jammu Treats Children to Memorable Day at Bagh-e-Bahu | Vishwa Bhartians excel in sports | DC Samba spearheads comprehensive development initiative at historic Purmandal Temple Shrine | SWD organises anti-drug awareness event for students | Punjab's South India Outreach Gains Momentum as Hyderabad-Chennai Roadshows Spark Strong Investor Interest | Children's Day Celebrated at CCI Palaash and CCI Parisha, Udhampur | Shiksha Niketan High School, Gandhi Nagar organises Bal Mela to celebrate Children's Day | GDC Vijaypur organises Electoral Literacy Awareness Campaign | Documentary on Vande Mataram Screened at Government Degree College Samba | Ups & downs of Power Politics in Bihar - I | Negligence in Eating Habits also Leads the Body and Mind towards Early Old Age. | Inner Song | ‘Vande Mataram’ inner song of every Indian heart: LG Sinha | Rana legacy lives on: BJP’s Divyani wins Nagrota by emphatic margin | PDP breaks NC’s Budgam citadel | Ruhullah committed political suicide by staying away from election campaign: CM Omar | House of Delhi bomber Dr Umar demolished | DySP Sunil Singh suspended, attached to PHQ | Property of separatist attached | CBK busts major land fraud, accused duped buyers of over Rs 29 lakhs | Back Issues  
 
news details
Sharp curve in India's 1st vertical bridge poses challenge for railways
4/9/2024 10:33:33 PM
Agencies
NEW DELHI, Apr 9: A sharp curve in the upcoming Pamban railway bridge, India's first vertical-lift bridge connecting the country's mainland with Rameswaram island, has become an additional challenge for the Railways besides its mechanical peculiarity and a rough sea.
The Rail Vikas Nigam Limited (RVNL), which is constructing this 2.08-km-long bridge, is facing a huge challenge in moving a lift span, which is 72.5-m-long, 16-m-wide and weighs 550 tonne, from the Rameshwaram end to 450 m in the sea to fix it to the bridge.
"We started moving this lift span on March 10 and till date, we have moved the 550 ton lift span 80 m towards the centre of the bridge. The biggest challenge is the 2.65 degree of curved alignment of the bridge. Had it been straight, we would have moved it faster," a senior official of RVNL said, adding the curved shape was essential due to various alignment changes.
The movement of the lift span to its final fixing point shall be completed by the end of May, as it still has to be carried 370 m more.
"Once we cross the curved portion, we can expedite its movement. We have taken a huge precaution while moving it in the sea as its size and weight requires great precision at each step," the official said.
The RVNL has set a deadline of June 30 to make the bridge operational and its officials say that they are trying their level best to meet it.
"Once the lift span is fixed, the remaining work is no big deal," an RVNL official said.
He added, "This lift span can be lifted up automatically up to 17 m for ships to pass. It will take 5 minutes to go up and the same time to come down and will be scheduled in such a way so that train services shouldn't be disrupted." The RVNL got this lift span designed from Spanish firm TYPSA and it was manufactured at Sattirakkudi Railway Station, which is 20 km away from the sea coast.
"We brought it in various parts and assembled it here at the coast because it was not possible to carry such a huge structure from the manufacturing point," the RVNL official said.
The train services between Mandapam in the mainland and Rameswaram island were suspended on December 23, 2022 after the existing rail bridge, which was built in 1913, was declared non-operational from the safety point of view.
"When the Pamban bridge was operational, trains used to move to the bridge and reach Rameshwaram. They used to move slowly on the Pamban bridge and reach the pilgrimage town in about 15 minutes," a Southern Railway official said.
At present, all trains terminate at Mandapam and people use road routes to reach Rameswaram. Prime Minister Narendra Modi laid the foundation stone of the new bridge, parallel to the old one, in November 2019 and the work was started in February 2020 by RVNL.
  Share This News with Your Friends on Social Network  
  Comment on this Story  
 
 
 
Early Times Android App
STOCK UPDATE
 
 
 
 
 
 
 
   
Home About Us Top Stories Local News National News Sports News Opinion Editorial ET Cetra Advertise with Us ET E-paper
 
 
J&K RELATED WEBSITES
J&K Govt. Official website
Jammu Kashmir Tourism
JKTDC
Mata Vaishnodevi Shrine Board
Shri Amarnath Ji Shrine Board
Shri Shiv Khori Shrine Board
UTILITY
Train Enquiry
IRCTC
Matavaishnodevi
BSNL
Jammu Kashmir Bank
State Bank of India
PUBLIC INTEREST
Passport Department
Income Tax Department
JK CAMPA
JK GAD
IT Education
Web Site Design Services
EDUCATION
Jammu University
Jammu University Results
JKBOSE
Kashmir University
IGNOU Jammu Center
SMVDU