Breaking News :   Terrorism claimed lives, shattered families: LG Sinha | ‘J&K witnessed massive infra expansion in healthcare post 2019’ | 30 years of tears: Kashmir’s forgotten terror-victims finally find their voice | Seizure of MP5 gun from Pak-trained terrorist alarmed security agencies | Justice Sanjeev Kumar inaugurates National Lok Adalat in Jammu | CBK cracks Rs 53 lakh land scam Files chargesheet against 4 accused | Income Tax Deptt sends SMS/emails for bogus political donation claims | MeT predicts light snowfall in Kashmir higher reaches | Former Law Secretary Goyal appointed as CIC | Over 200 OGWs detained in Kashmir | When personal history becomes cinema: Reading Dhurandhar through Aditya Dhar’s Kashmiri Pandit lens | Breakdown of Patel’s action derailed Kashmir Policy | DRDDG organized "Multi Specialty Free Test Camp” | Indian Army organised Paddar Cricket Premier League-2025 at Gulabgarh, Kishtwar | AIIMS OPD to become operational by March 2026: Rao Inderjit Singh | Secretary RDD inspects development projects in Marh Block | Samba police seizes 7 dumpers for illegal mining | Indian Defence Forces committed to adapting to changing environment: CDS General Chauhan | Kashmir gripped by Chilly Nights; Pulwama coldest at -4.2°C, Zojila plunges to -17°C | Introduction of LHB coaches in Train No. 19224/19223 | Chief Secretary visits mini-township Jagti | Satish Sharma inaugurates Indoor Stadium with multi-sports facility at Khour | Amit gives CLT formula for fast track economic growth in PHDCCI Delhi conclave | FICCI FLO JKL launches Menstrual Hygiene drive to strengthen women's health and participation in nation building | "Congress's ECI Lies Exposed: 73 Years of Constitutional Truth vs Political Distortion": Gaurav | Sant Hare Ram Dass Public School celebrates 9th annual function - "Journey of Culture" | 1013 cases Disposed off up with settlement of Rs 37272436 amount in National Lok Adalat in Udhampur | Chief of Army Staff, General Upendra Dwivedi reivews passing out parade at IMA | Public Centric Development is the Right of Every Citizen: Dr Devender Kumar Manyal | Proud beginning for towering tricolour at Banwat View Point Poonch | Pathania dedicates PMGSY roads worth Rs 100 crore to people of Udhampur | Five alumni of MRSAFPI commissioned into Indian Army and Indian Air Force | Leadership Summit at Thapar School of Management | JKSPYM SLCA organise training for Master-Volunteers of Dist. Ganderbal under Nasha Mukt Bharat Abhiyaan | Man causing public nuisance in Bhaderwah convicted of Community Service | Doda Police traced missing lady, reunited her with family | Inter-District drug peddler arrested with Heroin | Srinagar Emerges Champion in U-17 Boys UT Level Softball Tournament | Divine events collaboration with NDS has organise Music Competition | Govt PG College Rajouri organises Friendly Cricket Match | Government Polytechnic Reasi organises Awareness Programe on Stray Dog Attacks | J&K Players selected for the Indian Ball Badminton Team for International Ball Badminton Series | Back Issues  
 
news details
Sharp curve in India's 1st vertical bridge poses challenge for railways
4/9/2024 10:33:33 PM
Agencies
NEW DELHI, Apr 9: A sharp curve in the upcoming Pamban railway bridge, India's first vertical-lift bridge connecting the country's mainland with Rameswaram island, has become an additional challenge for the Railways besides its mechanical peculiarity and a rough sea.
The Rail Vikas Nigam Limited (RVNL), which is constructing this 2.08-km-long bridge, is facing a huge challenge in moving a lift span, which is 72.5-m-long, 16-m-wide and weighs 550 tonne, from the Rameshwaram end to 450 m in the sea to fix it to the bridge.
"We started moving this lift span on March 10 and till date, we have moved the 550 ton lift span 80 m towards the centre of the bridge. The biggest challenge is the 2.65 degree of curved alignment of the bridge. Had it been straight, we would have moved it faster," a senior official of RVNL said, adding the curved shape was essential due to various alignment changes.
The movement of the lift span to its final fixing point shall be completed by the end of May, as it still has to be carried 370 m more.
"Once we cross the curved portion, we can expedite its movement. We have taken a huge precaution while moving it in the sea as its size and weight requires great precision at each step," the official said.
The RVNL has set a deadline of June 30 to make the bridge operational and its officials say that they are trying their level best to meet it.
"Once the lift span is fixed, the remaining work is no big deal," an RVNL official said.
He added, "This lift span can be lifted up automatically up to 17 m for ships to pass. It will take 5 minutes to go up and the same time to come down and will be scheduled in such a way so that train services shouldn't be disrupted." The RVNL got this lift span designed from Spanish firm TYPSA and it was manufactured at Sattirakkudi Railway Station, which is 20 km away from the sea coast.
"We brought it in various parts and assembled it here at the coast because it was not possible to carry such a huge structure from the manufacturing point," the RVNL official said.
The train services between Mandapam in the mainland and Rameswaram island were suspended on December 23, 2022 after the existing rail bridge, which was built in 1913, was declared non-operational from the safety point of view.
"When the Pamban bridge was operational, trains used to move to the bridge and reach Rameshwaram. They used to move slowly on the Pamban bridge and reach the pilgrimage town in about 15 minutes," a Southern Railway official said.
At present, all trains terminate at Mandapam and people use road routes to reach Rameswaram. Prime Minister Narendra Modi laid the foundation stone of the new bridge, parallel to the old one, in November 2019 and the work was started in February 2020 by RVNL.
  Share This News with Your Friends on Social Network  
  Comment on this Story  
 
 
 
Early Times Android App
STOCK UPDATE
 
 
 
 
 
 
 
   
Home About Us Top Stories Local News National News Sports News Opinion Editorial ET Cetra Advertise with Us ET E-paper
 
 
J&K RELATED WEBSITES
J&K Govt. Official website
Jammu Kashmir Tourism
JKTDC
Mata Vaishnodevi Shrine Board
Shri Amarnath Ji Shrine Board
Shri Shiv Khori Shrine Board
UTILITY
Train Enquiry
IRCTC
Matavaishnodevi
BSNL
Jammu Kashmir Bank
State Bank of India
PUBLIC INTEREST
Passport Department
Income Tax Department
JK CAMPA
JK GAD
IT Education
Web Site Design Services
EDUCATION
Jammu University
Jammu University Results
JKBOSE
Kashmir University
IGNOU Jammu Center
SMVDU