Breaking News :   White coats of terror: Police bust doctors-led terror module | Improving lives of people Govt's prime objective : LG Sinha | High-stakes by-elections today: Prestige battle for NC, BJP; PDP eyes revival in Budgam | Paid holiday for voters today | Former Police officer gets 3-year jail for forging DOB | HC quashes charges against town planner | Ex-LBA chief alleges Buddhist under-representation in talks with MHA | Women Reservation Act 2023: SC seeks Centre’s reply on plea for implementation | PM Modi to visit Bhutan today | Anantnag Police continue raids against anti-national elements | Minimum temperature dips across Kashmir | BSF porter dies | Man set ablaze, hospitalised | A New Vision of the Bhagwat and the Concept of a Harmonious India | Golden Dawn—India’s Women Made Olympic History | India Moving Fast | SMVDU organizes two-day workshop on "Voices of India: Language, Culture, and Digital Humanities for Inclusive Education" | Congress, left suffer from 'Anti-RSS Phobia': Gaurav | Skill Development Centre organizes certificate distribution ceremony under PM Vishwakarma Yojna | Punjab SC commission chairman meets Governor, seeks stronger coordination for welfare of scheduled castes communities | NFR Loco Pilots Exemplary Vigilance Prevents Elephant Mishaps | Wave of patriotism and unity sweeps Uttar Pradesh under CM Yogi's leadership | JMC intensifies measures to control rising air pollution levels | Sham Lal Sharma reviews progress of development works on key ponds in Jammu North | 'Vande Mataram' had become source of inspiration for struggle against British Rule, induced patriotism among Indians: Balbir | NC concludes high-voltage campaign for Shameem Begum in Nagrota by-elections | Meeting of empowered committee on Micro, Small and Medium Enterprises held | All 16 DPSUs Serving As Strong Pillars Of India's Self-Reliance In Defence Production: Rajnath | Power Shutdown by KPDCL | CS visits Tawi Barrage, River front to assess pace of completion | 22 students from Allen Jammu selected for RMO | Ladakh moving towards self-reliance through integrated rural development: LG Kavinder | Director Information felicitates Gagan Jamwal on clinching Gold medal | Eight killed in blast near Red Fort, cars gutted and several injured | Madanjeet School of Green Energy Tech organise 5-day boot camp | MCM hosts thought-provoking workshop on Gender Realities | GDC Ramnagar organises Seminar on “History, Significance of Vande Mataram” | International Daily Rising School celebrates “The Rising Retreat” 2025 | DAV College hosts landmark International Seminar on Hindi, Non-Hindi Literature in the Indian Knowledge System | Anantnag Police acts tough against Illegal mining, vehicles seized | Comprehensive review meeting held on RDSS implementation, Power infrastructure development in Ladakh | Desh Bhagat University hosts 1st DBU Model United Nations 2025 | PHDCCI–HRAK delegation discussed key issues concerning tourism, trade, industry with Commissioner | Workshop on Soil Health Management held at Panchayat Sarore; 100 Farmers benefit from training | NIPER SAS Nagar launches Two-Week ITEC Training Programme | GDC Billawar, SKUAST-J organises One day Boot Camp on Innovation, Entrepreneurship | Girdhari Lal Dogra Memorial college, Hiranagar Organized POSH Act Awareness Programme | Girdhari Lal Dogra Memorial college, Hiranagar Organized POSH Act Awareness Programme | Anantnag Police continues Raids on Anti-National Elements, launches CASOs | IIM Jammu Inaugurates Thirteenth Batch of Nurturing Future Leadership Program | Students of SMVD College of Nursing, Kakryal Katra visit Indian Red Cross Society, J&K-UT | Raman Suri calls for public support to finish terror ecosystem | Back Issues  
 
news details
CEO ERA reviews progress on EOC building, 160 bedded additional block at B&J hospital
7/13/2024 10:03:16 PM
Early Times Report
SRINAGAR, July 13: Chief Executive Officer (CEO), Jammu and Kashmir Economic Reconstruction Agency, (ERA), Aijaz Asad, today chaired a meeting to review progress on various flagship sub projects being executed under the World Bank funded Jhelum Tawi Flood Recovery Project in the region.
While assessing work progress on the state of art EOC (Emergency Operations Centre) being constructed under JTFRP at an estimated cost of Rs 40.16 crore, the CEO was informed that most of the civil works including construction of main building, service building, dormitory building have been completed. Besides, construction of internal roads, boundary walls around the complex and installation of electrical poles has also been done while construction of fire fighting tank and other ancillary works is in progress.
The CEO directed the executing agency to immediately take up the work on installation of HVAC (heating ventilation and air conditioning) system in the building and simultaneously accelerating other activities under the prestigious sub-project to ensure its timely completion.
Pertinently, the State of Art Emergency Operations Centre (EOC) building at Ompura Budgam is being constructed under the component of Strengthening of Disaster Management Capacity of JTFRP which comprises of Main Control Building with G+1 floor, Service Block, Dormitory Building for NDRF & SDRF personnel, Recreation and large sized warehouse which will be used for stocking of various relief and rescue equipments and essential food commodities.
Later, Aijaz Asad reviewed progress on construction of 160 bedded additional block at Bone and Joint, hospital, Barzulla being constructed at a cost of Rs 103.27 crore. The CEO was informed that work on the sub-project is in advanced stage while installation of lifts, construction of connecting corridor between the old and new hospital buildings, other ancillary work on the main building is in full swing.
Aijaz Asad directed the R&B (PWD) to further expedite the pace of work on the sub project ensuring its completion within the stipulated timeline.
While briefing the CEO about the progress on construction of additional block at GDC, Bemina, the SE R&B, (PWD) informed that work on installation of lifts in the building and other minor ancillary works is being given further push to ensure earliest completion of the sub-project.
The CEO directed the engineers to meticulously monitor the progress of work on all the works being executed under the World Bank funded JTFRP to ensure that these are completed within the stipulated project deadline. He also directed for strict monitoring of quality parameters of these vital works.
Present in the meeting were Rakesh Mahajan, Director, Technical, JTFRP, Dr Altaf Kawoosa, Medical Superintendent, Bone & Joint Hospital, Barzulla, Sushil Kumar, Project Manager, JKERA, Mushtaq Ahmad, SE, R&B (PWD) Central and other senior officers of J&KERA, R&B (PWD) and Health Department.
  Share This News with Your Friends on Social Network  
  Comment on this Story  
 
 
 
Early Times Android App
STOCK UPDATE
 
 
 
 
 
 
 
   
Home About Us Top Stories Local News National News Sports News Opinion Editorial ET Cetra Advertise with Us ET E-paper
 
 
J&K RELATED WEBSITES
J&K Govt. Official website
Jammu Kashmir Tourism
JKTDC
Mata Vaishnodevi Shrine Board
Shri Amarnath Ji Shrine Board
Shri Shiv Khori Shrine Board
UTILITY
Train Enquiry
IRCTC
Matavaishnodevi
BSNL
Jammu Kashmir Bank
State Bank of India
PUBLIC INTEREST
Passport Department
Income Tax Department
JK CAMPA
JK GAD
IT Education
Web Site Design Services
EDUCATION
Jammu University
Jammu University Results
JKBOSE
Kashmir University
IGNOU Jammu Center
SMVDU