Breaking News :   Suspension of Indus Water Treaty could lead to hunger, thirst in Pakistan, admits Minister | VPN usage banned in Doda after suspected movement of terrorists | Jammu Cong leaders concerned over controversial remarks by Kashmir colleagues | Centre bans import of goods from Pak; prohibits vessels; blocks postal services | CM Omar calls on PM Modi | Border skirmishes continue for 9th day | Take stand against perpetrators: Farooq urges J&K people | NIA obtains Rana’s voice, handwriting samples | CRPF dismisses jawan for concealing his marriage with Pak Woman | ACB arrests Incharge PP GMC Jammu, his driver | Empowering Youth: 67 cases of Mission Youth schemes approved | ACB arrests Incharge PP GMC Jammu, his driver | Dal Lake Boat Capsize Youth’s body recovered | Rajnath set to skip Russia’s ‘Victory Day Parade’ | NMC cancels admission of 14 students, orders suspension of 26 more | Power Shut down | DC Reasi inspects ongoing cleanliness of water structures | U-14 boys compete in Carrom, Chess, Badminton, Yoga & Wrestling | Bandipora Legislators discuss roadmap for district | Desh Bhagat Global School NCC Navy Cadets Excel at Annual Training Camp | Training program on PMAY-U 2.0 held | Seminar on ‘Drug Addiction: A Curse’ held | GBHSS Rajouri organises maiden INTROFEST 2025 | Sadhotra exhorts women to play role in societal transformation, combating drug menace | Operation of 3 medical stores suspended for violating conditions of licences | WAVES 2025: Radio's Digital Future with Analog Coexistence Stressed by Global Experts | Union Minister of State Dr L Murugan honours 12 Community Radio Stations for their outstanding contributions | Nations adopt WAVES declaration to champion heritage, creativity, and collaboration in AI era | Netflix CEO Ted Sarandos Discusses Impact of Streaming on Indian Filmmaking at WAVES Summit | Centre's ban on Pakistan trade a strategic move post-Pahalgam Attack: Kavinder | Panun Kashmir urges Government to declare Pakistan a terrorist state | JMC allots modern kiosks and rehris to registered vendors | Rotary Club donates school supplies, inspires youth to give back | DC, SSP chair civil society meeting to address local developmental issues | MIER College of Education hosts Theatrical Tribute to Samuel Beckett's Legacy | Donation box theft case at temple solved by Jammu Police | Samba police seizes five vehicles for illegal mining activities | BBIA Club inaugurated by Samba Deputy Commissioner | GCW Udhampur NCC Cadets Excel at CATC Camp | GDC RS Pura hosts Poster Display on Viksit Vibrant Village Program | Kuldeep Gupta to represent AKF at Asian Youth Games 2025 technical meeting | Jaypee University hosts HR Conclave 2025 to strengthen academia-industry synergy | LPU's class of 2025 bids farewell with cheers, tears, and beats | GDC Ramgarh observes World Press Freedom Day | GDC Ganderbal organises annual road race | Back Issues  
 
news details
DDC reviews progress of CRF, NABARD Projects in Doda district
1/21/2025 10:50:16 PM
Early Times Report

DODA, Jan 21: District Development Commissioner (DDC) Harvinder Singh on Tuesday chaired a crucial review meeting in the mini conference hall, DC Office Complex, to assess the progress of projects funded under the Central Road Fund (CRF) and NABARD schemes.
The meeting was attended by the Chief Planning Officer (CPO), Superintending Engineers of PWD (R&B) Chenab Circle and Hydraulic Circle, Assistant Commissioner Revenue, Divisional Forest Officer, Chief Medical Officer, and Block Medical Officer. Officials stationed in Bhaderwah and Batote joined virtually to provide updates on their respective projects.
The DDC emphasized the importance of expediting ongoing projects to enhance the district's infrastructure and socio-economic development.
The Superintending Engineers presented detailed updates on status of the projects, challenges, and proposed solutions. Issues related to land acquisition, technical approvals and inter-departmental coordination were extensively discussed, with the DDC directing officers to address these bottlenecks promptly.
Special focus was placed on resolving delays, particularly those involving land disputes, forest clearance, and road construction issues, for which coordination with Tehsildars was mandated. The DDC also instructed the termination, blacklisting, and re-tendering of significantly delayed projects within a week.
The review also covered the progress of community-centric projects, such as improving road connectivity, irrigation facilities, and healthcare infrastructure. The construction of PHCs and road connectivity to these centers was highlighted, with officers directed to prioritize their timely completion. Forest clearance and land acquisition issues were taken up, and the DDC assured full administrative support to resolve such challenges.
Concluding the meeting, the DDC stressed the importance of maintaining quality standards, transparency in fund utilization, and accountability among departments. He directed officials to submit comprehensive progress reports for effective monitoring and assured that the administration would extend all necessary support to ensure impactful results.
  Share This News with Your Friends on Social Network  
  Comment on this Story  
 
 
 
Early Times Android App
STOCK UPDATE
  
BSE Sensex
NSE Nifty
 
CRICKET UPDATE
 
 
 
 
 
 
 
 
   
Home About Us Top Stories Local News National News Sports News Opinion Editorial ET Cetra Advertise with Us ET E-paper
 
 
J&K RELATED WEBSITES
J&K Govt. Official website
Jammu Kashmir Tourism
JKTDC
Mata Vaishnodevi Shrine Board
Shri Amarnath Ji Shrine Board
Shri Shiv Khori Shrine Board
UTILITY
Train Enquiry
IRCTC
Matavaishnodevi
BSNL
Jammu Kashmir Bank
State Bank of India
PUBLIC INTEREST
Passport Department
Income Tax Department
JK CAMPA
JK GAD
IT Education
Web Site Design Services
EDUCATION
Jammu University
Jammu University Results
JKBOSE
Kashmir University
IGNOU Jammu Center
SMVDU