Breaking News :   Siblings ran international drug cartel on directions of handlers in Pak, Canada | LG Sinha releases ‘Jai Kashmir’ | Delegations call on Lieutenant Governor | 50 Pak terrorists active in eight Jammu districts | We hit 9 terror targets in Pak with precision: NSA Doval | Crime Branch books SI, teacher, Anganwadi worker for using fake documents | PM Modi to distribute over 51,000 appointment letters | Wildlife Board clears over 30 defence projects | ED restores Rs 55 cr proceeds of crime | 10th batch of over 6,400 pilgrims leaves for Kashmir | ACB arrests lineman for accepting bribe | GST-linked bank account mandatory for e-tendering | Groom among 3 injured in mishap | NMC suggests 3-tier grievance-redressal mechanism | Justice for terror victims | Technology is helping turn NEP 2020 vision into reality in classrooms | The paper bag: A simple switch for a cleaner world | Kanwar Yatra: A Journey of Faith, Endurance, and Devotion | CM Yogi hears grievances of people in Janata Darshan | Yogi Govt deploys anti-drones to ensure safe, secure Kanwar Yatra | CM Pushkar Singh Dhami stresses simplification of Loan, Insurance processes | Jodhamal student sets an international record | Back Issues  
 
news details
Kathua district achieves major headway in execution of PMGSY projects
6/23/2025 9:59:57 PM
Early Times Report
KATHUA, June 23: Additional District Development Commissioner (ADDC) Surinder Mohan today chaired a meeting to review the status of Pradhan Mantri Gram Sadak Yojana (PMGSY) projects. The meeting was held in the VC Room of the DC Office Complex.
Reviewing the performance of the PMGSY Kathua Division, the Executive Engineer informed that of 124 projects sanctioned under Phase I work on 123 has been completed, while all 6 schemes under Phase-II stand completed. Similarly 6 out of 8 schemes sanctioned under Phase-III have been completed. Additionally, 10 new schemes have been earmarked under Phase-IV for implementation.
The ADDC was also apprised that out of 13 bridge projects taken up in the division, 5 have been completed, while utility shifting is pending on 5 other bridges.
In the PMGSY Division Billawar, of 122 schemes sanctioned under Phase-I, 114 have been completed. The remaining 8 schemes-4 each in Billawar and Bani Sub-Divisions-are pending due to forest clearance and other related issues, even as all schemes sanctioned under Phase-II and Phase-III have been completed. The Division has received sanction of 5 new schemes under the Phase-IV.
The ADDC instructed the concerned Executive Engineers to expedite the execution of all pending works and ensure their timely completion. He emphasized on resolving bottlenecks to achieve the set targets within stipulated time frame.
The meeting was attended by Chief Planning Officer Kathua, Ranjit Thakur and other concerned officers.
  Share This News with Your Friends on Social Network  
  Comment on this Story  
 
 
 
Early Times Android App
STOCK UPDATE
  
BSE Sensex
NSE Nifty
 
CRICKET UPDATE
 
 
 
 
 
 
 
 
   
Home About Us Top Stories Local News National News Sports News Opinion Editorial ET Cetra Advertise with Us ET E-paper
 
 
J&K RELATED WEBSITES
J&K Govt. Official website
Jammu Kashmir Tourism
JKTDC
Mata Vaishnodevi Shrine Board
Shri Amarnath Ji Shrine Board
Shri Shiv Khori Shrine Board
UTILITY
Train Enquiry
IRCTC
Matavaishnodevi
BSNL
Jammu Kashmir Bank
State Bank of India
PUBLIC INTEREST
Passport Department
Income Tax Department
JK CAMPA
JK GAD
IT Education
Web Site Design Services
EDUCATION
Jammu University
Jammu University Results
JKBOSE
Kashmir University
IGNOU Jammu Center
SMVDU