Breaking News :   The traditional customs and folk culture retreated in the blind race of modernity | Issues of heatwaves and powercuts | Baba Budan Ali Shah Jammu Chatha | Yashwant Mehta: A Voice that Resonates in Gujarati Literature | Failure is not the End – It’s the First step toward success | Injecting Fear | Sparkle Group, Amar Singh Club Organize Yoga Day | Celebration of International Yoga Day-2025 | Employment generation, improving employability of youngsters our top priority: LG Sinha | J&K gets major infra boost; 19 road, tunnel projects worth Rs 10,637 crore approved | NIA gets 5-day custody of two brothers arrested for sheltering Pak terrorists | ‘Terrorists used Chinese App ‘Ultra’ to contact Pak handlers’ | ‘Operation Sindoor’ achieved all its objectives: Rajnath Singh | Arab countries next targets of US, Israel: Dr Farooq | IRCTC to serve Kashmiri vegetarian cuisine on Katra-Srinagar Vande Bharat Train | Heavy rains trigger landslide on Mata Vaishno Devi track | Air India Express returns without landing | PM Modi pays tributes to Mookerjee on death anniversary | JKEEGA condoles the demise of Junior Engineer PDL | Brig Anjan Kumar Basumatari Inaugurates Blood Donation Camp | Shia Federation holds meeting | Northeast Frontier Railway steps up services for Ambubachi Mela devotees | CS for time-bound upgradation of services at SKIMS | Heroin smuggler arrested in Katra | RKS approves annual development plan for Govt Hospital Sarwal | DC Kathua reviews anti-flood measures | Udhampur police attaches property of terror accused | Kavinder pays tributes to Dr SP Mookerjee | MLA Arvind kick-start black topping work of Bhagwati Nagar Road | Bovine smuggling attempt foiled by Udhampur police | Kathua district achieves major headway in execution of PMGSY projects | Interstate drug kingpin arrested | Yogi govt to ensure environmental monitoring in Defense Corridor | Stop discrimination with Jammu: YRS | Capacity Building Programme of FPO's commences | AAP to contest by-polls from Nagrota Assembly Constituency | EC 's recent order to destroy elections records blow to democracy - Ravinder Sharma | J&K Deaf Athletes Shine at National Championships | Dr Suminder Singh interacts with CM Omar Abdullah | DPS Jammu students excel at 10th District Level Speedball Tournament 2025 | Empowering Future Financial Leaders: BBA (BFSI) programme at MCM | International Yoga Day celebrated at Govt SPMR College of Commerce | GDC Mahanpur concludes three-days Yoga workshop | Dogra Degree College celebrates Olympic Day | India top medal tally at Seychelles Boxing Tournament | SAI Diaries: TJ, Animesh Kujur enter TOPS developmental group; Pranati named for TAGG | Back Issues  
 
news details
Kathua district achieves major headway in execution of PMGSY projects
6/23/2025 9:59:57 PM
Early Times Report
KATHUA, June 23: Additional District Development Commissioner (ADDC) Surinder Mohan today chaired a meeting to review the status of Pradhan Mantri Gram Sadak Yojana (PMGSY) projects. The meeting was held in the VC Room of the DC Office Complex.
Reviewing the performance of the PMGSY Kathua Division, the Executive Engineer informed that of 124 projects sanctioned under Phase I work on 123 has been completed, while all 6 schemes under Phase-II stand completed. Similarly 6 out of 8 schemes sanctioned under Phase-III have been completed. Additionally, 10 new schemes have been earmarked under Phase-IV for implementation.
The ADDC was also apprised that out of 13 bridge projects taken up in the division, 5 have been completed, while utility shifting is pending on 5 other bridges.
In the PMGSY Division Billawar, of 122 schemes sanctioned under Phase-I, 114 have been completed. The remaining 8 schemes-4 each in Billawar and Bani Sub-Divisions-are pending due to forest clearance and other related issues, even as all schemes sanctioned under Phase-II and Phase-III have been completed. The Division has received sanction of 5 new schemes under the Phase-IV.
The ADDC instructed the concerned Executive Engineers to expedite the execution of all pending works and ensure their timely completion. He emphasized on resolving bottlenecks to achieve the set targets within stipulated time frame.
The meeting was attended by Chief Planning Officer Kathua, Ranjit Thakur and other concerned officers.
  Share This News with Your Friends on Social Network  
  Comment on this Story  
 
 
 
Early Times Android App
STOCK UPDATE
  
BSE Sensex
NSE Nifty
 
CRICKET UPDATE
 
 
 
 
 
 
 
 
   
Home About Us Top Stories Local News National News Sports News Opinion Editorial ET Cetra Advertise with Us ET E-paper
 
 
J&K RELATED WEBSITES
J&K Govt. Official website
Jammu Kashmir Tourism
JKTDC
Mata Vaishnodevi Shrine Board
Shri Amarnath Ji Shrine Board
Shri Shiv Khori Shrine Board
UTILITY
Train Enquiry
IRCTC
Matavaishnodevi
BSNL
Jammu Kashmir Bank
State Bank of India
PUBLIC INTEREST
Passport Department
Income Tax Department
JK CAMPA
JK GAD
IT Education
Web Site Design Services
EDUCATION
Jammu University
Jammu University Results
JKBOSE
Kashmir University
IGNOU Jammu Center
SMVDU