Breaking News :   Jammu getting its due share of inclusive development under Omar Abdullah-led Government: RL Gupta | National Conference afraid of defeat, avoiding Panchayat Polls in J&K: LoP Sharma | MLA Arvind Gupta inaugurates development works worth Rs 65 lakh in Jammu West | BIS raids jewellery outlet in Amritsar; 95 gold jewellery articles weighing 467.44g seized over Hallmarking violations | Reasi police intensify anti-narcotics drive | Distirct police Reasi inspects fertiliser & chemical shops; directs installation of CCTV cameras | Strong law and order and uninterrupted power supply under Yogi Govt give business a new boost | Show-Cause Notice Issued After Chhattisgarh Woman IPS Officer Fires AK-47 During Dussehra Ritual | India Stands For Peace | Chemicals in Festive Foods: A Dangerous Gamble with Human Health | Basohli Utsav: Celebrating Heritage | Crescent School Shines at Speedball Championship | SJVN is organizing 29th Inter CPSU Carrom Tournament | 72 lakh voters ready, but no poll date: J&K’s Panchayat election mystery | Ladakh Panchayat polls on Nov 21 | Delay in court replies won’t be tolerated : Govt warns officers | Amit Shah slams opposition, says protests will achieve nothing | HC main wing to close in Srinagar Oct 31 | J&K to witness dry weather till October 31 | 250-bed maternity hospital awaits site finalisation in Anantnag: CM Omar | India will support every meaningful effort to bring peace to Ukraine, West Asia: PM Modi | J&K Bank net profit rises 10% to Rs 546 crore in September quarter | Man sets stepmother ablaze | 2 OGWs arrested in Baramulla | Man held for pasting anti-national posters | Back Issues  
 
news details
NFR achieves major breakthrough of Tunnel No. 8
3/15/2026 10:14:30 PM
MALIGAON, Mar 15: Northeast Frontier Railway (NFR) has achieved a major milestone in the Sivok-Rangpo Railway Project with the successful breakthrough of Tunnel No. 8 on 12th March 2026. The breakthrough was achieved jointly by NFR and IRCON International Ltd., marking significant progress in this strategically important rail connectivity project for the NE region.
Tunnel No. 8 is one of the major tunnels of the project, with a total length of 4.148 km and an additional adit of 1.010 km. The excavation and mining of the tunnel were carried out under extremely challenging geological conditions, including highly weak, weathered and fractured rock strata. The work also faced additional challenges due to the uncertainties of hilly terrain and sensitivities related to the nearby NH-10 corridor.
With the successful completion of mining in Tunnel No. 8, tunnel excavation has now been completed in 13 out of the total 14 tunnels of the Sivok-Rangpo Railway Project. This achievement marks a crucial step forward in the overall progress of the project.
Significant progress has also been made in other major components of the project. Tunnel lining works, covering a total length of 32.4 km, have already been completed in 12 tunnels. In addition, ballastless track laying has been completed over 21 km inside the tunnels, further advancing the project towards operational readiness.
The Sivok-Rangpo New Rail Link Project is one of the crucial connectivity projects for the NE region. The project aims to connect the state of Sikkim with the national railway network and is part of the broader initiative of Indian Railways' Capital Connectivity project.
The total length of the project is 44.96 km, out of which 41.55 km lies in West Bengal and 3.41 km in Sikkim. About 38.623 km (around 86%) of the route runs through tunnels, 2.24 km through bridges, and 4.79 km consists of open cutting and station yards. Construction work involves 14 tunnels, with the longest tunnel measuring about 5.30 km and the shortest around 538 metres. The project also includes 13 major bridges and 10 minor bridges. The new railway line will have five stations i.e. Sivok, Riyang, Melli, Rangpo, and an underground halt station at Teesta Bazar, which will be among the unique infrastructure features of the project. Once completed, the project will connect Sikkim significantly improving transportation, ensuring uninterrupted supply of essential commodities, and boosting economic development in the region.
Construction activities across all fronts are progressing steadily, including civil works, track installation and railway electrification. The NFR is continuing its efforts to complete the remaining works and commission the Sivok-Rangpo Railway Project by December 2027, which will greatly enhance rail connectivity to the state of Sikkim and boost regional development and mobility.
  Share This News with Your Friends on Social Network  
  Comment on this Story  
 
 
 
Early Times Android App
STOCK UPDATE
 
 
 
 
 
 
 
   
Home About Us Top Stories Local News National News Sports News Opinion Editorial ET Cetra Advertise with Us ET E-paper
 
 
J&K RELATED WEBSITES
J&K Govt. Official website
Jammu Kashmir Tourism
JKTDC
Mata Vaishnodevi Shrine Board
Shri Amarnath Ji Shrine Board
Shri Shiv Khori Shrine Board
UTILITY
Train Enquiry
IRCTC
Matavaishnodevi
BSNL
Jammu Kashmir Bank
State Bank of India
PUBLIC INTEREST
Passport Department
Income Tax Department
JK CAMPA
JK GAD
IT Education
Web Site Design Services
EDUCATION
Jammu University
Jammu University Results
JKBOSE
Kashmir University
IGNOU Jammu Center
SMVDU