Delay in projects to cost exchequer Rs 5.6 cr
11/17/2010 9:36:57 PM
EARLY TIMES REPORT
Nov 17, 2010 (New Delhi)The cost over-run of five hydro power projects due to various delays is pegged at Rs. 5,645.1 crore by the Ministry of Statistics and Programme Implementation.
The review of hydro projects worth over Rs. 1,000 crore indicated that the cost over escalation in two such projects was over 80 per cent.
The projects being monitored by the ministry include Tehri Pump Storage Plant, Koteshwar in Uttrakhand, Teesta Low Dam-III and Lower Subansiri.
The ministry observed that the cost escalation of the Tehri Pump Storge Plant (1000 mega watt) in Uttarakhand is as high as 88.58 per cent. The project would now cost Rs. 3,124.76 crore compared to original estimate of Rs. 1,657 crore. It is expected to be completed in March, 2012 against the original deadline of July, 2010.
Similarly, the other project where cost escalation is as high 84.27 per cent is Koteshwar hydro electric project (400 mw) in Uttarakhand. Now it is expected to cost Rs. 2,398.39 crore compared to its original cost of Rs. 1,301.56 crore. It was to be completed in April, 2005 but it is now expected to be operational by December, 2010.
One other such project is Teesta Low Dam Project-III (132 mw) in West Bengal. The project cost escalated by 66.39 per cent to Rs. 1,279.40 crore compared to original estimated of Rs. 768.92 crore. Now it is expected to be completed by December 2011 against its earlier deadline of March 2007.
The cost of 330 mw Kishanganga hydro project in Jammu and Kashmir has also be escalated by 62.69 per cent to Rs. 3,642.04 crore as against its original cost of Rs. 2,238.67 crore. It was to be completed by July, 2014. But now it is expected to be operational by January, 2016.
NHPC's yet another project Lower Subansiri (2,000 mw) in Arunachal Pradesh has run into cost overrun of Rs. 1,166.66 crore and is now estimated at Rs. 7,451.99 crore.
  Share This News with Your Friends on Social Network  
  Comment on this Story  
 
 
top stories of the day
 
 
 
Early Times Android App
STOCK UPDATE
  
BSE Sensex
NSE Nifty
 
CRICKET UPDATE
 
 
 
 
 
 
 
 
   
Home About Us Top Stories Local News National News Sports News Opinion Editorial ET Cetra Advertise with Us ET E-paper
 
 
J&K RELATED WEBSITES
J&K Govt. Official website
Jammu Kashmir Tourism
JKTDC
Mata Vaishnodevi Shrine Board
Shri Amarnath Ji Shrine Board
Shri Shiv Khori Shrine Board
UTILITY
Train Enquiry
IRCTC
Matavaishnodevi
BSNL
Jammu Kashmir Bank
State Bank of India
PUBLIC INTEREST
Passport Department
Income Tax Department
JK CAMPA
JK GAD
IT Education
Web Site Design Services
EDUCATION
Jammu University
Jammu University Results
JKBOSE
Kashmir University
IGNOU Jammu Center
SMVDU