Breaking News :   From Srinagar, Defence Minister warns Pak: Stop supporting terrorism or face consequences | Nation proud of armed forces for scripting historic victory : LG Sinha | Our relations, dealings with Pak will be strictly bilateral: EAM | Of 14 identified terrorists, security forces neutralize 6 | ‘Pak’s nuclear weapons should be brought under IAEA watch’ | Echoes of tragedy: Aruba, Ayan’s innocence leaves Poonch in tears | Army Chief visits forward areas in Baramulla | 3 terrorists killed in Tral encounter | Search operation underway in Reasi | Schools reopen in 5 border districts across Jammu | Civil Aviation Minister reviews security at Srinagar, Jammu airports | CUET-UG cancelled at Rangreth centre | Fire breaks out in Poonch | Assistant Compiler terminated | Parihar, Azeem appointed Administrative Judges | Thakur appointed DG IRITM | Gold plunges amid weak global demand | Unmatched Precision | Dr Darakhshan Andrabi hails Operation Sindoor, condemns Pakistan for terror activities | MLA Vikram Randhawa honours CBSE class 10th & 12th toppers | Cracks in promises: Newly built Kourgali-Lalli road falls apart, villagers demand action | Village level teams to assess damages in shelling affected areas of Poonch | HC upheld the PSA of hardcore criminal | Punjab: DSP held for smuggling drugs, mobile phones in Sangrur Jail | Delhi High Court HC asks for NIA reply on Engineer Rashid bail plea | Court awards 10 years RI Rs 1 lakh fine to five including father, mother, son | AAP expels OP Khajuria from Jammu and Kashmir Unit over 'Indiscipline' | Natrang celebrates 43rd Foundation Day | Indian Red Cross Society, dispatches urgent relief to Poonch amid border crisis | Mission Director reviews HADP initiatives during field visit to Marh | Jammu police nab drug peddler in Akhnoor, seize heroin-like substance | SJVN successfully achieved COD of 78.23 MW capacity of 1000 MW Bikaner Solar Power Project | Vice Chancellor SKUAST-Jammu reviews University functioning post border disruptions | Gurjar Desh Charitable Trust pays heartfelt tribute to martyr ADDC Dr Raj Kumar Thapa | Jammu police foil bovine smuggling bid, rescue 12 cattle | JSS Kathua achieves 100% board results for class X and XII in session 2024-25 | Broadridge India, LPU Forge Industry-Academia Partnership to Build Future-Ready Tech Talent | IIPPT College, Greater Noida Hosts Grand "Teacher Felicitation Ceremony | IQAC, GDC Majalta organizes lecture on "The Role of Youth in National Crisis" | We were never really close friends: Neeraj Chopra on Arshad Nadeem | National shooting selection trials 2 and 3 in New Delhi and Bhopal from May 21 to June 1 | Unnati, Malvika, Aakarshi Exit Thailand Open; India''s campaign ends | IIM Kashipur celebrates its largest, most diverse graduating class at 12th convocation | DLSA Kishtwar hosts Awareness Programme | SCJS Organizes Special Programme on Mother's Day and Buddha Purnima | JKRLM promotes health, hygiene among SHGs | Samba Police arrest two with 17g Heroin-like substance | DIC Ramban organises Awareness Camp | GCW Udhampur Hosts Symposium on Promoting Indian Classical Music | DC Reasi reviews implementation of Road Safety Action Plan | Nation will never forget the sacrifices of Martyrs : Sadhotra | Strong commitment to inclusivity cornerstone of NC govt: Dr Farooq | Power shut down | Govt stands firmly with its people, especially the border residents: Dy CM | Vikar Rasool Wani Demands Rs. 20 Lakh Relief & 10 Marla Land for Uri Border Villages Affected by Cross-Border Shelling | Back Issues  
 
news details
12 km Chitoo road hits blockade due to contractor's apathy
12/7/2019 11:25:45 PM
Asif Iqbal Naik
Early Times Report
JAMMU, Dec 7: The construction of 12 KM Ungaie Nallah to Chitoo in Padder Sub Division of Kishtwar District has hit the road blockade after contractor withdraw the men and machinery from the under construction road.
As per the details available with "Early Times", the PMGSY has allotted the contract for constriction of 12 KM road up to village Chitoo at the estimated cost of Rs. 12 Cr around two years ago, but according to the locals-the contractor last month without any reason stop the construction work on this road and later withdraw the machinery by shifting it to some other work as a result of which there is apprehension among the local population with regard to further delay in completion of this prestigious roads proposed to provide road connectivity to more than 300 households in this remote area of the Union Territory of Jammu and Kashmir.
Speaking to "Early Times" Sarpanch Tayari Saplesha Devi and Bansi Lal Naib Sarpanch, Panchayat Tyari inform that the contractor only manage to construct 400-500 meters of road in last two added that the pace of construction work was going on at slow.
The said that however in the midst of multifarious activities-this road project was important for the people of this area and was hoping for its early completion-but to their disappointment - the slow pace of construction work take heavy toll on its time bound completion-now withdrawal of men and machinery by the contractor without any reason had diminishes the hopes of its completion in a time bound manner.
The panchayat representatives requested that the road work may kindly got restarted at an earliest to mitigate the sufferings of the people of this backward, downtrodden and poverty stricken area.
They also called upon Additional District Development Commissioner Kishtwar Mohammad Hanief Malik and requested him to take up the matter with the senior officials of PMGSY and the contractor so that the construction work on Chitoo road could be restored.
They also raise the issue of damage of village road constructed by the RDD department at the hands of GREF authorities and urged upon the administration to issue necessary directions to GREF officials with regard to repairment of the said road that provide connectivity to hamlets of Tyari Holla and Tainow as the road is having public importance since same is being used for transportation of food grains and other goods by the people.
The road according to them has got damage at various places due to ongoing construction of Padder Highway that will connect Kishtwar District with neighboring state of Himachal Pradesh.
ADDC Kishtwar also take up the matter with concern officials and directed them to look into the matter beside also seeks explanation from the officials with regard to slow pace of work.
HE assured the Panchayat representatives as well as to the visiting delegation that District Administration is committed for expediting the pace of various developmental projects and further assured them that the issue raised by them will be looked into on top priority.
  Share This News with Your Friends on Social Network  
  Comment on this Story  
 
 
 
Early Times Android App
STOCK UPDATE
  
BSE Sensex
NSE Nifty
 
CRICKET UPDATE
 
 
 
 
 
 
 
 
   
Home About Us Top Stories Local News National News Sports News Opinion Editorial ET Cetra Advertise with Us ET E-paper
 
 
J&K RELATED WEBSITES
J&K Govt. Official website
Jammu Kashmir Tourism
JKTDC
Mata Vaishnodevi Shrine Board
Shri Amarnath Ji Shrine Board
Shri Shiv Khori Shrine Board
UTILITY
Train Enquiry
IRCTC
Matavaishnodevi
BSNL
Jammu Kashmir Bank
State Bank of India
PUBLIC INTEREST
Passport Department
Income Tax Department
JK CAMPA
JK GAD
IT Education
Web Site Design Services
EDUCATION
Jammu University
Jammu University Results
JKBOSE
Kashmir University
IGNOU Jammu Center
SMVDU