Breaking News :   Justice For Terror Victim Families | Kathua Administration welcomes first Batch of Amarnath Yatris at Lakhanpur | Yatra of resilience: LG to flag off first batch today after Pahalgam carnage, Op Sindoor | LG visits Yatri Niwas at Bhagwati Nagar, reviews arrangements | LG reviews final preparations | LG chairs high-level meeting, discusses issues of terror victim families | LG flags off fleet of ambulances in Ramban, Anantnag districts | 5 real brothers from Budgam among fraudulently selected candidates | Hope beneath the surface: Govt plans underground hospital in Poonch | ACB catches DDC member red handed | Crime Branch books J&K Bank officers, others for frauds | Back Issues  
 
news details
LG takes comprehensive review of various NHPC projects in J&K
850MW Ratle new joint venture project to become reality soon
10/11/2020 11:49:37 PM
EARLY TIMES REPORT

SRINAGAR, Oct 11: Lieutenant Governor, Manoj Sinha took a comprehensive review of the status of various projects of National Hydroelectric Power Corporation (NHPC) in the Union Territory of Jammu and Kashmir in a meeting at the Raj Bhavan here today.
With the intervention of Lt Governor, modalities have been finalized for the upcoming 850MW, new joint venture Ratle project which will augment the existing generation capacity in the region. The meeting also decided that the supplementary MOU will be finalized through joint discussions between MOP(GOI), GoJK (JKSPDC) and NHPC.
Threadbare discussions were also held to fast-track the execution of the upcoming Pakal Dul, Kiru, and Kwar projects. Cumulatively, the upcoming power projects will generate 6298MW at the cost of Rs 54593 crores substantially enhancing the generation capacity in the region.
Chairman & Managing Director (CMD), NHPC Limited, AK Singh briefed the Lt Governor regarding the details of commissioned and generation capacity of NHPC’s Power Stations across J&K, besides the present status of the NHPC projects under execution in the UT.
The Lieutenant Governor was briefed about the completed Projects of NHPC in J&K and their generation capacity included - Power Stations- Salal (Stage I & II), MW 690 ; URI-I , MW 480; Dulhasti- MW 390; Sewa II, MW 120; Uri II, MW, 240 and Kishanganga, MW 330; collectively generating 2250 MW.
The Lt Governor issued on-spot directions for completion of ongoing projects and called for better synergy between agencies for making J&K a power surplus region in the country. Remove bottlenecks, if any, hampering the completion of the projects, he added.
The Lt Governor enquired about the CSR works being carried out by the NHPC in the field of Healthcare, Education, Swachh Bharat and Vocational Training. He also sought details of the Direct & Indirect Employment generated through NHPC projects to residents of J&K.
BVR Subrahmanyam, Chief Secretary; Rohit Kansal, Principal Secretary, Power Development Department; AK Singh, CMD, NHPC; V K Maini, Executive Director, NHPC; Deepak Saigal, GM, Nodal Officer, Ratle; A.K. Choudhary, Managing Director, Chenab Valley Power Projects (CVPPL) and other senior functionaries were also present.
  Share This News with Your Friends on Social Network  
  Comment on this Story  
 
 
 
Early Times Android App
STOCK UPDATE
  
BSE Sensex
NSE Nifty
 
CRICKET UPDATE
 
 
 
 
 
 
 
 
   
Home About Us Top Stories Local News National News Sports News Opinion Editorial ET Cetra Advertise with Us ET E-paper
 
 
J&K RELATED WEBSITES
J&K Govt. Official website
Jammu Kashmir Tourism
JKTDC
Mata Vaishnodevi Shrine Board
Shri Amarnath Ji Shrine Board
Shri Shiv Khori Shrine Board
UTILITY
Train Enquiry
IRCTC
Matavaishnodevi
BSNL
Jammu Kashmir Bank
State Bank of India
PUBLIC INTEREST
Passport Department
Income Tax Department
JK CAMPA
JK GAD
IT Education
Web Site Design Services
EDUCATION
Jammu University
Jammu University Results
JKBOSE
Kashmir University
IGNOU Jammu Center
SMVDU