Breaking News :   Justice For Terror Victim Families | Kathua Administration welcomes first Batch of Amarnath Yatris at Lakhanpur | Yatra of resilience: LG to flag off first batch today after Pahalgam carnage, Op Sindoor | LG visits Yatri Niwas at Bhagwati Nagar, reviews arrangements | LG reviews final preparations | LG chairs high-level meeting, discusses issues of terror victim families | LG flags off fleet of ambulances in Ramban, Anantnag districts | 5 real brothers from Budgam among fraudulently selected candidates | Hope beneath the surface: Govt plans underground hospital in Poonch | ACB catches DDC member red handed | Crime Branch books J&K Bank officers, others for frauds | Back Issues  
 
news details
J&K’s Kashmir Rail Link; Udhampur-Chenani, Nashri-Ramban Road Projects reviewed
Cabinet Secretary reviews Key Infra Projects
12/16/2020 11:18:42 PM

Early Times Report

Jammu, Dec 16: The Cabinet Secretary, Rajiv Gauba today chaired a high level meeting to review 11 Key Infrastructure Projects being implemented by various ministries across India.
Chief Secretary, B V R Subrahmanyam along with Chief Secretaries of various States including Delhi, Gujarat, Uttrakhand, Haryana, Maharashtra, and Chattisgarh participated in the meeting.
The Cabinet Secretary laid emphasis on the timely completion of infrastructural projects to prevent associated cost escalations. He said regular review of such projects is essential to monitor the scheduled progress and timely resolution of various bottlenecks to prevent avoidable delays in the project completion.
Progress on the Udhampur-Srinagar-Baramulla Rail Link Project was also reviewed in the meeting. The Chief Secretary, J&K, apprised the Cabinet Secretary that the project is progressing as per its schedule and the issues regarding availability of raw material and land acquisition are being assiduously resolved. It was informed that 3 phases of the project have been completed so far and the remaining 111 km of the 4th phase, which includes the world’s highest bridge on river Chenab, will be completed within the stipulated timeline. Regarding the progress of work on Udhampur-Chenani and Nashri-Ramban sections of National Highway 44, it was informed that the issues with regard to the executing agency have been resolved and the work is progressing smoothly.
Other projects including Mumbai-Ahmedabad High Speed Rail Project, Mumbai Refinery Expansion Project, Navi Mumbai International Airport Project, Vadodra-Mumbai Expressway, Dwaraka Expressway NHAI Project, among others were also reviewed.
  Share This News with Your Friends on Social Network  
  Comment on this Story  
 
 
 
Early Times Android App
STOCK UPDATE
  
BSE Sensex
NSE Nifty
 
CRICKET UPDATE
 
 
 
 
 
 
 
 
   
Home About Us Top Stories Local News National News Sports News Opinion Editorial ET Cetra Advertise with Us ET E-paper
 
 
J&K RELATED WEBSITES
J&K Govt. Official website
Jammu Kashmir Tourism
JKTDC
Mata Vaishnodevi Shrine Board
Shri Amarnath Ji Shrine Board
Shri Shiv Khori Shrine Board
UTILITY
Train Enquiry
IRCTC
Matavaishnodevi
BSNL
Jammu Kashmir Bank
State Bank of India
PUBLIC INTEREST
Passport Department
Income Tax Department
JK CAMPA
JK GAD
IT Education
Web Site Design Services
EDUCATION
Jammu University
Jammu University Results
JKBOSE
Kashmir University
IGNOU Jammu Center
SMVDU