Breaking News :   New freight train service big step for Kashmir apple growers: LG Sinha | LG attends closing ceremony of ‘Jashn-e-Dal’ | Will take up restoration of Jmu-Sgr highway with Union Minister: CM Omar | Cloudburst triggers flash floods in Reasi, no casualties | Day 21: Vaishno Devi Yatra remains suspended | Fruit growers’ union delegation meets LG | Doda: Educational institutions reopen after 3 weeks | Fraudster impersonating LG’s duty officer held in Rs 50 lakh scam: CBK | PM Modi lays foundation stone of projects worth around Rs 40,000 crore in Bihar | PM Inaugurates 16th armed forces’ conference at Eastern Command HQ | ITR filing deadline ends | DC Budgam calls for stronger enforcement & rehabilitation measures | DYSSO Samba launches major Inter-Zonal Sports tournament | Modi’s Governance: Gujarat Model to Bharatiya Model | Safety of Indians in America | Celebrating National Hindi Diwas | Parcel Train | FICCI FLO JKL rolls out Phase-4 of flood relief efforts in Jammu | Kuch Din Toh Aaiyein Ladakh Mein: LG Kavinder appeals in Navi Mumbai | Give your best to steer our nation ahead in growth & development: DyCM | MLA Sham Lal Sharma Pays Tribute to Sir M. Visvesvaraya on Engineers Day | Power shut down in several areas | Parcel cargo train from Kashmir to Adarsh Nagar Delhi flagged off | Javid Dar reviews status of NH-44 restoration | Only Aadhaar-authenticated users can book online general tickets in first 15 mins from Oct 1: Railways | DC Srinagar convenes DLSCC meeting | MLA Poonch, Ajaz Ahmed Jan offer condolences | Pakistan's terror nexus exposed again at UNSC: Gaurav | Randhawa reviews preparations at Bawe Wali Mata Mandir | Itoo flags off Dental Awareness Rally on Oral health hygiene | MLA Arvind Gupta inaugurates long-pending drain work at Rajpura | Boy injured in landmine blast in Anantnag, dies | Indian Army's first exclusive freight train on USBRL marks breakthrough | Punjab police busts cross-border weapon smuggling module with links to Pak | WPI inflation turns positive after 2 months, at 0.52% in August | SC to pass order on Sept 26 in suo motu case over lack of functional CCTVs in police stations | On Engineer's Day GCET Jammu inaugurates two-week induction programme | Crackdown on illegal mining continue on 2nd day | Ramban police recovers 30 lost mobile phones | Ravinder visits rain affected areas of Sunderbani, seeks relief, restorations on war footing | AIIMS Bathinda reaffirms zero tolerance for unethical practices | Indian Army organised interaction with prominent locals, media at Samote | JKEDI launches 3rd batch of Management Development Programs | GDC Bishnah celebrates Hindi Diwas in collaboration with J&K Rashtriya Bhasha Prachar Samiti | YCET conducts Induction Program | CCI raise serious issue of infrastructure crises | GCOE Jammu celebrates Hindi Diwas | MCM celebrates Hindi Diwas with fervour | Dogra Degree College celebrates Hindi Diwas | IIM Jammu hosts valedictory xeremony of Management Development Program on Corporate Governance | 3 cab drivers booked for violating traffic advisory, overcharging | Doda Police urges public to combat fake news, misinformation | PM Modi at 75: A legacy of vision, valor, Nation-Building: Rohiin Chandan | IRCS J&K provides relief material to flood-affected | JKAACL Jammu organizes one day symposium | Principal Secretary, Culture inaugurates hindi Pakhwada at K.L. Saigal Hall | SP North Vivek Shekhar Sharma releases devotional bhajan “Lad Fadeya Mahamai Da” | IGNOU Jammu successfully concludes Swachhata Pakhwada, reaffirming commitment to cleanliness | Back Issues  
 
news details
DC Poonch reviews progress on construction of border Bunkers
7/16/2021 10:33:55 PM

EARly Times Report

POONCH, July 16: District Development Commissioner Poonch, Inder Jeet today chaired a meeting with officers to review the status of construction of Bunkers in the district.
During the meeting, Xen, PDD informed that out of 555 allocated to RDD, 309 bunkers stand completed till date, while more 112 are under construction and the work of the rest 134 is not started yet.
Out of 200 bunkers designated as languishing projects, 70 have been completed, 80 are in progress, while work of the remaining 50 is yet to start.
Xen PWD, informed that out of 633 bunkers allotted to his department, 617 have been completed and out of pending 16 , work on 14 is under execution and 2 bunkers have not been started due to a dispute. The DC directed the Xen, PWD, to clear the dispute by the end of July.
He directed the executing agency to expedite the pace of work on construction of border bunkers to ensure their timely completion. He also directed the concerned to submit the physical verification report of bunkers within a week.
The meeting was attended by Chief Planning Officer, Madan Lal, Assistant Commissioner Development, Rajesh Lakhan, Xen PWD, Mohd. Parvez, BDO's of all sub divisions besides other concerned officers were present.
  Share This News with Your Friends on Social Network  
  Comment on this Story  
 
 
 
Early Times Android App
STOCK UPDATE
  
BSE Sensex
NSE Nifty
 
CRICKET UPDATE
 
 
 
 
 
 
 
 
   
Home About Us Top Stories Local News National News Sports News Opinion Editorial ET Cetra Advertise with Us ET E-paper
 
 
J&K RELATED WEBSITES
J&K Govt. Official website
Jammu Kashmir Tourism
JKTDC
Mata Vaishnodevi Shrine Board
Shri Amarnath Ji Shrine Board
Shri Shiv Khori Shrine Board
UTILITY
Train Enquiry
IRCTC
Matavaishnodevi
BSNL
Jammu Kashmir Bank
State Bank of India
PUBLIC INTEREST
Passport Department
Income Tax Department
JK CAMPA
JK GAD
IT Education
Web Site Design Services
EDUCATION
Jammu University
Jammu University Results
JKBOSE
Kashmir University
IGNOU Jammu Center
SMVDU