Breaking News :   Focus on innovation, employability, entrepreneurship: LG Sinha to KU | Nitin Nabin becomes BJP’s youngest national working president? | Third Kashmiri youth arrested in Arunachal for spying for Pakistan | J&K set for Panchayat, Municipal polls as SEC appointment process begins | Technology should amplify human judgment, not replace it: CJI Surya Kant | No link found between COVID-19 vaccination, sudden deaths in young adults | Prez Murmu rejects mercy plea of man convicted for rape, murder of 2-year-old | CBI chargesheets 4 Chinese nationals | J&K Samadhan logs 1.02 lakh grievances in 2025, disposal rate at 86.27% | ‘Prioritise women, SC/ST officers for central deputation’ | Chargesheet filed against 40 persons | Higher reaches receive fresh snowfall | Bhaderwah awaits snowfall, winter tourism hit | Bhaderwah awaits snowfall, winter tourism hit | High Court staff clinch 15-run win over High Court advocates at Sher-e-Kashmir Stadium | Awareness programme on labour codes, social security schemes held at Banihal | SDM reviews working of Mission Yuva doots in Thathri | Kanpur–Lucknow Expressway set to power startup growth, position Lucknow as an innovation hub | Restoring Hope | The 2025 outlook for Scientists in India: Challenges, opportunities & pathways forward | Love for Brother or Cry for Livelihood? | National Mathematics Day 2025 | Vijay Diwas Observed at Bishnah with Patriotic Fervour | Madhu Param Hans delivers spiritual sermons to devotees | JKTJAC holds Teachers’ Convention at Jammu; Zonal Body of Zone Bhalwal Announced | Banwat View Point in Poonch will become a symbol of national pride: Balbir | Suresh inaugurates two key roads worth Rs 30 Lakh in Panchayat Kaneri | Indian Army organises Swachhata Pakhwada | Media plays Pivotal Role in shaping public opinion, advancing vision of Viksit Bharat: Rohiin Chandan | CLUJ flags off Yoga team for All India Inter-University Games | Dogra Sadar Sabha reviews preparations for Dogri Manyata Divas, Youth induction held | SMVDU faculty secures JKST&IC grant for immersive reconstruction of Ancient Capital Parihaspora | Messi arrives in Mumbai for day 2 of “GOAT Tour” | GGHSS Rehari concludes inspiring Three-Day Activity Camp with Focus on Youth Empowerment | FICCI FLO JKL launches menstrual hygiene drive to Strengthen Women’s Health, participation in Nation Building | Two CRPF jawans injured in IEDs blast in Saranda forest | Samba police foils bovine smuggling attempt | Panchayat Degwar residents hail Ajaz Jan for providing Rs 25 lakh for development works | ISRO lines up 7 launches, including uncrewed Gaganyaan mission by March 2026 | Four CMs, over 100 CEOs to attend WEF annual meeting | Honouring Martyrs through healing: Dr Sushil Cardiac camp at Pouni Reasi | Back Issues  
 
news details
CS directs operationalization of 8 resting places, 3 vehicle holding areas, before 31st October and 30th November respectively
Major Road Projects in Jammu and Kashmir reviewed
9/30/2021 11:32:18 PM
Early Times Report

SRINAGAR, Sept 30: The Chief Secretary, Dr.Arun Kumar Mehta today chaired a high-level meeting to review the progress of various road projects in Jammu and Kashmir under execution in the different schemes of UT and Central governments.
Administrative Secretaries of Home, Power Development, Public Works (R&B), Mining, besides Divisional Commissioners of Kashmir/Jammu, officers from BRO,NHAI, NHIDCL and concerned Deputy Commissioners participated in the meeting. It was informed that the Mining department has allottedshort-term permit for extracting the minor minerals to the executing agency to ensure continuous supply of construction material for the Jammu semi-ring road project. It was further informed that NHAI has constructed crash barriers/parapets at all the critical stretches on Udhampur-Ramban sectionto prevent occurrence of fatal accidents on the National Highway-44.
Dr Mehta directed the installation of such barriers on all critical stretchesof Ramban-Banihal section within a week, especially in the areas prone to frequent landslides and slippages.
To facilitate smooth traffic flow on the Ramban- Banihal stretch of the National Highway, the traffic police and district administration were directed to properly demarcate single-lane driving zones and ensure lane-driving and traffic discipline among the commuters.
The Chief Secretary further directed the District Administration, Ramban to reduce response time to 15 minutes for clearing up traffic snarl ups on the highway caused by vehicles breakdown or accidents by deploying adequate number of cranes on Ramban-Banihal stretch, particularly on the ‘under-construction stretches.
Dr. Mehta further directed NHAI to operationalize 8 rest areas ( wash rooms with mini eating joints) by 31st October, 2021 and all 3 vehicle holding areas/parking bays on NH-44 by 30th November, 2021 to provide ease of travel to the commuters on the National Highway.
He also directed the JKTDC to set up similar facilities on national highway for use by the public by 31st October, 2021.
The Chief Secretary also reviewed the progress on the Z-Morh tunnel; Srinagar-Shopian-Qazigund road; Srinagar semi-ring road project; Chenani-Sudmahadev-Goha road; Jammu-Akhnoor-Poonch road and the upcoming Delhi-Katra expressway and fixed specific timelines for their completion.
Dr Mehta also reviewed the status of works on bridges like Noor Jahan bridge, Brazloo bridge, Gadora bridge among others and gave specific timelines for their operationalisation so that they could be dedicated to the people of the UT.
It was directed that the Srinagar-Shopian-Qazigund along with bypass should be made operational by July, 2022.
The Chief Secretary asked the DC, Udhampur to hand over the 3.3842 hectares land to the executing agency by 7th October, 2021 so that work on the Chenani- Sudhmahadev Goha road is commenced.
District administrations of Jammu and Samba and Kathua were directed to hand over the possession of land for Delhi Amritsar Katra express way to the executing agency by 1st November, 2021.
Dr Mehta further directed that land acquisition for Z morh tunnel should be completed by 15th October 2021.
Similarly, the department was asked to make the Noor Jehan bridge trafficable by 31st December, 2021 besides readying Gadora bridge ready for inauguration by 1st January, 2021.
The Chief Secretary further directed that the condition of the road from Panthachowk to Badami Bagh cantonment should be improved by 15 October, 2021.
The Chief Secretary urged all the concerned Deputy Commissioners to expeditiously resolve all the land acquisition issues bedevilling the construction work on the highway and complete the land acquisition early so that the all ongoing projects are completed within the stipulated timelines.
  Share This News with Your Friends on Social Network  
  Comment on this Story  
 
 
 
Early Times Android App
STOCK UPDATE
 
 
 
 
 
 
 
   
Home About Us Top Stories Local News National News Sports News Opinion Editorial ET Cetra Advertise with Us ET E-paper
 
 
J&K RELATED WEBSITES
J&K Govt. Official website
Jammu Kashmir Tourism
JKTDC
Mata Vaishnodevi Shrine Board
Shri Amarnath Ji Shrine Board
Shri Shiv Khori Shrine Board
UTILITY
Train Enquiry
IRCTC
Matavaishnodevi
BSNL
Jammu Kashmir Bank
State Bank of India
PUBLIC INTEREST
Passport Department
Income Tax Department
JK CAMPA
JK GAD
IT Education
Web Site Design Services
EDUCATION
Jammu University
Jammu University Results
JKBOSE
Kashmir University
IGNOU Jammu Center
SMVDU