Breaking News :   Formulation of PRI, BDC Plan under district Capex Budget 2025-26 discussed | Amarnath Yatra symbol of unity, brotherhood: LG Sinha | Unfazed by terror threats, devotees flock to join Amarnath Yatra | 26,000 pilgrims pay obeisance in 2 days | Pilgrim from UP dies after falling unconscious | Proud to see our daughters breaking barriers, achieving success: LG Sinha | From separatism to mainstream: JeI leader vows to work within constitution | Man conspires with his wife to eliminate her lover | China used India-Pak conflict as 'live lab': Deputy Army Chief | CB presents chargesheet against notorious fraudsters | Govt Employees under UPS to get tax benefit akin to NPS: Finance Ministry | Come and see Kashmir: Shivraj Chouhan to people | Policeman injured in accidental firing | CUET-UG 2025 results announced | Day 3: Search for terrorists continues | New timings announced for courts | Brain Tracks Emotional Transitions Through Music | Disintegration of real life in the reel world, life getting tired in the race of show off | The Digital Revolution: 10 Years of Digital India and Beyond | Tribute To Valor Of Armed Forces | 367 vehicles involved in illegal mining seized by police | Mission YUVA not just an initiative but transformational opportunity: MD & CEO | SSP conducts PCPG meeting at Gandoh | Union Agriculture Secretary visits agricultural institutions, facilities in Kashmir | NFR recognizes track maintainer for timely action in detecting landslide in Lumding-Badarpur hill section | SSP holds crime/security review meeting | Sadhotra seeks strengthening of internet connectivity on Baltal, Pahalgam routes for smooth Amarnath Yatra | Kavinder meets Rajasthan CM in Jaipur; discusses J&K's transformation post Art 370 abrogation | Monsoon Ravages: 43 dead in Himachal Pradesh in 2 weeks, 37 missing | Resolution taken for purity, cleanliness of rivers | HC quashs FIR against then MS SMHS Hospital, Srinagar in corruption case | Naxalism confined to just 5-6 districts now: Rajnath Singh | NIA arrests key absconding accused in murder of Karnataka BJP leader | CJI Gavai assures 'complete transparency' in collegium system | 3-Day Induction Training for newly placed Headmasters of Jammu division concludes | Director Industries visits langar for Amaranth Yatris | Police arrests drug peddler | Despite challenges, mango growers deliver remarkable results using technology: CM Yogi | Drug peddlers nabbed by police, vehicle seized | Missing lady traced within 72 hours by Nowabad police | UP Govt ramps up export focus with third edition of Mega Trade Show | SMVDU NCC Cadets Excel at ATC in Udhampur | DIG Sarah Rizvi felicitates Sunny Mahajan | KSS celebrate Mata Sharika Jyanti with traditional religious fervor | Girdari Lal Dogra Memorial Degree College adopts villages under UBA | DBU celebrates Doctors' Day | GGM Science College unveils admission brochure for 2025-26 | GDC Ramnagar organises summer internship | CUJ approves Research guide ship for constituent colleges, dual degrees in syndicate | Back Issues  
 
news details
Div Com reviews progress of works on sewerage projects
UEED & NBCC directed to meet revised timelines, Div Com takes cognisance of perpetual delays
11/20/2021 10:27:41 PM

EArly Times REport

JAMMU, Nov 20: Divisional Commissioner Jammu, Dr Raghav Langer on Saturday chaired a meeting to review progress on various ongoing sewerage network projects and new plants proposed for the city, here.
The Divisional Commissioner directed the agencies to categorise their targets with respect to number of households, effluent volume and nallahs to be tapped. He sought detailed stage wise progress on each individual portion of the city’s sewerage network.
While examining the presentation by UEED, the Div Com stressed that certain areas like project reports should be improved. He directed the agency representative(s) to identify bottlenecks and eliminate the same.
The Divisional Commissioner insisted that the agencies design the ambitious project with the aim of arresting dump of undesirable city effluents into river Tawi at the earliest, and set separate targets on the projects for its right and left banks.
Dr Langer was informed that roughly 40% of the projected number of households and its population on the right bank of River Tawi, has been linked with sewerage lines and the projects for saturating the rest population are under preparation. A total of 293 kms of sewerage network has been laid on the right bank in parts of Jammu East/Jammu West areas (Zone I&II). A total of 55,000 households have been tapped till date under the ongoing projects.
There are total 13 Nallahs draining into the river on the right bank and the departmental officials apprised the Div Com that approx 500 cr shall be required to fully tap them and lay complete network to fully cover all households on the right bank of City.
NBCC was reprimanded for being unable to complete the balance 1850 household connections under JNNURM/Languishing sector scheme and deadline of January 15, 2022 was set for the same.
67 MLD capacity of Sewerage treatment plants (STPs) stands created in Bhagwati Nagar. The Div Com directed the respective officers to submit reports of daily inflow-outflow and power consumption logs of sewage treatment plants currently running in the city in addition to their BOD-COD test levels summaries.
Other aspects of the project, which include restoration, resurfacing of roads and electrification of the digging affected areas were also sought by the Div Com. He also directed complete resurfacing of the Circular Road within fifteen days.
Meanwhile, the Div Com was apprised that works on sewerage scheme costing 51 cr is under progress through UEED on the left bank of Tawi River in which 05 Nallahs are to be tapped.
Work on 4 MLD STP is compete however, the works on sewerage network is progressing at a very slow pace; upon which SE UEED was directed by the Div Com to invoke penalty clause on the contractor and get works executed at the risk and cost of the defaulting contractor.
Those present in the meeting included Commissioner JMC, Avny Lavasa; Director ERA Jammu, Ravinder Mansotra; Executive Director, NBCC, MK Chawla; Chief Engineer PHE Jammu, Manish Kumar Bhat; Chief Engineer R&B, Manzoor Hussain, Chief Engineer, PDD (JPDCL) Ashwani Sachdewa, SE UEED, Rakesh Kumar among other senior officers.
  Share This News with Your Friends on Social Network  
  Comment on this Story  
 
 
 
Early Times Android App
STOCK UPDATE
  
BSE Sensex
NSE Nifty
 
CRICKET UPDATE
 
 
 
 
 
 
 
 
   
Home About Us Top Stories Local News National News Sports News Opinion Editorial ET Cetra Advertise with Us ET E-paper
 
 
J&K RELATED WEBSITES
J&K Govt. Official website
Jammu Kashmir Tourism
JKTDC
Mata Vaishnodevi Shrine Board
Shri Amarnath Ji Shrine Board
Shri Shiv Khori Shrine Board
UTILITY
Train Enquiry
IRCTC
Matavaishnodevi
BSNL
Jammu Kashmir Bank
State Bank of India
PUBLIC INTEREST
Passport Department
Income Tax Department
JK CAMPA
JK GAD
IT Education
Web Site Design Services
EDUCATION
Jammu University
Jammu University Results
JKBOSE
Kashmir University
IGNOU Jammu Center
SMVDU