Breaking News :   Poonch bears maximum brunt of Pak shelling | CM Omar visits shelling hit Uri | Airspace to Cyberspace: How India fought swarms of drones, wave of misinformation during conflict | IAF jammed Pak’s Chinese-supplied air defence systems | CDS, tri-service Chiefs brief Prez Murmu | CDS, Army, Navy, Air Chiefs, shed light on successful conduct of operation | CM slams Sardesai: ‘Which Indian won’t support PM’s anti-terror doctrine?’ – Netizens applaud Omar Abdullah | 3 killed Lashkar terrorists behind recent terror activities: Army | Pak hands over BSF Jawan to India after 21 days | Article 370, Rape, Bulldozer Justice: India’s new CJI Justice has delivered many landmark verdicts | Tanker crushes court official to death | Schools reopen in border Distts | Govt amends Prison Manual | Bridging The Gap | Shelling by Pakistan on civilians is highly condemnable : Sadhotra | Div Com, Kashmir reviews Mata Kheer Bhawani Mela arrangements through video conferencing | Northern Army Commander briefs CM Omar on security situation | Helicopter service resumes after 7 days | Kathua police attach property worth Rs 19 lakh of notorious drug peddler | Jammu Municipal Corporation takes action against unregistered dairies | Inqlabi demands relief for shelling victims, FIR against MP minister for derogatory remarks | Rana advocates mandatory bunkers in border areas to protect lives | NFR leveraging modern technology for ensuring safety of Lumding - Badarpur Hill Section | CM Yogi orders maximum vigilance in zoos to avert bird flu threat | Aerial right for transmission lines remains with the State: HC | Gold declines Rs 650 to Rs 96,850/10 Gm amid weak global cues | Notorious drug peddler held in Udhampur, heroin seized | Mission Director Sandeep Kumar reviews progress of key projects under HADP | BLSKS presented 495th musical play “Ekta - Ekta Ka Diya” | Operation Sindoor: A wake-up call for Pakistan: Rohiin Chandan | Two held in Bishnah assault case, sharp weapons recovered by Jammu police | IGNOU to open online portal for re-registration for July 2025 session | Govt appoints 122 Junior Assistants to address clerical staff shortage in RDD | JSSJ Soars High with Stellar CBSE Class 10 & 12 Board Results | SMVDU faculty present research paper in international conference | Dogra Degree College launches "Rashtra Pratham - Nation First" campaign | Back Issues  
 
news details
Zojila tunnel project that will connect Leh all year near halfway mark
3/28/2022 11:37:29 PM
Early Times Report
SONAMARG, Mar 28: The work on the strategic Zojila Tunnel, which will provide all-weather connectivity between Ladakh region and the rest of the country, is nearing the halfway mark as the excavation for seven-km tunnel length has been completed, officials said here on Monday.
"The works have been carried out on a war footing. We have completed 40-45 per cent of road works and tunnel works so far. The tunnel excavation works of 7,002 metres have been completed as of now," said an official of Mega Engineering and Industries Limited (MEIL), the executing agency.
The officials said the work on the prestigious Zojila project on the Srinagar-Leh highway is about to reach the halfway mark.
Once completed, the Zojila project which consists of tunnels, roads, shafts, and bridges will have Asia's longest bi-directional tunnel.
The project is a unique infrastructure project which will provide year-long connectivity between Srinagar and Ladakh. "It also decreases the travel time between the two regions," the official said.
The officials said Zojila Project is being executed with engineering expertise and advanced New Austrian Tunnelling Method (NATM)
"MEIL has carried the works in sub-zero temperatures, especially at minus 40 degrees, in high altitude and hilly and hard rocky terrain. It is hard to execute all drilling and civil works in that hilly terrains which contain hard rock and heavy seepage," the official added.
MEIL's project in-charge Harpal Singh said, "We are doing the project with dedication, determination and hard work." The Zojila project consists of a total of 18-km-long tunnels and 17-km-long road, three vertical shafts, four bridges, and other associated structures.
MEIL has deployed a total of 1,268 advanced and high-end technology machinery and equipment for the execution of the project with a 2000-strong workforce.
  Share This News with Your Friends on Social Network  
  Comment on this Story  
 
 
 
Early Times Android App
STOCK UPDATE
  
BSE Sensex
NSE Nifty
 
CRICKET UPDATE
 
 
 
 
 
 
 
 
   
Home About Us Top Stories Local News National News Sports News Opinion Editorial ET Cetra Advertise with Us ET E-paper
 
 
J&K RELATED WEBSITES
J&K Govt. Official website
Jammu Kashmir Tourism
JKTDC
Mata Vaishnodevi Shrine Board
Shri Amarnath Ji Shrine Board
Shri Shiv Khori Shrine Board
UTILITY
Train Enquiry
IRCTC
Matavaishnodevi
BSNL
Jammu Kashmir Bank
State Bank of India
PUBLIC INTEREST
Passport Department
Income Tax Department
JK CAMPA
JK GAD
IT Education
Web Site Design Services
EDUCATION
Jammu University
Jammu University Results
JKBOSE
Kashmir University
IGNOU Jammu Center
SMVDU