Breaking News :   Our sole aim is to foster peace, achieve goal of Viksit Bharat: LG Sinha | Bridge funding gap for MSMEs and startups: LG | Teachers’ terror links raise alarm in Education Department | Cong awaits high command’s nod to join NC in bypolls | DM Jammu bans misuse of courier services | Govt primary school reopens after 25 years in Rajouri | MeT predicts rain, snow | Man found dead | Crackdown against narco-terror handlers continues | PNB, Circle Office, Jammu has organised Walkathon | Dipr bids farewell to additional director Harjit Grewal & Deputy director Hardeep Singh | Pinegrove excels at Zonal Level National Cricket Championship | Chandigarh University celebrates Punjab Day with 2-day cultural extravaganza ‘Virasat-e-Punjab’ | BSF Rajouri organizes 5 KM Pre-Marathon Run Ahead of Jammu Marathon | Army Public School conducts faculty development programme | Partap World School Brings 50+ Prestigious Institutions Under One Roof | “Win the booth, win the election” mantra of electoral success: Balbir | Deaf Cricket Team J&K calls on YNC provincial president | Harjot Bains flays centre’s move to dissolve Panjab University senate | Dr (Professor) Netar Parkash Sharma: A Beacon of Perseverance, Simplicity and Strength of Character | Women of Punjab refrain from having children! | Studying doesn’t have to feel dull or tiring with a few smart brain tricks | Manifesto: A Powerful Weapon of Democracy or an Electoral Deception? | GDC R S Pura observes Vigilance Awareness Week | One-day Webinar on “Effective Optimization Algorithms in Permanent Magnet Machines Design” held at SMVDU | National Unity Day celebrates at National College of Education | KIIT, FIDE, AICE join hands to Promote Chess in India | Circuit Sitting of CAT Jammu Bench held at Leh | 287 Army Ex-Servicemen inducted as Security Personnel | GGM Science College observes National Unity Day | Annual Technical Festival inaugurate at Sardar Beant Singh State University, Gurdaspur | Cyber Police Station Udhampur recovers Rs 3.71 Lakh | MCM empowers students through sessions on financial literacy, makeup artistry | BLSKS condludes special campaign on Nasha Mukat Bharat | Director Horticulture conducts field visit to Satwari, R.S. Pura | Foundation Day of various states/UTs celebrates at LG Secretariat | Annual Congregation | Director Health Services Jammu chairs District-Level review meeting | SCERT Divisional Office Jammu concludes 5 day workshop | Chronic Troublemaker bokked under PSA | One notorious bovine smuggler booked under PSA | 78th Annual Nirankari Sant Samagam begins, Satguru calls for Inner-Reflection | Back Issues  
 
news details
Chairman, CEO, Railway Board inspects ongoing works on Katra- Banihal section of USBRL Project
9/11/2022 10:41:06 PM
Early Times Report

Jammu, Sept 11: Vinay Kumar Tripathi, Chairman and CEO, Railway Board inspected the ongoing works on Katra- Banihal(111 Km) section of USBRL Project in Jammu & Kashmir from 09/09/2022 to 10/09/2022.
Inspection started from tunnel T-1( 3159m) .
Tunnel excavation of 1860 m has been completed from portal P1 end and 1039 m completed from P2 end. Now, the balance excavation is only 260m. Due to Main boundary thrust location, the progress is very slow. Tunnel excavation requires lot of pre- support measures and also post excavation support systems. Executing agency was advised to complete balance excavation of 260 meters expeditiously by augmenting resources. Northern Railway /Konkan Railway Corporation Limited were directed to closely monitor the progress.
After Tunnel T-1, inspection continued with run through in already completed tunnel T-2 having length of 5090m of Main tunnel and parallel escape tunnel of length 5072m. BLT work in this tunnel is in progress and nearly 2.5 km of HBL (Hydraulically bounded layer) has already been laid.
After T-2, Anji Bridge (Katra end), which is Indian Railway’s first Cable stayed bridge having total length of 725m was inspected. Anji Bridge has a single Main Pylon of height 193m from foundation top and 331 m above the river bed. At Katra end of this bridge, construction of MA1 abutment substructure was in progress and 9m has been cast out of 22.3m height. Project executives informed that only balance work on Katra end is 38m span of MA1 and CA2, which is under fabrication and will be launched by Dec.’2022.
Thereafter, Reasi end of Anji bridge was inspected. Sub-structure has been completed and super structure launching/erection is under way. 249m out of 473m deck has been erected which includes launching of 6 segments using Derrick (segment launcher). Project executives informed that launching of 3 segment (i.e 30m ) in a month is being achieved and all efforts are being made to expedite the same. CRB appreciated the good work being done and advised the project authorities to further improve the progress so as to complete the work expeditiously.
After Anji Bridge, other major bridge no 39 was inspected, which is a continues composite girder of 490m length, which is in final stage of completion.
The tallest Pier P5 of this bridge is 105m from foundation level and Reasi yard is extending over this bridge and will holds two lines and also two platforms.
Deck slab for Main girder has been completed and platform girder is in progress. It was informed by project executives that balance works shall be completed by Nov’22.
Reasi station building work was also inspected. Ground floor slab has been cast and shuttering work for column of first floor was in progress. It was informed that GRP & RPF Barracks are being constructed below the circulating area as basement and work of same is in full swing.
Thereafter, from Reasi inspection continued by travelling 20 Km to Bakkal end and reached Bridge-43, which is 777m long and is 2nd longest bridge in this project. Bridge has curvature of 1.4⁰ and launching of girder has been done on curve with precision by end launching from both ends & is completed. Castin of deck slab is in progress.
After Bridge-39 inspection continued to Chenab Bridge, which is highest Railway Bridge on the Globe. Golden joint of Deck for this bridge was successfully completed on 13 Aug.’2022.
All tunnel, bridge & track linking works from Chenab bridge onwards till Tunnel T-14 were inspected. CRB expressed satisfaction regarding pace and progress of works and directed Project Authorities to further push up the progress specially T-14 and BLT works. He further emphasised that E&M and S&T works should also be taken up in parallel so as to ensure timely completion of the project.
  Share This News with Your Friends on Social Network  
  Comment on this Story  
 
 
 
Early Times Android App
STOCK UPDATE
 
 
 
 
 
 
 
   
Home About Us Top Stories Local News National News Sports News Opinion Editorial ET Cetra Advertise with Us ET E-paper
 
 
J&K RELATED WEBSITES
J&K Govt. Official website
Jammu Kashmir Tourism
JKTDC
Mata Vaishnodevi Shrine Board
Shri Amarnath Ji Shrine Board
Shri Shiv Khori Shrine Board
UTILITY
Train Enquiry
IRCTC
Matavaishnodevi
BSNL
Jammu Kashmir Bank
State Bank of India
PUBLIC INTEREST
Passport Department
Income Tax Department
JK CAMPA
JK GAD
IT Education
Web Site Design Services
EDUCATION
Jammu University
Jammu University Results
JKBOSE
Kashmir University
IGNOU Jammu Center
SMVDU