Breaking News :   CM Omar meets HM Shah, discusses statehood | Somnath Temple beacon of nation: LG Sinha | Narco empire razed in minutes: Properties of 3 siblings bulldozed in Hiranagar | Govt to auction 12 limestone blocks in J&K | Country has adequate fuel stocks, no need to panic: Rajnath Singh | PM repeats call for saving fuel, cutting gold purchase | Court refuses bail in LeT-linked case, cites prima facie truth | All-party Parliamentary delegation visits clock tower at Lal chowk | Family escapes unhurt after BSNL tower falls on house | Police register FIRs against Srinagar hotel, homestay owners | X restricts Iltija Mufti’s account | Vb-G Ram G act to come into force from July 1 | JKBOSE extends re-evaluation dates | Bengal Reclaims Itself | The Alarming Surge of Crime and the Challenge of a Safe Society | Reduce Fuel Consumption | JCCI hails not to purchase gold | Prof (Dr) M Srinivas delivers inspiring session at AIIMS Jammu | Drugs are as dangerous as guns for society: Dr Darakhshan | Morning Walkers Association felicitates RK Jain | Lieutenant Governor Inaugurates National Youth Festival- Aarohan 2026 in Srinagar | Inter-district drug module busted by Udhampur police | NIA Court sends five LeT module accused to 25-day judicial custody | Historic Commencement of Viksit Bharat - G RAM G Act across rural India from July 1st 2026 | Somnath Amrut Mahotsav celebrated with religious fervour across Ramban | NIA Court rejects bail to three accused in Kulgam Sarpanch killing case | DPS Jammu Teachers participate in AI & Computational Thinking Workshop at IIT Jammu | CLUJ promotes indigenous sports through Kabaddi Mats launch | Rural students outshine urban peers in Class 10th results; Jaito's Harleen tops Punjab with 99.38%: Harjot Bains | Guru Nanak Dev University Creates History in Global Innovation Rankings | Chief Minister attends State-Level "Somnath Swabhiman Parv" at Arunai in Pehowa | GDC Ganderbal conducts PRC-cum- Special Lecture under FYUGP (NEP 2020) | Kathua campus, University of Jammu launches UG admissions for session 2026-27 | Back Issues  
 
news details
NCR Transport Corporation starts power supply to Shatabdi Nagar for Namo Bharat trains
2/12/2025 11:05:29 PM
Agencies

New Delhi, Feb 12: The National Capital Region Transport Corporation (NCRTC) has started power supply to the Shatabdi Nagar receiving sub-station in Meerut for its corridor, ensuring uninterrupted electricity for Namo Bharat trains and stations as well as Meerut Metro, a statement said on Wednesday.
The NCRTC is setting up five receiving sub-stations (RSSs) along the Delhi-Ghaziabad-Meerut Namo Bharat corridor; one each at Sarai Kale Khan, Ghaziabad and Muradnagar; and two are located in Meerut at Shatabdi Nagar and Modipuram, it said.
Shatabdi Nagar is the first operational RSS in the city, while the second is under construction at Modipuram, the statement said.
From RSS, 25 kV electric power is supplied to the overhead equipment (OHE) for train operations, while 33 kV power is distributed to stations through the 33 kV ring main system and auxiliary sub-stations (ASS), it said.
The RSS receives power from distribution companies and transmits it via the 33 kV ring main system to the ASS at each station, ensuring efficient operation of station appliances. The power supply system is designed for high reliability and redundancy. In case of any disruption at one RSS, the adjacent RSS can seamlessly take over the load, ensuring an uninterrupted power supply, it stated.
The Shatabdi Nagar RSS will supply power to several key stations in Meerut, including Shatabdi Nagar, Partapur, Rithani, Brahmpuri, Meerut Central, Bhaisali, Begumpul and MES Colony stations. Currently, the Ghaziabad and Muradnagar RSS units are providing power to the 55-km operational section including 11 stations between New Ashok Nagar and Meerut South.
The Shatabdi Nagar RSS receives power from Uttar Pradesh Power Transmission Corporation Limited (UPPTCL) grid sub-station through 220 kV Extra High Tension (EHT) cables, which further distributes 25 kV power for train operations and 33 kV power for auxiliary and other electrical loads of Namo Bharat stations, it said.
Currently, the trial run of the Meerut Metro is underway between Meerut South and Meerut Central stations. The viaduct construction on the Meerut section has been completed, while track-laying activities along with the installation of Overhead Equipment (OHE) and signalling systems are progressing in the remaining section.
  Share This News with Your Friends on Social Network  
  Comment on this Story  
 
 
 
Early Times Android App
STOCK UPDATE
 
 
 
 
 
 
 
   
Home About Us Top Stories Local News National News Sports News Opinion Editorial ET Cetra Advertise with Us ET E-paper
 
 
J&K RELATED WEBSITES
J&K Govt. Official website
Jammu Kashmir Tourism
JKTDC
Mata Vaishnodevi Shrine Board
Shri Amarnath Ji Shrine Board
Shri Shiv Khori Shrine Board
UTILITY
Train Enquiry
IRCTC
Matavaishnodevi
BSNL
Jammu Kashmir Bank
State Bank of India
PUBLIC INTEREST
Passport Department
Income Tax Department
JK CAMPA
JK GAD
IT Education
Web Site Design Services
EDUCATION
Jammu University
Jammu University Results
JKBOSE
Kashmir University
IGNOU Jammu Center
SMVDU