Breaking News :   Tribal Gujjar Bakkerwal Welfare Foundation knocks on NCST's door, seeks action under SC/ST Act | CM Omar reviews roadmap to strengthen senior secondary education in J&K | CM calls for mission-mode action to address Srinagar's stray dog menace | Over 6 Kg Heroin recovered, 5 held in Amritsar: Punjab Police | Court frames charges against 2 in Ramban-Mumbai Charas smuggling case | 'File ITR before Aug 31 deadline' | EOW Kashmir arrests Bangalore-hiding accused in Rs 2 cr investment fraud case | 3 fugitives deported from Malaysia | 3 families evacuated after land subsidence, cracks in houses in Ramban | Landslide threat looms over Dhingidhar village, residents seek immediate safety measures | Justice reaches frontier as NALSA Jagriti programme held | NFR construction GM conducts inspection of key sections of Jiribam - Imphal New Line Project | District police Ramban apprehends absconder wanted in 23 year-old case | Two children drown in Jammu Khala rivulet in Paonta area | Div Com reviews development proposals for heritage sites in Budgam, Pulwama | J&K Fencing Association Felicitated Vishal Thapar for selection in upcoming Asian Games | Suvaid, Abbas, Aleena among gold winners; Zaheeb, Essa, Aiman figure among silver medallists | GDC Kunjwani Hosts Orientation Programme | Declines to quash transfer of PM package employee; directs Govt to decide representation within 3 weeks | Vice-President launches India's first non-GMO high-expansion popcorn maize hybrid seed | Property not belonging to accused can't be attached under UAPA: Court | PDP protests against 6.83% electricity tariff hike | DIG IR Range visits newly established headquarters of 1st JKAP Women Battalion | Syed Mohammad Altaf Bukhari calls for adequate arrangements for smooth observance of Eid Milad-un-Nabi (SAW) | AIIMS Jammu welcomes Prof (Dr) Sanjeev Sinha as new Executive Director & CEO; Prof (Dr) DN Sharma's tenure concludes | CBC organizes awareness programme on VB-G RAM G Act in Leh | People want affordable power, not broken promises and higher bills: Balbir | Uttar Pradesh's daughters becoming self-reliant, creating a new identity by joining 'Mukhyamantri Yuva Udyami Yojana' | MY Bharat to organise Khelo India Samvaad across Jammu & Kashmir on August 27 | Natrang's 'Colours of Jammu Kashmir' outshines at IIM Jammu | Plantation drive held at HSS Chowki Choura | Read your manifesto twice: Tony slams Omar Govt over power tariff hike | Central Bank of India Chandigarh Region Organises Retail Credit Outreach Camp | Rekha Mahajan extends best wishes to newly appointed Mahila Morcha National President | Rahul Gandhi works to insult Uttar Pradesh and the Country: CM Yogi | JK Rehbar-e-Taleem Teachers Forum holds general meeting in Srinagar | DPS Jammu student Veer Vikram Singh thakur makes literary debut with dark fantasy novel The Sinner's Veda | Back Issues  
 
news details
USBRL Project fully operational after 28 years
6/7/2025 10:37:02 PM
Early Times Report

Katra, June 7: The 272-km Udhampur-Srinagar-Baramulla Rail Link Project, which was started in 1997, took almost 28 years to become operational. Its first 55 km long section between Jammu and Udhampur was completed in April 2005.
According to Northern Railways, the whole project was completed and operationalised in multiple phases, with the last one being inaugurated by Prime Minister Narendra Modi on Friday.
After opening the Jammu-Udhampur section, the then UPA government focused on sections in Kashmir and operationalised the 68 km long Anantnag-Mazhom rail link in October 2008.
“Then came a 32 km long Mazhom – Baramulla rail link on which train services started in February 2009. So by 2009, locals availed train journey from the last point of the USBRL project, ie, Baramulla to Anantnag,” a Northern Railway official said.
He added, “Since work was going on simultaneously on other sections, Railways was able to extend the train service from Anantnag to Quazigund towards Jammu side by October end in 2009.”
The Railways achieved another significant milestone when it further extended the train services from Quazigund to Banihal in June 2013, which involved the construction of an 11.215 km long Pir Panjal tunnel.
“Almost a year later, in July 2014, the Udhampur-Katra line from the Jammu side was made operational,” the official said.
According to a railway source, “When the Modi government came to power, the rail services were operational from Baramulla to Banihal in Kashmir side and Katra to Jammu on the other side. The missing link – Banihal to Katra – needed to become operational for bringing Kashmir on the rail network of the country.”
“The Modi government completed the Banihal to Katra connectivity in two phases. First, Banihal to Sangaldan in Feb 2024 and then Sangaldan to Katra on June 6, 2025, was made operational, completing the missing link,” he added The Northern Railway said that the Banihal to Katra section has the iconic Chenab and Anji Bridge and some of the toughest and longest tunnels.
“For instance, the 12.75 km long country’s longest operational rail tunnel is between Banihal and Sangaldan. Many other challenging infrastructure development works were materialised in the past 11 years,” another official said.
  Share This News with Your Friends on Social Network  
  Comment on this Story  
 
 
 
Early Times Android App
STOCK UPDATE
 
 
 
 
 
 
 
   
Home About Us Top Stories Local News National News Sports News Opinion Editorial ET Cetra Advertise with Us ET E-paper
 
 
J&K RELATED WEBSITES
J&K Govt. Official website
Jammu Kashmir Tourism
JKTDC
Mata Vaishnodevi Shrine Board
Shri Amarnath Ji Shrine Board
Shri Shiv Khori Shrine Board
UTILITY
Train Enquiry
IRCTC
Matavaishnodevi
BSNL
Jammu Kashmir Bank
State Bank of India
PUBLIC INTEREST
Passport Department
Income Tax Department
JK CAMPA
JK GAD
IT Education
Web Site Design Services
EDUCATION
Jammu University
Jammu University Results
JKBOSE
Kashmir University
IGNOU Jammu Center
SMVDU