Breaking News :   Counting Wealth Beyond Coins | Women’s Reservation: The Foundation of a New India and the Pinnacle of Possibilities | Revolutionizing Connectivity | On Baisakhi, LG Sinha dedicates phase-I of Tawi Riverfront Project to public | Change needs spirit for selfless service: LG | CM Omar thanks PM Modi, Gadkari for approval of tunnels | After devastating Aug 2025 cloud burst, Machail Mata Yatra commences with opening of temple’s door | Budgam Police books man for fake WhatsApp account in SSP’s name | Zojila tunnel nears breakthrough | PM Modi pays tribute to Babasaheb Ambedkar, lauds Article 370 abrogation, UCC | Ambedkar staunchly opposed Article 370: Amit Shah | Targeting drug cartels to dismantle supply chains | Couple killed in Jammu accident | Nitish Kumar resigns as Bihar CM | Nine-month road closure near Nansu Shiv Mandir causes hardship ahead of Baisakhi Mela | Div Com, IGP Jammu pay obeisance at Revered Shrine | Satish Sharma leads Baisakhi Milan celebrations at Akhnoor; pushes for preserving cultural legacy | FICCI FLO JKL hosts Change of Guard Ceremony at Four A Resorts | JAKASICON concluded at AIIMS Jammu: A three-day national surgical conference | Reasi police cracks down on drug peddling; heroin recovered at Katra-Reasi road | Satish Sharma, RL Gupta reaffirm statehood demand, calls it constitutional imperative on Ambedkar Jayanti | Seerbagh-Sempora bridge nearing completion, to be opened soon: Deputy Chief Minister | Fire Service Day observed in Srinagar, Fire Safety Week launched across J&K | Randhawa delivers on promise, launches lane & drain works in Ward No. 5 | Police conduct Anti-Drug Awareness Programmes under Nasha Mukt J&K Abhiyaan | Central University of Jammu organized academic trip to Bhaderwah | JKNC leaders pay rich tributes to BR Ambedkar on 135th Birth Anniversary | Seminar held in Chandigarh to mark 135th Birth Anniversary of BR Ambedkar | NILM Jammu celebrates Birth Anniversary of Dr BR Ambedkar at Ganga Nagar | BJP Government Has Always Prioritized Women's Empowerment: Pardeep Sharma | Inauguration of the Delhi-Dehradun Economic Corridor | Cabinet secretary addresses army commanders’ conference | Rajouri police arrests drug peddler; 7 grams of heroin like narcotic substance recovered in Thanamandi | 119th Birth Anniversary of Shaivacharya Swami Lakshmanjoo celebrated | Historic Baisakhi Mela at Nainsoo inaugurated | 'Solar Didi' campaign gains momentum in UP, women leading the clean energy revolution | Blood Donation Camp Organized at GMC Jammu on Baisakhi by SOLACE NGO | Inter-District Drug Peddler arrested with Heroin at Majalta by Udhampur Police | J&K F&ES launches Fire Service Week; reports 25% drop in fire Incidents | Cross-border illegal arms smuggling module busted in Punjab, 3 held | Fuel price freeze: Rs 18/litre loss on petrol, Rs 35 on diesel | Baisakhi celebrated across Kashmir, Sikh devotees offer prayers at Gurdwaras | Back Issues  
 
news details
NHAI sets Mar 2027 deadline for completion of Delhi-Katra expressway
2/25/2026 10:46:25 PM
Early Times Report

Jammu, Feb 25: The Delhi-Amritsar-Katra Expressway, the fifth major expressway being developed in the country, is set for completion by March 2027, a senior official of the National Highways Authority of India said on Wednesday.
The construction of the National Expressway 5 (NE5), which began in April 2021, had significantly slowed last year due to Operation Sindoor as well as heavy rains and floods across northern states. Once completed, the project is expected to considerably enhance regional connectivity, promote religious tourism and facilitate faster mobility for the armed forces, the official said.
The expressway will reduce the distance from Delhi to Katra from 727 to 588 kilometres, cutting travel time from 14 to about six hours, he said.
Speaking to news agency, Rajiv Kumar, project director, NHAI (Project Implementation Unit Jammu), said, “Construction of the expressway was hit badly last year in the aftermath of Operation Sindoor and later by heavy rains and flooding. But the work has gathered pace again. The deadline for its completion has been fixed for March next year.” Kumar said the National Expressway 5 is the fifth major expressway being developed in the country and has been conceptualised as a religious corridor, supplementing existing air and rail connectivity.
“It will connect two of the most prominent pilgrimage destinations — Sri Harmandir Sahib, also known as the Golden Temple or Darbar Sahib in Amritsar (Punjab) and Mata Vaishno Devi shrine in Katra (Reasi district, Jammu and Kashmir),” he said.
A large number of devotees visit Mata Vaishno Devi annually, the official said, explaining that they currently rely on rail and air travel. The expressway would provide a third option, enabling Delhi-Katra travel in approximately six hours.
“We had only five to six months of effective work last year. One of the biggest challenges was retaining manpower during tense security situations. Many workers left due to safety concerns and had to be persuaded to return. Additionally, heavy rains washed away two bridges, severely disrupting supply lines,” Kumar said.
Strategically, the NHAI official said, the expressway is significant for Jammu and Kashmir due to its proximity to the International Border.
“Running parallel to sensitive border areas, the corridor is expected to facilitate faster deployment and improved mobility for defence forces,” he said.
Kumar said advanced segmental bridge construction technology — a method adopted during the construction of Delhi Metro and Dwarka Expressway — is being used in the current project.
Packages 15 and 16 along the Jammu-Samba stretch included an elevated corridor of nearly 21.5 kilometres, which posed a challenge due to heavy traffic movement. However, the target was achieved using segmental bridge construction technology without disrupting traffic, the NHAI official said.
Keeping the upcoming annual Amarnath Yatra in mind, the official said, a target has been set to complete nearly 30 kilometres of the Jammu-Kathua stretch before the start of the pilgrimage later this year.
  Share This News with Your Friends on Social Network  
  Comment on this Story  
 
 
 
Early Times Android App
STOCK UPDATE
 
 
 
 
 
 
 
   
Home About Us Top Stories Local News National News Sports News Opinion Editorial ET Cetra Advertise with Us ET E-paper
 
 
J&K RELATED WEBSITES
J&K Govt. Official website
Jammu Kashmir Tourism
JKTDC
Mata Vaishnodevi Shrine Board
Shri Amarnath Ji Shrine Board
Shri Shiv Khori Shrine Board
UTILITY
Train Enquiry
IRCTC
Matavaishnodevi
BSNL
Jammu Kashmir Bank
State Bank of India
PUBLIC INTEREST
Passport Department
Income Tax Department
JK CAMPA
JK GAD
IT Education
Web Site Design Services
EDUCATION
Jammu University
Jammu University Results
JKBOSE
Kashmir University
IGNOU Jammu Center
SMVDU