x

Like our Facebook Page

   
Early Times Newspaper Jammu, Leading Newspaper Jammu
 
Breaking News :   Congress faces embarrassment in Kargil | Omar, Sajad exchange barbs after police ask them to reschedule political activities | After losing 5 family members last year, Banu Begum awaits promised compensation | Lok Sabha poll contest between vote for development and ‘vote for jihad’: Amit Shah | Effective defence-industry ecosystem shaping up in country: Gen Pande | Kedarnath portals to open today, devotees head for shrine | Poonch attack: Search operation enters sixth day | NIA attaches 4 more properties | Court extends remand of accused | First Hajj flight takes off | MeT predicts rains | Army concludes Kulgam operation | Holiday on May 25 | Judicial Academy organises pre-appointment training for newly selected Civil Judges | Kavinder accused Congress leadership | Healthy Lifestyle | Omar Abdullah writes to ECI | Director Agriculture Discusses Collaborative Initiatives with NABARD Officials | Police challaned 94 vehicles under operation third eye | Annual Jagran organized at Maa Vaishno Devi Mandir Bhagwati Nagar | J&K Pay Verification process simplified for pensioners | Police foils bovine smuggling attempt, rescues 5 bovines | DC Kulgam chairs monthly NCORD meeting | Mega awareness rally organised at Koteranka by SVEEP team | J&K industrial sector in worst shape due to anti industrial policy of BJP : Rattan Lal Gupta | SSP Jammu recommends strong action against vehicles continuously indulging in bovine smuggling | FICCI FLO JKL Organizes Awareness Session on ‘Cyber Menace’ at MIET | Dr. Darakhshan Andrabi Visits Sufi Shrine, Emphasizes Peace and Development in J&K | Div Com, IGP Kashmir review departure arrangements for first batch of Hajj pilgrims at Srinagar airport | Narco smmugling module busted in Baramulla, drugs worth Rs 50 crore, cash recovered: Police | Only I spoke against revocation of Article 370 in Parliament: Azad | Rakesh Jewellers announces exciting offers on Akshaya Tritiya | House Searches continue in Greater Kailash Murder Case | Solemnization of valid second marriage is a must for bigamy conviction | Back Issues  
 
news details
Majority of proposed power projects stalled in JK
24x7 supply by 2019 may remain a slogan of coalition regime
6/9/2018 11:53:47 PM
Ishtiyaq Ahmad
Early Times Report
Srinagar, June 9: With majority of the proposed hydropower projects having been stalled even as the electricity demand is likely to reach 4,217 MW by 2021-22, the ambitious plan of the PDP-BJP government to provide uninterrupted power supply to the people by 2019 may remain a slogan.
Sources told Early Times that though the Jammu and Kashmir has significant hydropower potential for development due to its predominantly mountainous terrain, access to electricity has been hampered over the years due to slow pace of works on different power projects.
The process to make the state supply power 24x7 was set in motion, when the government in June 2016 signed 24x7 "Power For All" (PFA) document aimed at providing round the clock power supply to people of the state.
The documents were signed in presence of Union Power Minister during two-day state power ministers' conference held on June 16-17 at Goa.
Along with Jammu and Kashmir, the PFA documents were signed by Mizoram and Arunachal Pradesh and three Union Territories including Delhi, Daman & Diu and Dadra & Nagar Haveli. "The plan aims to provide each household access to electricity, 24x7 reliable Power supply and adequate supply to agricultural consumers as per state policy by 2019".
However sources told Early Times that though the other states are moving in the right direction in this regard, it seems that Jammu and Kashmir is heading for a major crisis in the coming years if projects taken up for increasing generation and infrastructure development continue to get delayed.
Official sources said a survey conducted by the Union Ministry of Power had projected that J&K would have a peak demand of 4217 MW in 2021-22, with an energy requirement of 21,884million units.
"Hydropower projects take decades to complete and keeping in view the unexpected challenges, the Indus Water Treaty and political issues involved, the state is not expected to complete the existing projects on time. Several hydropower projects are already behind schedule," sources maintained.
The projects like the 850-MW Rattle project on the Chenab in Kishtwar district was abandoned by the executing agency following a dispute with locals. Legal hurdles and dispute with locals had led to delay in starting the work on the Parnai Hydel Project in Poonch, 1,200 MW Sawalkote, 600 MW Kiru, 240 MW Kirthal, 50 MW Lower Kainal, 520 MW Kawar and 280 MW Ujh.
However, one of the top officials of the Power department said that the government is reviving all the stalled projects.
"We had got the techno-economic clearance for Kirthal-II from central electricity authority only last year and the same is expected for the Sawlakote soon," said the official on condition of anonymity.
The PDC owns 22 hydropower projects with cumulative capacity of around 1210 MW. But the state's energy requirement has gone beyond 2700 MW.
J&K is one among the states having vast hydro power potential from where electricity is also being supplied to several parts of the country. But the state on its own is suffering for want of power as it has to purchase electricity worth hundreds of crores rupees annually from the centre power corporations.
Sources said that Jammu and Kashmir would only be able to provide 24-hour power supply in the next four years if it doubles the power purchase to meet the demand of consumers.
It is to mention here that Union Minister of Power (independent Charge) Raj Kumar Singh had admitted that a population of 4.5 lakh in Jammu Kashmir was still devoid of electricity.
Speaking at the inaugural function of the 330 MW Kishen Ganga hydroelectric project and Srinagar semi ring road project, Singh had said 134 un-electrified villages in Jammu Kashmir had been electrified during the past two-and-a-half-years of Prime Minister Narendra Modi-led government.
Singh had also claimed that the Government of India (GoI) was not only planning to electrify the un-electrified villages across Jammu Kashmir but also ensure 24 hour power supply to the electrified areas.
"New Delhi was doing everything possible to ensure 24-hour power supply in Jammu Kashmir and the construction of the 1000 MW PakalDul project would go a long way in realising this dream," Singh had said.
  Share This News with Your Friends on Social Network  
  Comment on this Story  
 
 
 
Early Times Android App
STOCK UPDATE
  
BSE Sensex
NSE Nifty
 
CRICKET UPDATE
 
 
 
 
 
 
 
 
   
Home About Us Top Stories Local News National News Sports News Opinion Editorial ET Cetra Advertise with Us ET E-paper
 
 
J&K RELATED WEBSITES
J&K Govt. Official website
Jammu Kashmir Tourism
JKTDC
Mata Vaishnodevi Shrine Board
Shri Amarnath Ji Shrine Board
Shri Shiv Khori Shrine Board
UTILITY
Train Enquiry
IRCTC
Matavaishnodevi
BSNL
Jammu Kashmir Bank
State Bank of India
PUBLIC INTEREST
Passport Department
Income Tax Department
JK CAMPA
JK GAD
IT Education
Web Site Design Services
EDUCATION
Jammu University
Jammu University Results
JKBOSE
Kashmir University
IGNOU Jammu Center
SMVDU