Breaking News :   Justice For Terror Victim Families | Kathua Administration welcomes first Batch of Amarnath Yatris at Lakhanpur | Yatra of resilience: LG to flag off first batch today after Pahalgam carnage, Op Sindoor | LG visits Yatri Niwas at Bhagwati Nagar, reviews arrangements | LG reviews final preparations | LG chairs high-level meeting, discusses issues of terror victim families | LG flags off fleet of ambulances in Ramban, Anantnag districts | 5 real brothers from Budgam among fraudulently selected candidates | Hope beneath the surface: Govt plans underground hospital in Poonch | ACB catches DDC member red handed | Crime Branch books J&K Bank officers, others for frauds | Back Issues  
 
news details
DC Jammu reviews progress of works under District Capex Budget, Developmental Deliverables
8/26/2022 10:42:00 PM

EArly Times Report

JAMMU, Aug 26: Deputy Commissioner Avny Lavasa today reviewed the progress of works under District Capex Budget 2022-23 including UT, DDC, BDC, PRI components and status of developmental deliverables in the district.
At the outset, the Deputy Commissioner took a detailed department wise review of the works.
The concerned officers informed the Chair that against 4055 approved works (207 works are under UT component, 274 under BDC, 309 under DDC and 3223 are under PRI component), estimates of 3798 have been prepared and 3123 have been tendered.
It was further apprised that under UT component, out of 207 works, 196 have tendered and 159 have been allotted, while against 3223 PRI component works, estimates of 3049 have been prepared and tenders of 2545 works have already been floated.
Similarly, under the DDC component, out of 309 works, estimates of 289 have been prepared and 216 have been tendered. Under the BDC component, out of 274 works, estimates of 205 have been prepared and 196 have been tendered which shows more than 90% progress.
After taking the work wise review, the DC stressed on the concerned authorities to take all possible measures to accelerate the pace for their time-bound completion.
The Deputy Commissioner asked the officers to ensure speedy allotment, execution and completion of each work.
Later, the Deputy Commissioner chaired a meeting of officers from various departments to review the progress and achievements under developmental deliverables. The officers and heads of departments informed the chair about the progress made and targets realized.
The DC directed the officers to prioritize implementation of developmental deliverables to achieve the targets on time with tangible results on the ground.
CPO Yoginder Katoch, besides the officers from different departments including Health, Education, Jal Shakti, Agriculture, Horticulture, Labour, Employment, Industries, Handloom etc were present in the meeting.
  Share This News with Your Friends on Social Network  
  Comment on this Story  
 
 
 
Early Times Android App
STOCK UPDATE
  
BSE Sensex
NSE Nifty
 
CRICKET UPDATE
 
 
 
 
 
 
 
 
   
Home About Us Top Stories Local News National News Sports News Opinion Editorial ET Cetra Advertise with Us ET E-paper
 
 
J&K RELATED WEBSITES
J&K Govt. Official website
Jammu Kashmir Tourism
JKTDC
Mata Vaishnodevi Shrine Board
Shri Amarnath Ji Shrine Board
Shri Shiv Khori Shrine Board
UTILITY
Train Enquiry
IRCTC
Matavaishnodevi
BSNL
Jammu Kashmir Bank
State Bank of India
PUBLIC INTEREST
Passport Department
Income Tax Department
JK CAMPA
JK GAD
IT Education
Web Site Design Services
EDUCATION
Jammu University
Jammu University Results
JKBOSE
Kashmir University
IGNOU Jammu Center
SMVDU