Breaking News :   New freight train service big step for Kashmir apple growers: LG Sinha | LG attends closing ceremony of ‘Jashn-e-Dal’ | Will take up restoration of Jmu-Sgr highway with Union Minister: CM Omar | Cloudburst triggers flash floods in Reasi, no casualties | Day 21: Vaishno Devi Yatra remains suspended | Fruit growers’ union delegation meets LG | Doda: Educational institutions reopen after 3 weeks | Fraudster impersonating LG’s duty officer held in Rs 50 lakh scam: CBK | PM Modi lays foundation stone of projects worth around Rs 40,000 crore in Bihar | PM Inaugurates 16th armed forces’ conference at Eastern Command HQ | ITR filing deadline ends | DC Budgam calls for stronger enforcement & rehabilitation measures | DYSSO Samba launches major Inter-Zonal Sports tournament | Modi’s Governance: Gujarat Model to Bharatiya Model | Safety of Indians in America | Celebrating National Hindi Diwas | Parcel Train | FICCI FLO JKL rolls out Phase-4 of flood relief efforts in Jammu | Kuch Din Toh Aaiyein Ladakh Mein: LG Kavinder appeals in Navi Mumbai | Give your best to steer our nation ahead in growth & development: DyCM | MLA Sham Lal Sharma Pays Tribute to Sir M. Visvesvaraya on Engineers Day | Power shut down in several areas | Parcel cargo train from Kashmir to Adarsh Nagar Delhi flagged off | Javid Dar reviews status of NH-44 restoration | Only Aadhaar-authenticated users can book online general tickets in first 15 mins from Oct 1: Railways | DC Srinagar convenes DLSCC meeting | MLA Poonch, Ajaz Ahmed Jan offer condolences | Pakistan's terror nexus exposed again at UNSC: Gaurav | Randhawa reviews preparations at Bawe Wali Mata Mandir | Itoo flags off Dental Awareness Rally on Oral health hygiene | MLA Arvind Gupta inaugurates long-pending drain work at Rajpura | Boy injured in landmine blast in Anantnag, dies | Indian Army's first exclusive freight train on USBRL marks breakthrough | Punjab police busts cross-border weapon smuggling module with links to Pak | WPI inflation turns positive after 2 months, at 0.52% in August | SC to pass order on Sept 26 in suo motu case over lack of functional CCTVs in police stations | On Engineer's Day GCET Jammu inaugurates two-week induction programme | Crackdown on illegal mining continue on 2nd day | Ramban police recovers 30 lost mobile phones | Ravinder visits rain affected areas of Sunderbani, seeks relief, restorations on war footing | AIIMS Bathinda reaffirms zero tolerance for unethical practices | Indian Army organised interaction with prominent locals, media at Samote | JKEDI launches 3rd batch of Management Development Programs | GDC Bishnah celebrates Hindi Diwas in collaboration with J&K Rashtriya Bhasha Prachar Samiti | YCET conducts Induction Program | CCI raise serious issue of infrastructure crises | GCOE Jammu celebrates Hindi Diwas | MCM celebrates Hindi Diwas with fervour | Dogra Degree College celebrates Hindi Diwas | IIM Jammu hosts valedictory xeremony of Management Development Program on Corporate Governance | 3 cab drivers booked for violating traffic advisory, overcharging | Doda Police urges public to combat fake news, misinformation | PM Modi at 75: A legacy of vision, valor, Nation-Building: Rohiin Chandan | IRCS J&K provides relief material to flood-affected | JKAACL Jammu organizes one day symposium | Principal Secretary, Culture inaugurates hindi Pakhwada at K.L. Saigal Hall | SP North Vivek Shekhar Sharma releases devotional bhajan “Lad Fadeya Mahamai Da” | IGNOU Jammu successfully concludes Swachhata Pakhwada, reaffirming commitment to cleanliness | Back Issues  
 
news details
Plan under implementation to ensure 24×7 power supply in J&K: CM Omar
3/17/2025 11:23:33 PM
Early Times Report

Jammu, Mar 17: Jammu and Kashmir Chief Minister Omar Abdullah on Monday said a well-coordinated plan which includes modernisation works in transmission and distribution system is under implementation to ensure 24×7 power supply to the consumers in the Union Territory. Abdullah also said that no major progress has been achieved in the development of a coal block in Odisha. The coal block was allocated to J&K State Power Development Corporation (JKSPDC) jointly with NTPC in July, 2013 by the Union Ministry of Coal. Of the total estimated geological reserves of 396 MT, 266 MT was allocated to NTPC and 130 MT to JKSPDC.
The chief minister, who is also in-charge of the power ministry, shared the information in a written reply to a question by BJP’s Rajiv Jasrotia in the legislative assembly.
“The department is committed to providing 24/7 reliable, affordable, and high-quality power supply to every household. A well-coordinated plan, taking a holistic view of all key elements of the power supply chain, is under implementation.
“The plan includes development of several generation projects and system upgradation/modernization works in transmission and distribution systems under Tariff Based Competitive Bidding (TBCB) and schemes like Revamped Distribution Sector Scheme (RDSS), with a target completion by 2027-28,” Abdullah said.
He said major hydro projects, namely Pakal Dul, Kiru, Kwar, and Ratle are progressing fast and are expected to collectively add over 3,000 MW in installed capacity after their commissioning by 2027.
In addition, new projects such as 390 MW Kirthai-I, 258 MW Dulhasti-II, 800 MW Bursar, 1,856 MW Sawalkote, 240 MW Uri-I Stage-II, 89 MW Ujh, and 930 MW Kirthal-II are also planned for completion within the next 10 years, he said.
To meet growing demand, he said, efforts are being made to create a balanced energy mix, including hydro, thermal, and renewable sources of energy, through creation of own generating stations and entering into Power Purchase Agreements with outside generators.
He said a resource adequacy plan has been formulated with the help of central government, taking into consideration future load projections and peak demand for the next 10 years.
To create adequate transmission infrastructure for the evacuation of power from upcoming projects, enhance peak load handling capacity, and support growing demand, the transmission system is being improved, Abdullah said.
Under the plan, he said, the department aims to add around 2,406 MVA (at 220 & 132 kV levels) through setting up of new grid substations and the augmentation of existing grid substations in Jammu region.
Similarly, in the Kashmir region, around 2,500 MVA capacity is targeted to be added at both voltage levels. Additionally, several existing grid stations will be renovated and modernised in a phased manner, he said.
The chief minister said J&K has significant potential for solar energy, and the installation of solar rooftops is being encouraged through the PM Surya Ghar Muft Bijli Yojana.
He said as metering progresses and reaches a larger number of consumers, the government expects significant improvements in power supply, with no power cuts in low-loss areas.
“Such improvements are already evident on feeders where 100 per cent smart metering has been completed — 45 in Kashmir and 50 in Jammu,” he said.
On the coal block in Odisha, he said JKSPDC and NTPC signed the joint venture agreement on June 15, 2015 for exploration, development and operation of the jointly allocated coal mining block.
However, NTPC Limited on November 22, 2018 surrendered its share in the coal block citing reasons like envisaged delay in environmental clearance, non-accessibility to the site along with hostile local environment in nearby areas and the same was accepted by the concerned ministry.
In June, 2019, the J&K government requested the coal ministry for allotment of alternative coal block, in place of Kudanali-Laburi in favour of the NTPC-JKSPDC joint venture company in light of the challenges anticipated in its development, Abdullah said.
However, he said, the request was declined by the ministry of coal citing the reason that there was no provision under MMDR Act, 1957 to allocate an alternate coal block in lieu of a cancelled coal block.
In another written reply to a starred question by NC legislator Mushtaq Ahmad Guroo, the chief minister said a MoU (memorandum of understanding) was signed between JKSPDC and NHPC on January 3, 2021 for the execution of 1,856 MW Sawalkote HEP, 258 MW Dulhasti Stage-II and 240 MW Uri-I stage-II by NHPC in built, own, operate and transfer (BOOT) mode for a period of 40 years.
As per the MoU, the J&K government is entitled to receive 12 per cent free power, one per cent Local Area Development Fund (LADF), first right of refusal for purchase of 50 per cent of power generated at price determined by the regulator.
  Share This News with Your Friends on Social Network  
  Comment on this Story  
 
 
 
Early Times Android App
STOCK UPDATE
  
BSE Sensex
NSE Nifty
 
CRICKET UPDATE
 
 
 
 
 
 
 
 
   
Home About Us Top Stories Local News National News Sports News Opinion Editorial ET Cetra Advertise with Us ET E-paper
 
 
J&K RELATED WEBSITES
J&K Govt. Official website
Jammu Kashmir Tourism
JKTDC
Mata Vaishnodevi Shrine Board
Shri Amarnath Ji Shrine Board
Shri Shiv Khori Shrine Board
UTILITY
Train Enquiry
IRCTC
Matavaishnodevi
BSNL
Jammu Kashmir Bank
State Bank of India
PUBLIC INTEREST
Passport Department
Income Tax Department
JK CAMPA
JK GAD
IT Education
Web Site Design Services
EDUCATION
Jammu University
Jammu University Results
JKBOSE
Kashmir University
IGNOU Jammu Center
SMVDU