Breaking News :   2 national parties fight, 2 regional parties watch: BJP-Congress slogan war rocks Srinagar | Child betrayed in her school’s shadow: Second teacher suspended | Chitta in Khaki: Another woman cop held with Heroin | High Court upholds acquittal of 3 persons | Court cancels anticipatory bail in Rs 93-lakh land fraud case | Protect children’s future, say no to drugs: DGP Prabhat | Frame practical roadmap for mountain development: CM Omar | NIA attaches property used to harbour Pak LeT terrorists | ACB catches official red-handed | HC makes uniform mandatory for clerks | AI, Nuclear and Biological Weapons: A Looming Threat to Humanity’s Survival | Wrapped in Danger: The Silent Poison in Our Takeaway Food | Buyers beware! | Sunder Gems & Jewels Premium Pop-Up inaugurated in Jammu amidst the gracious presence of AWWA members | DG Prosecution J&K addresses prosecution fraternity of UT | J&K DyCM assures swift relief and restoration after record-breaking rains in Jammu | Sakeena Itoo chairs 31st JKWDC Board meeting | Amit Sharma reviews progress of DCHB under Census 2027 across all districts of J&K and Ladakh | Jammu police arrest two persons; Heroin-like substance and illegal weapons recovered by PS Gandhi Nagar | Celebrity singers Aminder Bobby, Chaman lehri enthralled the audience in AIDSC | Biggest accusation of vote theft in India's history lies on Omar Abdullah's family: LoP Sharma | Mamta Yadav assumes charge as Director Information | One day training under IHIP-IDSP of Medical Officers & Medical College doctors held | SKUAST-Jammu's Veterinary Students Embark on North India Educational Tour | 538th Monday theatre at Pacca Talab Jammu | Igniting Aspirations: IIT Jammu hosts students from GDC Kargil, Ladakh | Thapar Institute wins two FICCI Higher Education Excellence Awards 2026 | State Cancer Institute, GMC Jammu Observes Breast Cancer Awareness Day and Organises E-Pledge on Nasha Mukti | Congress has become synonymous with anarchy and disorder in the country: CM | Six SMVDU faculty feature in Stanford's Top 2% Scientists List | Indian Army strengthens Army - Awan connect through Panch & Sarpanch meet at Goha, Doda | MLA Arvind Gupta inaugurates development works worth Rs 70 Lakh in Jammu West | Back Issues  
 
news details
Deadlock over Singhpora–Vailoo tunnel project ends
9/11/2026 10:02:36 PM
Early Times Report

JAMMU, Sept 11: The long-pending Singhpora–Vailoo twin-tube tunnel project under Sinthan Pass is set to move ahead, with the National Highways & Infrastructure Development Corporation Limited (NHIDCL) inviting bids for its construction along the Kishtwar–Vailoo–Khanabal section of National Highway-244 The project, estimated to cost Rs 3,567.51 crore, is aimed at providing an all-weather connectivity link between Kishtwar in the Chenab Valley and Anantnag in south Kashmir, offering an alternative to the treacherous Sinthan Top route that frequently remains closed during winter due to heavy snowfall.
According to a Notice Inviting Bid issued by NHIDCL, the 38.611-km highway package will be executed in Engineering, Procurement and Construction (EPC) mode.
The package includes construction of a 10.331-km left tunnel tube and a 10.363-km right tunnel tube, along with approach roads and other associated infrastructure. The stipulated construction period is 60 months, followed by a 120-month maintenance period.
The project will connect Chhatroo in Kishtwar district with Vailoo in Anantnag district. The eastern approach from Chhatroo to the tunnel portal will cover 17.088 km, while the western approach towards Vailoo will extend for 11.160 km, including the portal section.
The eastern portal, proposed near Singhpora in Kishtwar district, will be located at an elevation of around 2,243 metres, while the western portal at Gadole will be at approximately 2,404 metres.
The tunnel will have a nine-metre carriageway, footpaths and dedicated emergency facilities. The two tubes will be interconnected through cross-passages at intervals of about 500 metres to facilitate pedestrian movement and emergency evacuationv As per the project documents, 20 cross-passages, each 6.1 metres wide and 18.5 metres long, have been proposed.
The tunnel will be equipped with semi-transverse ventilation, fire detection and firefighting systems, CCTV surveillance, emergency communication facilities, traffic-control systems, lighting, drainage and waterproofing arrangements.
Fire hydrants will be installed at intervals of 250 metres, besides hose connections and fire extinguishers at shorter intervals.
The project package also includes construction of approach roads, bridges, viaducts, culverts, drainage systems, safety installations and other ancillary works.
A total of 21 major and minor bridges, viaducts and viaduct-cum-bridge structures have been proposed, with the longest being a 1,345-metre viaduct at design chainage 139+660.
The approach roads will be developed as two-lane highways with paved shoulders. The project also provides for roadside and catch drains extending over 26 km and 28 km, respectively.
  Share This News with Your Friends on Social Network  
  Comment on this Story  
 
 
 
Early Times Android App
STOCK UPDATE
 
 
 
 
 
 
 
   
Home About Us Top Stories Local News National News Sports News Opinion Editorial ET Cetra Advertise with Us ET E-paper
 
 
J&K RELATED WEBSITES
J&K Govt. Official website
Jammu Kashmir Tourism
JKTDC
Mata Vaishnodevi Shrine Board
Shri Amarnath Ji Shrine Board
Shri Shiv Khori Shrine Board
UTILITY
Train Enquiry
IRCTC
Matavaishnodevi
BSNL
Jammu Kashmir Bank
State Bank of India
PUBLIC INTEREST
Passport Department
Income Tax Department
JK CAMPA
JK GAD
IT Education
Web Site Design Services
EDUCATION
Jammu University
Jammu University Results
JKBOSE
Kashmir University
IGNOU Jammu Center
SMVDU