Breaking News :   World Red Cross Day | ‘Ensure maximum participation of displaced KP voters’ | 6 months on, Sarthal remains without electricity | Supreme Court to pass order on interim bail to Delhi CM Arvind Kejriwal on May 10 | Assembly elections after completion of Amarnath Yatra, predicts Farooq | Exploring emotions through art: A therapeutic workshop for Jodhamal teachers | ECI establishes 4 special polling booths | Poonch Attack: CCTV footage of suspected terrorists surfaces | Search operation enters 5th day | Eyewitness shares chilling details | CS reviews progress on vision document for accelerating employment through entrepreneurship | Div Com Jammu chairs Civil Military Liaison meeting | Suspension not a punishment: CAT | ACB files case against PWD officers | Salman Khan house firing case: Two `shooters' sent in judicial custody | Panels framed for challaning | Police raid houses of drug peddlers | MeT predicts light rains | Vikram Randhawa, Moulana Syed appealed to vote for BJP at Kargil | 51-year-old passenger arrested for smoking on Vistara flight to Mumbai | RBI asks non-banks to stick to Rs 20,000 loan cash payout limit: Report | CBI arrests 4 men for trafficking Indians to Russia-Ukraine war zone | Intramural Competition kicks off in Kishtwar District | DC Rajouri reviews implementation of BBBP; functioning of One-Stop Centre, DHEW, CWC & JJB | Nehru, Congress wasted India's crucial time by implementing 'under par' policies: Kavinder | SSP holds crime/security review meeting at DPL | Dr Darakhshan Andrabi Advocates for Peace, Morality at Imam Conference | Crackdown on illegal mining, 4 vehicles seized | Police introduces GPS tracker anklets to monitor bailed out criminals | CAT issues stern warning: Uphold judicial orders or face coercive action | Man injured in bear attack at Konibal | ECPFWA appoints new office bearers | Police Traces out Missing youth, reunites with family | Police Traces out Missing youth, reunites with family | Police rescues 32 bovines, seizes 3 vehicles | Bovine smuggling bid foiled, 2 bovines, 1 vehicle seized | Commemorative event marks World Red Cross Day in Jammu | Cyber Cell recovered money amount to Rs 1,55,000 | 5 dumpers seized by J&K police for illegal mining | LPU hosts mega reunion: Thousands of LPU alumni relive cherished campus memories | District Jammu hosts Inter-School Judo Competition | GDC RS Pura commemorates World Red Cross Day | GDC Ramgarh organizes one-day awareness lecture | KIIT-DU & KPIT Technologies announce strategic partnership with launch of co-branded MTech programme | GDC Vijaypur organises Lecture on Rabindra Nath Tagore: A Naturalist Philosopher | Condolences pour in for late Haji Basheer Naseem Choudhary | Back Issues  
 
news details
Former PHE mantri's interference causes damage to Tawi Barrage
Project likely to miss set deadline
2/12/2018 11:09:25 PM
Arun Singh
Early Times Report
Jammu, Feb 12: The alleged change in original design of Auto Mechanically Gate Barrage project in River Tawi by Irrigation and Flood Control Department on the direction of a former PHE Minister to save his land adjacent to the project site from inundation, caused huge damage to the under construction project and also delayed its completion which was scheduled to happen on March 31, 2018.
The Government had formed a committee in 2017 to ascertain reasons for repeated damage caused to the construction of Auto Mechanical Operated Gate Barrage (Wadi Tawi, Nikki Tawi) at Belicharana, Jammu.
The committee during its inspection showed resentment and observed that the collapse of curved barrage due to the devastating floods of 2014 and construction of the dumping site under the direction of the former PHE Minister whose land is situated adjacent to the barrage to prevent his land for inundation resulted in the collapse of the curved barrage.
During inspection, the committee was informed by the officials of the department that as per the approved design 70% water was supposed to flow from Wadi Tawi and 30% from Nikki Tawi. On the contrary after the construction of said dumping site, 70% of water flows from Nikki Tawi and 30% from Wadi Tawi.
It further said that the project was comprised of thirty one gates, eleven in Wadi Tawi, twenty in Nikki Tawi, which was approved in the year 2010 and the date of completion was set as March 31, 2018 as per the approved designs having length of 370 mtr and height 4 mtr with sluice gates across River Tawi at an estimated cost of Rs 70 Cr. It was further added that in the year 2016, the work on the project was stopped due to onset of monsoon resulting in inordinate delay while executing the construction work. He further added that 80 % would be completed in the year 2018. The Ministry of Water Resources Government of India under AIBP had allotted the funds under 13th Finance Commission. The project of executed as per the approved design and specification after observing all the Codal formalities.
Undue interference of former PHE minister has delayed completion of Tawi Barrage and also delayed its completion.
  Share This News with Your Friends on Social Network  
  Comment on this Story  
 
 
 
Early Times Android App
STOCK UPDATE
  
BSE Sensex
NSE Nifty
 
CRICKET UPDATE
 
 
 
 
 
 
 
 
   
Home About Us Top Stories Local News National News Sports News Opinion Editorial ET Cetra Advertise with Us ET E-paper
 
 
J&K RELATED WEBSITES
J&K Govt. Official website
Jammu Kashmir Tourism
JKTDC
Mata Vaishnodevi Shrine Board
Shri Amarnath Ji Shrine Board
Shri Shiv Khori Shrine Board
UTILITY
Train Enquiry
IRCTC
Matavaishnodevi
BSNL
Jammu Kashmir Bank
State Bank of India
PUBLIC INTEREST
Passport Department
Income Tax Department
JK CAMPA
JK GAD
IT Education
Web Site Design Services
EDUCATION
Jammu University
Jammu University Results
JKBOSE
Kashmir University
IGNOU Jammu Center
SMVDU